CCLME.ORG - 40 CFR PART 35—STATE AND LOCAL ASSISTANCE
Loading (50 kb)...'
(continued)
top
Each construction contract must include the “Supplemental General Conditions” set forth in appendix C–2 to this subpart.

§ 35.938-9 Subcontracts under construction contracts.
top
(a) The award or execution of subcontracts by a prime contractor under a construction contract awarded to the prime contractor by the grantee, and the procurement and negotiation procedures used by prime contractors in awarding or executing subcontracts are not required to comply with any of the provisions, selection procedures, policies or principles set forth in §35.936 or §35.938 except those specifically stated in this section. In addition, the bid protest procedures of §35.939 are not available to parties executing subcontracts with prime contractors except as specifically provided in that section.

(b) The award or execution of subcontracts by a prime contractor under a formally advertised, competitively bid, fixed price construction contract awarded to the prime contractor by the grantee, and the procurement and negotiation procedures used by such prime contractors in awarding or executing such subcontracts must comply with the following:

(1) Section 35.936–2 (Grantee procurement systems; State or local law);

(2) Section 35.936–7 (Small and minority business);

(3) Section 35.936–13 (Specifications);

(4) Section 35.936–15 (Limitations on subagreement award);

(5) Section 35.936–17 (Fraud and other unlawful or corrupt practices);

(6) Section 35.938–5(d) (Negotiation of contract amendments); and

(7) Applicable subagreement clauses (see appendix C–2, clauses 8, 10, 14, 15, 16; note clause 11).

(c) The award of subcontracts under construction contracts not described above in paragraph (b) of this section and the procurement and negotiation procedures of prime contractors on contracts not meeting that description must comply with paragraphs (b)(1) through (4) of this section as well as the principles of §35.938–5.

§ 35.939 Protests.
top
(a) General. A protest based upon an alleged violation of the procurement requirements of §§35.936 through 35.938–9 of this subpart may be filed against a grantee's procurement action by a party with an adversely affected direct financial interest. Any such protest must be received by the grantee within the time period in paragraph (b)(1) of this section. The grantee is responsible for resolution of the protest before the taking of the protested action, in accordance with paragraph (d) of this section, except as otherwise provided by paragraph (j) or (k) or §35.938–4(h)(5). The Regional Administrator will review grantee protest determinations in accordance with paragraph (e) of this section, if a timely request for such review is filed under paragraph (b)(2) of this section. In the case of protests which he determines are untimely, frivolous, or without merit, the Regional Administrator may take such actions as are described in paragraphs (f)(7), (i)(2), and (k) of this section.

(b) Time limitations. (1) A protest under paragraph (d) of this section should be made as early as possible during the procurement process (for example, immediately after issuance of a solicitation for bids) to avoid disruption of or unnecessary delay to the procurement process. A protest authorized by paragraph (d) of this section must be received by the grantee within 1 week after the basis for the protest is known or should have been known, whichever is earlier (generally, for formally advertised procurement, after bid opening, within 1 week after the basis for the protest is, or should have been, known).

(i) However, in the case of an alleged violation of the specification requirements of §35.936–13 (e.g., that a product fails to qualify as an “or equal”) or other specification requirements of this subpart, a protest need not be filed prior to the opening of bids. But the grantee may resolve the issue before receipt of bids or proposals through a written or other formal determination, after notice and opportunity to comment is afforded to any party with a direct financial interest.

(ii) In addition, where an alleged violation of the specification requirements of §35.936–13 or other requirements of this subpart first arises subsequent to the receipt of bids or proposals, the grantee must decide the protest if the protest was received by the grantee within 1 week of the time that the grantee's written or other formal notice is first received.

(2) A protest appeal authorized by paragraph (e) of this section must be received by the Regional Administrator within 1 week after the complainant has received the grantee's determination.

(3) If a protest is mailed, the complaining party bears the risk of nondelivery within the required time period. It is suggested that all documents transmitted in accordance with this section be mailed by certified mail (return receipt requested) or otherwise delivered in a manner which will objectively establish the date of receipt. Initiation of protest actions under paragraph (d) or (e) of this section may be made by brief telegraphic notice accompanied by prompt mailing or other delivery of a more detailed statement of the basis for the protest. Telephonic protests will not be considered.

(c) Other initial requirements. (1) The initial protest document must briefly state the basis for the protest, and should—

(i) Refer to the specific section(s) of this subpart which allegedly prohibit the procurement action;

(ii) Specifically request a determination pursuant to this section;

(iii) Identify the specific procurement document(s) or portion(s) of them in issue; and

(iv) Include the name, telephone number, and address of the person representing the protesting party.

