c. Flow reduction. The cost-effectiveness analysis for each facility planning area shall include an evaluation of the costs, cost savings, and effects of flow reduction measures unless the existing ADBF from the area is less than 70 gpcd, or the current population of the applicant municipality is under 10,000, or the Regional Administrator exempts the area for having an effective existing flow reduction program. Flow reduction measures include public education, pricing and regulatory approaches or a combination of these. In preparing the facilities plan and included cost effectiveness analysis, the grantee shall, as a minimum:

(1) Estimate the flow reductions implementable and cost effective when the treatment works become operational and after 10 and 20 years of operation. The measures to be evaluated shall include a public information program; pricing and regulatory approaches; installation of water meters, and retrofit of toilet dams and low-flow showerheads for existing homes and other habitations; and specific changes in local ordinances, building codes or plumbing codes requiring installations of water saving devices such as water meters, water conserving toilets, showerheads, lavatory faucets, and appliances in new homes, motels, hotels, institutions, and other establishments.

(2) Estimate the costs of the proposed flow reduction measures over the 20-year planning period, including costs of public information, administration, retrofit of existing buildings and the incremental costs, if any, of installing water conserving devices in new homes and establishments.

(3) Estimate the energy reductions; total cost savings for wastewater treatment, water supply and energy use; and the net cost savings (total savings minus total costs) attributable to the proposed flow reduction measures over the planning period. The estimated cost savings shall reflect reduced sizes of proposed wastewater treatment works plus reduced costs of future water supply facility expansions.

(4) Develop and provide for implementing a recommended flow reduction program. This shall include a public information program highlighting effective flow reduction measures, their costs, and the savings of water and costs for a typical household and for the community. In addition, the recommended program shall comprise those flow reduction measures which are cost effective, supported by the public and within the implementation authority of the grantee or another entity willing to cooperate with the grantee.

(5) Take into account in the design of the treatment works the flow reduction estimated for the recommended program.

d. Industrial flows. (1) The treatment works' total design flow capacity may include allowances for industrial flows. The allowances may include capacity needed for industrial flows which the existing treatment works presently serves. However, these flows shall be carefully reviewed and means of reducing them shall be considered. Letters of intent to the grantee are required to document capacity needs for existing flows from significant industrial users and for future flows from all industries intending to increase their flows or relocate in the area. Requirements for letters of intent from significant industrial dischargers are set forth in §35.925–11(c).

(2) While many uncertainties accompany forecasting future industrial flows, there is still a need to allow for some unplanned future industrial growth. Thus, the cost-effective (grant eligible) design capacity and flow of the treatment works may include (in addition to the existing industrial flows and future industrial flows documented by letters of intent) a nominal flow allowance for future nonidentifiable industries or for unplanned industrial expansions, provided that 208 plans, land use plans and zoning provide for such industrial growth. This additional allowance for future unplanned industrial flow shall not exceed 5 percent (or 10 percent for towns with less than 10,000 population) of the total design flow of the treatment works exclusive of the allowance or 25 percent of the total industrial flow (existing plus documented future), whichever is greater.

e. Staging of treatment plants. (1) The capacity of treatment plants (i.e., new plants, upgraded plants, or expanded plants) to be funded under the construction grants program shall not exceed that necessary for wastewater flows projected during an initial staging period determined by one of the following methods:

(a) First method. The grantee shall analyze at least three alternative staging periods (10 years, 15 years, and 20 years). He shall select the least costly (i.e., total present worth or average annual cost) staging period.

(b) Second method. The staging period shall not exceed the period which is appropriate according to the following table.


Staging Periods for Treatment Plants
------------------------------------------------------------------------
Staging
Flow growth factors (20 years) \1\ period \2\
(years)
------------------------------------------------------------------------
Less than 1.3............................................... 20
1.3 to 1.8.................................................. 15
Greater than 1.8............................................ 10
------------------------------------------------------------------------
\1\ Ratio of wastewater flow expected at end of 20 year planning period
to initial flow at the time the plant is expected to become
operational.
\2\ Maximum initial staging period.