(2) The party filing the protest must concurrently transmit a copy of the initial protest document and any attached documentation to all other parties with a direct financial interest which may be adversely affected by the determination of the protest (generally, all bidders or proposers who appear to have a substantial and reasonable prospect of receiving an award if the protest is denied or sustained) and to the appropriate EPA Regional Administrator.

(d) Grantee determination. (1) The grantee is responsible for the initial resolution of protests based upon alleged violations of the procurement requirements of this subpart.

(2) When the grantee receives a timely written protest, he must defer the protested procurement action (see paragraph (h) of this section) and:

(i) Afford the complaining party and interested parties an opportunity to present arguments in support of their views in writing or at a conference or other suitable meeting (such as a city council meeting),

(ii) Inform the complainant and other interested parties of the procedures which the grantee will observe for resolution of the protest;

(iii) Obtain an appropriate extension of the period for acceptance of the bid and bid bond(s) of each interested party, where applicable; failure to agree to a suitable extension of such bid and bid bond(s) by the party which initiated the protest shall be cause for summary dismissal of the protest by the grantee or the Regional Administrator; and

(iv) Promptly deliver (preferably by certified mail, return receipt requested, or by personal delivery) its written determination of the protest to the complaining party and to each other participating party.

(3) The grantee's determination must be accompanied by a legal opinion addressing issues arising under State, territorial, or local law (if any) and, where step 3 construction is involved, by an engineering report, if appropriate.

(4) The grantee should decide the protest as promptly as possible—generally within 3 weeks after receipt of a protest, unless extenuating circumstances require a longer period of time for proper resolution of the protest.

(e) Regional Administrator review. (1) A party with a direct financial interest adversely affected by a grantee determination made under paragraph (d) with respect to a procurement requirement of this subpart may submit a written request to the Regional Administrator for his review of such determination. Any such request must be in writing, must adequately state the basis for the protest (including reference to the specific section(s) of this subpart alleged to prohibit the procurement action), and must be received by the Regional Administrator within 1 week after the complaining party has received the grantee's determination of the protest. A copy of the grantee's determination and other documentation in support of the request for review shall be transmitted with the request.

(2) The Regional Counsel or his delegee will afford both the grantee and the complaining party, as well as any other party with a financial interest which may be adversely affected by determination of the protest, an opportunity to present arguments in support of their views in writing or at a conference at a time and place convenient to the parties as determined by the Regional Counsel or his delegee, and he shall thereafter promptly submit in writing his report and recommendations (or recommended determination) concerning the protest to the Regional Administrator.

(3) Any such conference should be held within not more than 10 days after receipt of the request for review and the report should be transmitted to the Regional Administrator within 10 days after the date set for receipt of the participants' written materials or for the conference. The Regional Administrator should transmit his determination of the protest with an adequate explanation thereof to the grantee and simultaneously to each participating party within 1 week after receipt of the report and recommendations. His determination shall constitute final agency action, from which there shall be no further administrative appeal. The Regional Counsel may extend these time limitations, where appropriate.

(4) The Regional Administrator may review the record considered by the grantee, and any other documents or arguments presented by the parties, to determine whether the grantee has complied with this subpart and has a rational basis for its determination.

(5) If a determination is made by the Regional Administrator which is favorable to the complainant, the grantee's procurement action (for example, contract award) must be taken in accordance with such determination.

(f) Procedures. (1) Where resolution of an issue properly raised with respect to a procurement requirement of this subpart requires prior or collateral resolution of a legal issue arising under State or local law, and such law is not clearly established in published legal decisions of the State or other relevant jurisdiction, the grantee or Regional Administrator may rely upon:

(i) An opinion of the grantee's legal counsel adequately addressing the issue (see §35.936–2(b));

(ii) The established or consistent practice of the grantee, to the extent appropriate; or

(iii) The law of other States or local jurisdictions as established in published legal decisions; or

(iv) If none of the foregoing adequately resolve the issue, published decisions of the Comptroller General of the United States (U.S. General Accounting Office) or of the Federal courts addressing Federal requirements comparable to procurement requirements of this subpart.

(2) For the determination of Federal issues presented by the protest, the Regional Administrator may rely upon:

(i) Determinations of other protests decided under this section, unless such protests have been reversed; and

(ii) Decisions of the Comptroller General of the United States or of the Federal courts addressing Federal requirements comparable to procurement requirements of this subpart.

(3) The Regional Counsel may establish additional procedural requirements or deadlines for the submission of materials by parties or for the accomplishment of other procedures. Where time limitations are established by this section or by the Regional Counsel, participants must seek to accomplish the required action as promptly as possible in the interest of expediting the procurement action.

(4) A party who submits a document subsequent to initiation of a protest proceeding under paragraph (d) or (e) of this section must simultaneously furnish each other party with a copy of such document.