(2) A municipality may stage the construction of a treatment plant for a shorter period than the maximum allowed under this policy. A shorter staging period might be based upon environmental factors (secondary impacts, compliance with other environmental laws under §35.925–14, energy conservation, water supply), an objective concerning planned modular construction, the utilization of temporary treatment plants, or attainment of consistency with locally adopted plans including comprehensive and capital improvement plans. However, the staging period in no case may be less than 10 years, because of associated cost penalties and the time necessary to plan, apply for and receive funding, and construct later stages.

(3) The facilities plan shall present the design parameters for the proposed treatment plant. Whenever the proposed treatment plant components' size or capacity would exceed the minimum reliability requirements suggested in the EPA technical bulletin, “Design Criteria for Mechanical, Electric, and Fluid System and Component Reliability,” a complete justification, including supporting data, shall be provided to the Regional Administrator for his approval.

f. Staging of interceptors. Since the location and length of interceptors will influence growth, interceptor routes and staging of construction shall be planned carefully. They shall be consistent with approved 208 plans, growth management plans and other environmental laws under §35.925–14 and shall also be consistent with Executive orders for flood plains and wetlands.

(1) Interceptors may be allowable for construction grant funding if they eliminate existing point source discharges and accommodate flows from existing habitations that violate an enforceable requirement of the Act. Unless necessary to meet those objectives, interceptors should not be extended into environmentally sensitive areas, prime agricultural lands and other undeveloped areas (density less than one household per 2 acres). Where extension of an interceptor through such areas would be necessary to interconnect two or more communities, the grantee shall reassess the need for the interceptor by further consideration of alternative wastewater treatment systems. If the reassessment demonstrates a need for the interceptor, the grantee shall evaluate the interceptor's primary and secondary environmental impacts, and provide for appropriate mitigating measures such as rerouting the pipe to minimize adverse impacts or restricting future connections to the pipe. Appropriate and effective grant conditions (e.g., restricting sewer hookups) should be used where necessary to protect environmentally sensitive areas or prime agricultural lands from new development. NPDES permits shall include the conditions to insure implementation of the mitigating measures when new permits are issued to the affected treatment facilities in those cases where the measures are required to protect the treatment facilities against overloading.

(2) Interceptor pipe sizes (diameters for cylindrical pipes) allowable for construction grant funding shall be based on a staging period of 20 years. A larger pipe size corresponding to a longer staging period not to exceed 40 years may be allowed if the grantee can demonstrate, wherever water quality management plans or other plans developed for compliance with laws under §35.925–14 have been approved, that the larger pipe would be consistent with projected land use patterns in such plans and that the larger pipe would reduce overall (primary plus secondary) environmental impacts. These environmental impacts include:

(a) Primary impacts. (i) Short-term disruption of traffic, business and other daily activities.

(ii) Destruction of flora and fauna, noise, erosion, and sedimentation.

(b) Secondary impacts. (i) Pressure to rezone or otherwise facilitate unplanned development.

(ii) Pressure to accelerate growth for quicker recovery of the non-Federal share of the interceptor investments.

(iii) Effects on air quality and environmentally sensitive areas by cultural changes.

(3) The estimation of peak flows in interceptors shall be based upon the following considerations:

(a) Daily and seasonal variations of pipe flows, the timing of flows from the various parts of the tributary area, and pipe storage effects.

(b) The feasibility of off-pipe storage to reduce peak flows.

(c) The use of an appropriate peak flow factor that decreases as the average daily flow to be conveyed increases.

9. State guidelines. If a State has developed or chooses to develop comprehensive guidelines on cost-effective sizing and staging of treatment works, the Regional Administrator may approve all or portions of the State guidance for application to step 1 facility plans. Approved State guidance may be used instead of corresponding portions of these guidelines, if the following conditions are met:

a. The State guidance must be at least as stringent as the provisions of these guidelines.

b. The State must have held at least one public hearing on proposed State guidance, under regulations in part 25 of this chapter, before submitting the guidance for Agency approval.

10. Additional capacity beyond the cost-effective capacity. Treatment works which propose to include additional capacity beyond the cost-effective capacity determined in accordance with these guidelines may receive Federal grant assistance if the following requirements are met:

a. The facilities plan shall determine the most cost-effective treatment works and its associated capacity in accordance with these guidelines. The facilities plan shall also determine the actual characteristics and total capacity of the treatment works to be built.

b. Only a portion of the cost of the entire proposed treatment works including the additional capacity shall be eligible for Federal funding. The portion of the cost of construction which shall be eligible for Federal funding under sections 203(a) and 202(a) of the Act shall be equivalent to the estimated construction costs of the most cost-effective treatment works. For the eligibility determination, the costs of construction of the actual treatment works and the most cost-effective treatment works must be estimated on a consistent basis. Up-to-date cost curves published by EPA's Office of Water Program Operations or other cost estimating guidance shall be used to determine the cost ratios between cost-effective project components and those of the actual project. These cost ratios shall be multiplied by the step 2 cost and step 3 contract costs of actual components to determine the eligible step 2 and step 3 costs.

c. The actual treatment works to be built shall be assessed. It must be determined that the actual treatment works meets the requirements of the National Environmental Policy Act and all applicable laws, regulations, and guidance, as required of all treatment works by §§35.925–8 and 35.925–14. Particular attention should be given to assessing the project's potential secondary environmental effects and to ensuring that air quality standards will not be violated. The actual treatment works' discharge must not cause violations of water quality standards.

d. The Regional Administrator shall approve the plans, specifications, and estimates for the actual treatment works under section 203(a) of the Act, even though EPA will be funding only a portion of its designed capacity.

e. The grantee shall satisfactorily assure the Agency that the funds for the construction costs due to the addtional capacity beyond the cost-effective treatment works' capacity as determined by EPA (i.e., the ineligible portion of the treatment works), as well as the local share of the grant eligible portion of the construction costs will be available.

f. The grantee shall execute appropriate grant conditions or releases providing that the Federal Government is protected from any further claim by the grantee, the State, or any other party for any of the costs of construction due to the additional capacity.

g. Industrial cost recovery shall be based upon the portion of the Federal grant allocable to the treatment of industrial wastes.

h. The grantee must implement a user charge system which applies to the entire service area of the grantee, including any area served by the additional capacity.

Appendix B to Subpart E of Part 35—Federal Guidelines—User Charges for Operation and Maintenance of Publicly Owned Treatment Works
top
(a) Purpose. To set forth advisory information concerning user charges based on actual use pursuant to section 204 of the Clean Water Act, hereinafter referred to as the Act. Applicable requirements are set forth in subpart E (40 CFR part 35).

(b) Authority. The authority for establishment of the user charge guidelines is contained in section 204(b)(2) of the Act.

(c) Background. Section 204(b)(1) of the Act provides that after March 1, 1973, Federal grant applicants shall be awarded grants only after the Regional Administrator has determined that the applicant has adopted or will adopt a system of charges to assure that each recipient of waste treatment services will pay its proportionate share of the costs of operation and maintenance, including replacement. The intent of the Act with respect to user charges is to distribute the cost of operation and maintenance of publicly owned treatment works to the pollutant source and to promote self-sufficiency of treatment works with respect to operation and maintenance costs. The 1977 Amendments amended section 204(b) to allow grantees to establish user charge systems based on ad valorem taxes. This appendix does not apply to ad valorem user charge systems.

(d) Definitions—(1) Replacement. Expenditures for obtaining and installing equipment, accessories, or appurtenances which are necessary to maintain the capacity and performance during the service life of the treatment works for which such works were designed and constructed. The term “operation and maintenance” includes replacement.