(5) The procedures established by this section are not intended to preclude informal resolution or voluntary withdrawal of protests. A complainant may withdraw its appeal at any time, and the protest proceeding shall thereupon be terminated.

(6) The Regional Administrator may utilize appropriate provisions of this section in the discharge of his responsibility to review grantee procurement under 40 CFR 35.935–2.

(7) A protest may be dismissed for failure to comply with procedural requirements of this section.

(g) Burden of proof. (1) In proceedings under paragraphs (d) and (e) of this section, if the grantee proposes to award a formally advertised, competitively bid, fixed price contract to a party who has submitted the apparent lowest price, the party initiating the protest will bear the burden of proof in the protest proceedings.

(2) In the proceedings under paragraph (e) of this section—

(i) If the grantee proposes to award a formally advertised, competitively bid, fixed-price contract to a bidder other than the bidder which submitted the apparent lowest price, the grantee will bear the burden of proving that its determination concerning responsiveness is in accordance with this subchapter; and

(ii) If the basis for the grantee's determination is a finding of nonresponsibility, the grantee must establish and substantiate the basis for its determination and must adequately establish that such determination has been made in good faith.coverage) as is required by State or local law or the grantee or as is customary and appropriate. Under the Flood Disaster Protection Act of 1973, a contractor must purchase flood insurance to cover his risk of loss if the grantee has not purchased the insurance (see §30.405–10 of this subchapter).

§ 35.940 Determination of allowable costs.
top
The grantee will be paid, upon request in accordance with §35.945, for the Federal share of all necessary costs within the scope of the approved project and determined to be allowable in accordance with §30.705 of this chapter, this subpart, and the grant agreement.

§ 35.940-1 Allowable project costs.
top
Allowable costs include:

(a) Costs of salaries, benefits, and expendable material the grantee incurs for the project, except as provided in §35.940–2(g);

(b) Costs under construction contracts;

(c) Professional and consultant services;

(d) Facilities planning directly related to the treatment works;

(e) Sewer system evaluation (§35.927);

(f) Project feasibility and engineering reports;

(g) Costs required under the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (42 U.S.C. 4621 et seq., 4651 et seq.), and part 4 of this chapter;

(h) Costs of complying with the National Environmental Policy Act, including costs of public notices and hearings;

(i) Preparation of construction drawings, specifications, estimates, and construction contract documents;

(j) Landscaping;

(k) Removal and relocation or replacement of utilities, for which the grantee is legally obligated to pay;

(l) Materials acquired, consumed, or expended specifically for the project;

(m) A reasonable inventory of laboratory chemicals and supplies necessary to initiate plant operations;

(n) Development and preparation of an operation and maintenance manual;

(o) A plan of operation, in accordance with guidance issued by the Administrator;

(p) Start-up services for new treatment works, in accordance with guidance issued by the Administrator;

(q) Project identification signs (§30.625–3 of this chapter);

(r) Development of a municipal pretreatment program approvable under part 403 of this chapter, and purchase of monitoring equipment and construction of facilities to be used by the municipal treatment works in the pretreatment program;

(s) Costs of complying with the procurement requirements of these regulations (see §35.936–20).

(t) Reasonable costs of public participation incurred by grantees which are identified in a public participation work plan, or which are otherwise approved by EPA, shall be allowable.

[43 FR 44049, Sept. 27, 1978, as amended at 44 FR 10304, Feb. 16, 1979]

§ 35.940-2 Unallowable costs.
top
Costs which are not necessary for the construction of a treatment works project are unallowable. Such costs include, but are not limited to:

(a) Basin or areawide planning not directly related to the project;

(b) Bonus payments not legally required for completion of construction before a contractual completion date;

(c) Personal injury compensation or damages arising out of the project, whether determined by adjudication, arbitration, negotiation, or otherwise;

(d) Fines and penalties due to violations of, or failure to comply with, Federal, State, or local laws;

(e) Costs outside the scope of the approved project;

(f) Interest on bonds or any other form of indebtedness required to finance the project costs;

(g) Ordinary operating expenses of local government, such as salaries and expenses of a mayor, city council members, or city attorney, except as provided in §35.940–4;

(h) Site acquisition (for example, sewer rights-of-way, sewage treatment plantsite, sanitary landfills and sludge disposal areas) except as otherwise provided in §35.940–3(a);

(i) Costs for which payment has been or will be received under another Federal assistance program;

(j) Costs of equipment or material procured in violation of §35.938–4(h);

(k) Costs of studies under §35.907 (d)(6) and (7) when performed solely for the purpose of seeking an allowance for removal of pollutants under part 403 of this chapter;

(l) Costs of monitoring equipment used by industry for sampling and analysis of industrial discharges to municipal treatment works;

(m) Construction of privately-owned treatment works, including pretreatment facilities, except as authorized by section 201(h) of the Act and §35.918;

(n) Preparation of a grant application, including a plan of study.