(2) User charge. A charge levied on users of treatment works for the cost of operation and maintenance of such works.

(e) Classes of users. At least two basic types of user charge systems are common. The first is to charge each user a share of the treatment works operation and maintenance costs based on his estimate of measured proportional contribution to the total treatment works loading. The second system establishes classes for users having similar flows and waste water characteristics; i.e., levels of biochemical oxygen demand, suspended solids, etc. Each class is then assigned its share of the waste treatment works operation and maintenance costs based on the proportional contribution of the class to the total treatment works loading. Either system is in compliance with these guidelines.

(f) Criteria against which to determine the adequacy of user charges. The user charge system shall be approved by the Regional Administrator and shall be maintained by the grantee in accordance with the following requirements:

(1) The user charge system must result in the distribution of the cost of operation and maintenance of treatment works within the grantee's jurisdiction to each user (or user class) in proportion to such user's contribution to the total wastewater loading of the treatment works. Factors such as strength, volume, and delivery flow rate characteristics shall be considered and included as the basis for the user's contribution to ensure a proportional distribution of operation and maintenance costs to each user (or user class).

(2) For the first year of operation, operation and maintenance costs shall be based upon past experience for existing treatment works or some other rational method that can be demonstrated to be applicable.

(3) The grantee shall review user charges annually and revise them periodically to reflect actual treatment works operation and maintenance costs.

(4) The user charge system must generate sufficient revenue to offset the cost of all treatment works operation and maintenance provided by the grantee.

(5) The user charge system must be incorporated in one or more municipal legislative enactments or other appropriate authority. If the project is a regional treatment works accepting wastewaters from treatment works owned by others, then the subscribers receiving waste treatment services from the grantee shall have adopted user charge systems in accordance with these guidelines. Such user charge systems shall also be incorporated in the appropriate municipal legislative enactments or other appropriate authority.

(g) Model user charge systems. The user charge system adopted by the applicant must result in the distribution of treatment works operation and maintenance costs to each user (or user class) in approximate proportion to his contribution to the total wastewater loading of the treatment works. The following user charge models can be used for this purpose; however, the applicant is not limited to their use. The symbols used in the models are as defined below:

CT = Total operation and maintenance (O. & M.) costs per unit of time.

Cu = A user's charge for O. & M. per unit of time.

Cs = A surcharge for wastewaters of excessive strength.

Vc = O&M cost for transportation and treatment of a unit of wastewater volume.

Vu = Volume contribution from a user per unit of time.

VT = Total volume contribution from all users per unit of time.

Bc = O&M cost for treatment of a unit of biochemical oxygen demand (BOD).

Bu = Total BOD contribution from a user per unit of time.

BT = Total BOD contribution from all users per unit of time.

B = Concentration of BOD from a user above a base level.

Sc = O&M cost for treatment of a unit of suspended solids.

Su = Total suspended solids contribution from a user per unit of time.

S = Concentration of SS from a user above a base level.

Pc = O&M cost for treatment of a unit of any pollutant.

Pu = Total contribution of any pollutant from a user per unit of time.

PT = Total contribution of any pollutant from all users per unit of time.

P = Concentration of any pollutant from a user above a base level.

(1) Model No. 1. If the treatment works is primarily flow dependent or if the BOD, suspended solids, and other pollutant concentrations discharged by all users are approximately equal, then user charges can be developed on a volume basis in accordance with the model below:

Cu = CT/VT(Vu)

(2) Model No. 2.—When BOD, suspended solids, or other pollutant concentrations from a user exceed the range of concentration of these pollutants in normal domestic sewage, a surcharge added to a base charge, calculated by means of Model No. 1, can be levied. The surcharge can be computed by the model below:

Cs = [Bc(B)=Sc(S)=Pc(P)]Vu

(3) Model No. 3.—This model is commonly called the “quantity/quality formula”:

Cu = Vc Vu=Bc Bu=Sc Su=Pc Pu

(h) Other considerations.—(1) Quantity discounts to large volume users will not be acceptable. Savings resulting from economies of scale should be apportioned to all users or user classes.