§ 35.940-3 Costs allowable, if approved.
top
Certain direct costs are sometimes necessary for the construction of a treatment works. The following costs are allowable if reasonable and if the Regional Administrator approves them in the grant agreement.

(a) Land acquired after October 17, 1972, that will be an integral part of the treatment process, or that will be used for ultimate disposal of residues resulting from such treatment (for example, land for spray irrigation of sewage effluent).

(b) Land acquired after December 26, 1977, that will be used for storage of treated wastewater in land treatment systems before land application.

(c) Land acquired after December 26, 1977, that will be used for composting or temporary storage of compost residues which result from wastewater treatment, if EPA has approved a program for use of the compost.

(d) Acquisition of an operable portion of a treatment works. This type of acquisition is generally not allowable except when determined by the Regional Administrator in accordance with guidance issued by the Administrator.

(e) Rate determination studies required under §35.925–11.

(f) A limited amount of end-of-pipe sampling and associated analysis of industrial discharges to municipal treatment works as provided in §35.907(f).

§ 35.940-4 Indirect costs.
top
Indirect costs shall be allowable in accordance with an indirect cost agreement negotiated and incorporated in the grant agreement. An indirect cost agreement must identify those cost elements allowable under §35.940–1. Where the benefits derived from indirect services cannot be readily determined, a lump sum for overhead may be negotiated if EPA determines that this amount will be approximately the same as the actual indirect costs.

§ 35.940-5 Disputes concerning allowable costs.
top
The grantee should seek to resolve any questions relating to cost allowability or allocation at its earliest opportunity (if possible, before execution of the grant agreement). Final determinations concerning the allowability of costs shall be conclusive unless appealed within 30 days in accordance with the “Disputes” provisions of part 30, subpart J, of this subchapter.

§ 35.945 Grant payments.
top
The grantee shall be paid the Federal share of allowable project costs incurred within the scope of an approved project and which are currently due and payable from the grantee (i.e., not including withheld or deferred amounts), subject to the limitations of §§35.925–18, 35.930–5, 35.930–6, and 35.965 (b) and (c), up to the grant amount set forth in the grant agreement and any amendments thereto. Payments for engineering services for step 1, 2 or 3 shall be made in accordance with §35.937–10 and payments for step 3 construction contracts shall be made in accordance with §§35.938–6 and 35.938–7. All allowable costs incurred before initiation of construction of the project must be claimed in the application for grant assistance for that project before the award of the assistance or no subsequent payment will be made for the costs.

(a) Initial request for payment. Upon award of grant assistance, the grantee may request payment for the unpaid Federal share of actual or estimated allowable project costs incurred before grant award subject to the limitations of §35.925–18. Payment for such costs shall be made in accordance with the negotiated payment schedule included in the grant agreement.

(b) Interim requests for payment. The grantee may submit requests for payments for allowable costs in accordance with the negotiated payment schedule included in the grant agreement. Upon receipt of a request for payment, subject to the limitations set forth in §30.615–3 of this subchapter and §§35.935–12, 35.935–13, and 35.935–16, the Regional Administrator shall cause to be disbursed from available appropriated funds such amounts as are necessary so that the total amount of Federal payments to the grantee for the project is equal to the Federal share of the actual or estimated allowable project costs incurred to date, as certified by the grantee in its most recent request for payment. Generally, payments will be made within 20 days after receipt of a request for payment.

(c) Adjustment. At any time before final payment under the grant, the Regional Administrator may cause any request(s) for payment to be reviewed or audited. Based on such review or audit, any payment may be reduced for prior overpayment or increased for prior underpayment.

(d) Refunds, rebates, credits, etc. The Federal share of any refunds, rebates, credits, or other amounts (including any interest) that accrue to or are received by the grantee for the project, and that are properly allocable to costs for which the grantee has been paid under a grant, must be credited to the current State allotment or paid to the United States. Reasonable expenses incurred by the grantee for the purpose of securing such refunds, rebates, credits, or other amounts shall be allowable under the grant when approved by the Regional Administrator.

(e) Final payment. After completion of final inspection under §35.935–14, approval of the request for payment which the grantee designates as the “final payment request,” and the grantee's compliance with all applicable requirements of this subchapter and the grant agreement, the Regional Administrator shall pay to the grantee any balance of the Federal share of allowable project costs which has not already been paid. The grantee must submit the final payment request promptly after final inspection.

(f) Assignment and release. By its acceptance of final payment, the grantee agrees to assign to the United States the Federal share of refunds, rebates, credits or other amounts (including any interest) properly allocable to costs for which the grantee has been paid by the Government under the grant. The grantee thereby also releases and discharges the United States, its officers, agents, and employees from all liabilities, obligations, and claims arising out of the project work or under the grant, subject only to exceptions previously specified in writing between the Regional Administrator and the grantee.

(g) Payment of costs incurred under the Uniform Relocation Assistance and Real Property Acquisition Policies Act. Notwithstanding the provisions of paragraph (a) of this section, if the Regional Administrator determines it is necessary for the expeditious completion of a project, he may make advance payment after grant award under §4.502(c) of this subchapter for the EPA share of the cost of any payment of relocation assistance by the grantee. The requirements in §30.615–1 (b) and (d) of this subchapter apply to any advances of funds for assistance payments.

[43 FR 44049, Sept. 27, 1978, as amended at 44 FR 39340, July 5, 1979]

§ 35.950 Suspension, termination or annulment of grants.
top
Grants may be suspended under §30.915, or terminated or annulled under §30.920. The State agency shall be concurrently notified in writing of any such action.

§ 35.955 Grant amendments to increase grant amounts.
top
Grant agreements may be amended under §30.900–1 of this chapter for project changes which have been approved under §§30.900 and 35.935–11 of this subchapter. However, no grant agreement may be amended to increase the amount of a grant unless the State agency has approved the grant increase from available State allotments and reallotments under §35.915.

§ 35.960 Disputes.
top
(a) The Regional Administrator's final determination on the ineligibility of a project (see §35.915(h)) or a grant applicant (see §35.920–1), on the Federal share (see §35.930–5(b)), or on any dispute arising under a grant shall be final and conclusive unless the applicant or grantee appeals within 30 days from the date of receipt of the final determination. (See subpart J of part 30 of this subchapter.)

(b) The EPA General Counsel will publish periodically as a Notice document in the Federal Register a digest of grant appeals decisions.

§ 35.965 Enforcement.
top
If the Regional Administrator determines that the grantee has failed to comply with any provision of this subpart, he may impose any of the following sanctions:

(a) The grant may be terminated or annulled under §30.920 of this subchapter;

(b) Project costs directly related to the noncompliance may be disallowed;

(c) Payment otherwise due to the grantee of up to 10 percent may be withheld (see §30.615–3 of this chapter);

(d) Project work may be suspended under §30.915 of this subchapter;

(e) A noncomplying grantee may be found nonresponsible or ineligible for future Federal assistance or a noncomplying contractor may be found nonresponsible or ineligible for approval for future contract award under EPA grants;

(f) An injunction may be entered or other equitable relief afforded by a court of appropriate jurisdiction;

(g) Such other administrative or judicial action may be instituted if it is legally available and appropriate.

§ 35.970 Contract enforcement.
top
(a) Regional Administrator authority. At the request of a grantee, the Regional Administrator is authorized to provide technical and legal assistance in the administration and enforcement of any contract related to treatment works for which an EPA grant was made and to intervene in any civil action involving the enforcement of such contracts, including contract disputes which are the subject of either arbitration or court action. Any assistance is to be provided at the discretion of the Regional Administrator and in a manner determined to best serve the public interest. Factors which the Regional Administrator may consider in determining whether to provide assistance are:

(1) Available agency resources.

(2) Planned or ongoing enforcement action.

(3) The grantee's demonstration of good faith to resolve contract matters at issue.

(4) The grantee's adequate documentation.

(5) The Federal interest in the contract matters at issue.

(b) Grantee request. The grantee's request for technical or legal assistance should be submitted in writing and be accompained by documentation adequate to inform the Regional Administrator of the nature and necessity of the requested assistance. A grantee may orally request assistance from the Regional Administrator on an emergency basis.

(c) Privity of contract. The Regional Administrator's technical or legal involvement in any contract dispute will not make EPA a party to any contract entered into by the grantee. (See §35.936–8.)

(d) Delegation to States. The authority to provide technical and legal assistance in the administration of contract matters described in this section may be delegated to a State agency under subpart F of this part if the State agency can demonstrate that it has the appropriate legal authority to undertake such functions.

Appendix A to Subpart E of Part 35—Cost-Effectiveness Analysis Guidelines
top
1. Purpose. These guidelines represent Agency policies and procedures for determining the most cost-effective waste treatment management system or component part.

2. Authority. These guidelines are provided under sections 212(2)(C) and 217 of the Clean Water Act.

3. Applicability. These guidelines, except as otherwise noted, apply to all facilities planning under step 1 grant assistance awarded after September 30, 1978. The guidelines also apply to State or locally financed facilities planning on which subsequent step 2 or step 3 Federal grant assistance is based.

4. Definitions. Terms used in these guidelines are defined as follows:

a. Waste treatment management system. Used synonymously with “complete waste treatment system” as defined in §35.905 of this subpart.

b. Cost-effectiveness analysis. An analysis performed to determine which waste treatment management system or component part will result in the minimum total resources costs over time to meet Federal, State, or local requirements.

c. Planning period. The period over which a waste treatment management system is evaluated for cost-effectiveness. The planning period begins with the system's initial operation.

d. Useful life. The estimated period of time during which a treatment works or a component of a waste treatment management system will be operated.

e. Disaggregation. The process or result of breaking down a sum total of population or economic activity for a State or other jurisdiction (i.e., designated 208 area or SMSA) into smaller areas or jurisdictions.

5. Identification, selection, and screening of alternatives. a. Identification of alternatives. All feasible alternative waste management systems shall be initially identified. These alternatives should include systems discharging to receiving waters, land application systems, on-site and other non-centralized systems, including revenue generating applications, and systems employing the reuse of wastewater and recycyling of pollutants. In identifying alternatives, the applicant shall consider the possibility of no action and staged development of the system.

b. Screening of alternatives. The identified alternatives shall be systematically screened to determine those capable of meeting the applicable Federal, State and local criteria.

c. Selection of alternatives. The identified alternatives shall be initially analyzed to determine which systems have cost-effective potential and which should be fully evaluated according to the cost-effectiveness analysis procedures established in the guidelines.

d. Extent of effort. The extent of effort and the level of sophistication used in the cost-effectiveness analysis should reflect the project's size and importance. Where processes or techniques are claimed to be innovative technology on the basis of the cost reduction criterion contained in paragraph 6e(1) of appendix E to this subpart, a sufficiently detailed cost analysis shall be included to substantiate the claim to the satisfaction of the Regional Administrator.

6. Cost-effectiveness analysis procedures.

a. Method of analysis. The resources costs shall be determined by evaluating opportunity costs. For resources that can be expressed in monetary terms, the analysis will use the interest (discount) rate established in paragraph 6e. Monetary costs shall be calculated in terms of present worth values or equivalent annual values over the planning period defined in section 6b. The analysis shall descriptively present nonmonetary factors (e.g., social and environmental) in order to determine their significance and impact. Nonmonetary factors include primary and secondary environmental effects, implementation capability, operability, performance reliability and flexibility. Although such factors as use and recovery of energy and scarce resources and recycling of nutrients are to be included in the monetary cost analysis, the non-monetary evaluation shall also include them. The most cost-effective alternative shall be the waste treatment management system which the analysis determines to have the lowest present worth or equivalent annual value unless nonmonetary costs are overriding. The most cost-effective alternative must also meet the minimum requirements of applicable effluent limitations, groundwater protection, or other applicable standards established under the Act.

b. Planning period. The planning period for the cost-effectiveness analysis shall be 20 years.

c. Elements of monetary costs. The monetary costs to be considered shall include the total value of the resources which are attributable to the waste treatment management system or to one of its component parts. To determine these values, all monies necessary for capital construction costs and operation and maintenance costs shall be identified.

(1) Capital construction costs used in a cost-effective analysis shall include all contractors' costs of construction including overhead and profit, costs of land, relocation, and right-of-way and easement acquisition; costs of design engineering, field exploration and engineering services during construction; costs of administrative and legal services including costs of bond sales; startup costs such as operator training; and interest during construction. Capital construction costs shall also include contingency allowances consistent with the cost estimate's level of precision and detail.

(2) The cost-effectiveness analysis shall include annual costs for operation and maintenance (including routine replacement of equipment and equipment parts). These costs shall be adequate to ensure effective and dependable operation during the system's planning period. Annual costs shall be divided between fixed annual costs and costs which would depend on the annual quantity of waste water collected and treated. Annual revenues generated by the waste treatment management system through energy recovery, crop production, or other outputs shall be deducted from the annual costs for operation and maintenance in accordance with guidance issued by the Administrator.

d. Prices. The applicant shall calculate the various components of costs on the basis of market prices prevailing at the time of the cost-effectiveness analysis. The analysis shall not allow for inflation of wages and prices, except those for land, as described in paragraph 6h(1) and for natural gas. This stipulation is based on the implied assumption that prices, other than the exceptions, for resources involved in treatment works construction and operation, will tend to change over time by approximately the same percentage. Changes in the general level of prices will not affect the results of the cost-effectiveness analysis. Natural gas prices shall be escalated at a compound rate of 4 percent annually over the planning period, unless the Regional Administrator determines that the grantee has justified use of a greater or lesser percentage based upon regional differentials between historical natural gas price escalation and construction cost escalation. Land prices shall be appreciated as provided in paragraph 6h(1). Both historical data and future projections support the gas and land price escalations relative to those for other goods and services related to waste water treatment. Price escalation rates may be updated periodically in accordance with Agency guidelines.

e. Interest (discount) rate. The rate which the Water Resources Council establishes annually for evaluation of water resource projects shall be used.

f. Interest during construction. (1) Where capital expenditures can be expected to be fairly uniform during the construction period, interest during construction may be calculated at I=1/2PCi where:

I=the interest accrued during the construction period,

P=the construction period in years,

C=the total capital expenditures,

i=the interest rate (discount rate in section 6e).

(2) Where expenditures will not be uniform, or when the construction period will be greater than 4 years, interest during construction shall be calculated on a year-by-year basis.

g. Useful life. (1) The treatment works' useful life for a cost-effectiveness analysis shall be as follows:

Land—permanent.

Waste water conveyance structures (includes collection systems, outfall pipes, interceptors, force mains, tunnels, etc.)—50 years.

Other structures (includes plant building, concrete process tankage, basins, lift stations structures, etc.)—30–50 years.

Process equipment—15–20 years.

Auxiliary equipment—10–15 years.

(2) Other useful life periods will be acceptable when sufficient justification can be provided. Where a system or a component is for interim service, the anticipated useful life shall be reduced to the period for interim service.

h. Salvage value. (1) Land purchased for treatment works, including land used as part of the treatment process or for ultimate disposal of residues, may be assumed to have a salvage value at the end of the planning period at least equal to its prevailing market value at the time of the analysis. In calculating the salvage value of land, the land value shall be appreciated at a compound rate of 3 percent annually over the planning period, unless the Regional Administrator determines that the grantee has justified the use of a greater or lesser percentage based upon historical differences between local land cost escalation and construction cost escalation. The land cost escalation rate may be updated periodically in accordance with Agency guidelines. Right-of-way easements shall be considered to have a salvage value not greater than the prevailing market value at the time of the analysis.

(2) Structures will be assumed to have a salvage value if there is a use for them at the end of the planning period. In this case, salvage value shall be estimated using straight line depreciation during the useful life of the treatment works.

(3) The method used in paragraph 6h(2) may be used to estimate salvage value at the end of the planning period for phased additions of process equipment and auxiliary equipment.

(4) When the anticipated useful life of a facility is less than 20 years (for analysis of interim facilities), salvage value can be claimed for equipment if it can be clearly demonstrated that a specific market or reuse opportunity will exist.

7. Innovative and alternative wastewater treatment processes and techniques.

a. Beginning October 1, 1978, the capital costs of publicly owned treatment works which use processes and techniques meeting the criteria of appendix E to this subpart and which have only a water pollution control function, may be eligible if the present worth cost of the treatment works is not more than 115 percent of the present worth cost of the most cost-effective pollution control system, exclusive of collection sewers and interceptors common to the two systems being compared, by 115 percent, except for the following situation.

b. Where innovative or alternative unit processes would serve in lieu of conventional unit processes in a conventional waste water treatment plant, and the present worth costs of the nonconventional unit processes are less than 50 percent of the present worth costs of the treatment plant, multiply the present worth costs of the replaced conventional processes by 115 percent, and add the cost of nonreplaced unit processes.

c. The eligibility of multipurpose projects which combine a water pollution control function with another function, and which use processes and techniques meeting the criteria of appendix E to this subpart, shall be determined in accordance with guidance issued by the Administrator.

d. The above provisions exclude individual systems under §35.918. The regional Administrator may allow a grantee to apply the 15-percent preference authorized by this section to facility plans prepared under step 1 grant assistance awarded before October 1, 1978.

8. Cost-effective staging and sizing of treatment works.

a. Population projections. (1) The disaggregation of State projections of population shall be the basis for the population forecasts presented in individual facility plans, except as noted. These State projections shall be those developed in 1977 by the Bureau of Economic Analysis (BEA), Department of Commerce, unless, as of June 26, 1978, the State has already prepared projections. These State projections may be used instead of the BEA projections if the year 2000 State population does not exceed that of the BEA projection by more than 5 percent. If the difference exceeds this amount, the State must either justify or lower its projection. Justification must be based on the historical and current trends (e.g., energy and industrial development, military base openings) not taken into account in the BEA projections. The State must submit for approval to the Administrator the request and justification for use of State projections higher than the BEA projections. By that time, the State shall issue a public notice of the request. Before the Administrator's approval of the State projection, the Regional Administrator shall solicit public comments and hold a public hearing if important issues are raised about the State projection's validity. State projections and disaggregations may be updated periodically in accordance with Agency guidelines.

(2) Each State, working with designated 208 planning agencies, organizations certified by the Governor under section 174(a) of the Clean Air Act, as amended, and other regional planning agencies in the State's nondesignated areas, shall disaggregate the State population projection among its designated 208 areas, other standard metropolitan statistical areas (SMSA's) not included in the 208 area, and non-SMSA counties or other appropriate jurisdictions. States that had enacted laws, as of June 26, 1978, mandating disaggregation of State population totals to each county for areawide 208 planning may retain this requirement. When disaggregating the State population total, the State shall take into account the projected population and economic activities identified in facility plans, areawide 208 plans and municipal master plans. The sum of the disaggregated projections shall not exceed the State projection. Where a designated 208 area has, as of June 26, 1978, already prepared a population projection, it may be used if the year 2000 population does not exceed that of the disaggregated projection by more than 10 percent. The State may then increase its population projection to include all such variances rather than lower the population projection totals for the other areas. If the 208 area population forecast exceeds the 10 percent allowance, the 208 agency must lower its projection within the allowance and submit the revised projection for approval to the State and the Regional Administrator.

(3) The State projection totals and the disaggregations will be submitted as an output of the statewide water quality management process. The submission shall include a list of designated 208 areas, all SMSA's, and counties or other units outside the 208 areas. For each unit the disaggregated population shall be shown for the years 1980, 1990, and 2000. Each State will submit its projection totals and disaggregations for the Regional Administrator's approval before October 1, 1979. Before this submission, the State shall hold a public meeting on the disaggregations and shall provide public notice of the meeting consistent with part 25 of this chapter. (See §35.917(e).)

(4) When the State projection totals and disaggregations are approved they shall be used thereafter for areawide water quality management planning as well as for facility planning and the needs surveys under section 516(b) of the Act. Within areawide 208 planning areas, the designated agencies, in consultation with the States, shall disaggregate the 208 area projections among the SMSA and non-SMSA areas and then disaggregate these SMSA and non-SMSA projections among the facility planning areas and the remaining areas. For those SMSA's not included within designated 208 planning areas, each State, with assistance from appropriate regional planning agencies, shall disaggregate the SMSA projection among the facility planning areas and the remaining areas within the SMSA. The State shall check the facility planning area forecasts to ensure reasonableness and consistency with the SMSA projections.

(5) For non-SMSA facility planning areas not included in designated areawide 208 areas, the State may disaggregate population projections for non-SMSA counties among facility planning areas and remaining areas. Otherwise, the grantee is to forecast future population growth for the facility planning area by linear extrapolation of the recent past (1960 to present) population trends for the planning area, use of correlations of planning area growth with population growth for the township, county or other larger parent area population, or another appropriate method. A population forecast may be raised above that indicated by the extension of past trends where likely impacts (e.g., significant new energy developments, large new industries, Federal installations, or institutions) justify the difference. The facilities plan must document the justification. These population forecasts should be based on estimates of new employment to be generated. The State shall check individual population forecasts to insure consistency with overall projections for non-SMSA counties and justification for any difference from past trends.

(6) Facilities plans prepared under step 1 grant assistance awarded later than 6 months after Agency approval of the State disaggregations shall follow population forecasts developed in accordance with these guidelines.

b. Wastewater flow estimates. (1) In determining total average daily flow for the design of treatment works, the flows to be considered include the average daily base flows (ADBF) expected from residential sources, commercial sources, institutional sources, and industries the works will serve plus allowances for future industries and nonexcessive infiltration/inflow. The amount of nonexcessive infiltration/inflow not included in the base flow estimates presented herein, is to be determined according to the Agency guidance for sewer system evaluation or Agency policy on treatment and control of combined sewer overflows (PRM 75–34).

(2) The estimation of existing and future ADBF, exclusive of flow reduction from combined residential, commercial and institutional sources, shall be based upon one of the following methods:

(a) Preferred method. Existing ADBF is estimated based upon a fully documented analysis of water use records adjusted for consumption and losses or on records of wastewater flows for extended dry periods less estimated dry weather infiltration. Future flows for the treatment works design should be estimated by determining the existing per capita flows based on existing sewered resident population and multiplying this figure by the future projected population to be served. Seasonal population can be converted to equivalent full time residents using the following multipliers:

Day-use visitor 0.1–0.2 Seasonal visitor 0.5–0.8
The preferred method shall be used wherever water supply records or wastewater flow data exist. Allowances for future increases of per capita flow over time will not be approved.

(b) Optional method. Where water supply and wastewater flow data are lacking, existing and future ADBF shall be estimated by multiplying a gallon per capita per day (gpcd) allowance not exceeding those in the following table, except as noted below, by the estimated total of the existing and future resident populations to be served. The tabulated ADBF allowances, based upon several studies of municipal water use, include estimates for commercial and institutional sources as well as residential sources. The Regional Administrator may approve exceptions to the tabulated allowances where large (more than 25 percent of total estimated ADBF) commercial and institutional flows are documented.



------------------------------------------------------------------------
Gallons per
Description capita per
day
------------------------------------------------------------------------
Non-SMSA cities and towns with projected total 10-year 60-70
populations of 5,000 or less..............................
Other cities and towns..................................... 65-80 (continued)