(2) User charges may be established based on a percentage of the charge for water usage only in cases where the water charge is based on a constant cost per unit of consumption.

[39 FR 5270, Feb. 11, 1974]

Appendix C–1 to Subpart E of Part 35—Required Provisions—Consulting Engineering Agreements
top
1. General

2. Responsibility of the Engineer

3. Scope of Work

4. Changes

5. Termination

6. Remedies

7. Payment

8. Project Design

9. Audit; Access to Records

10. Price Reduction for Defective Cost or Pricing Data

11. Subcontracts

12. Labor Standards

13. Equal Employment Opportunity

14. Utilization of Small or Minority Business

15. Covenant Against Contingent Fees

16. Gratuities

17. Patents

18. Copyrights and Rights in Data

1. general

(a) The owner and the engineer agree that the following provisions apply to the EPA grant-eligible work to be performed under this agreement and that such provisions supersede any conflicting provisions of this agreement.

(b) The work under this agreement is funded in part by a grant from the U.S. Environmental Protection Agency. Neither the United States nor the U.S. Environmental Protection Agency (hereinafter, “EPA”) is a party to this agreement. This agreement which covers grant-eligible work is subject to regulations contained in 40 CFR 35.936, 35.937, and 35.939 in effect on the date of execution of this agreement. As used in these clauses, the words “the date of execution of this agreement” mean the date of execution of this agreement and any subsequent modification of the terms, compensation or scope of services pertinent to unperformed work.

(c) The owner's rights and remedies provided in these clauses are in addition to any other rights and remedies provided by law or this agreement.

2. responsibility of the engineer

(a) The engineer shall be responsible for the professional quality, technical accuracy, timely completion, and the coordination of all designs, drawings, specifications, reports, and other services furnished by the engineer under this agreement. The engineer shall, without additional compensation, correct or revise any errors, omissions, or other deficiencies in his designs, drawings, specifications, reports, and other services.

(b) The engineer shall perform such professional services as may be necessary to accomplish the work required to be performed under this agreement, in accordance with this agreement and applicable EPA requirements in effect on the date of execution of this agreement.

(c) The owner's or EPA's approval of drawings, designs, specifications, reports, and incidental engineering work or materials furnished hereunder shall not in any way relieve the engineer of responsibility for the technical adequacy of his work. Neither the owner's nor EPA's review, approval or acceptance of, nor payment for, any of the services shall be construed to operate as a waiver of any rights under this agreement or of any cause of action arising out of the performance of this agreement.

(d) The engineer shall be and shall remain liable, in accordance with applicable law, for all damages to the owner or EPA caused by the engineer's negligent performance of any of the services furnished under this agreement, except for errors, omissions or other deficiencies to the extent attributable to the owner, owner-furnished data or any third party. The engineer shall not be responsible for any time delays in the project caused by circumstances beyond the engineeer's control. Where innovative processes or techniques (see 40 CFR 35.908) are recommended by the engineer and are used, the engineer shall be liable only for gross negligence to the extent of such use.

3. scope of work

The services to be performed by the engineer shall include all services required to complete the task or Step in accordance with applicable EPA regulations (40 CFR part 35, subpart E in effect on the date of execution of this agreement) to the extent of the scope of work as defined and set out in the engineering services agreement to which these provisions are attached.

4. changes

(a) The owner may, at any time, by written order, make changes within the general scope of this agreement in the services or work to be performed. If such changes cause an increase or decrease in the engineer's cost of, or time required for, performance of any services under this agreement, whether or not changed by any order, an equitable adjustment shall be made and this agreement shall be modified in writing accordingly. The engineer must assert any claim for adjustment under this clause in writing within 30 days from the date of receipt by the engineer of the notification of change, unless the owner grants a further period of time before the date of final payment under this agreement.

(b) No services for which an additional compensation will be charged by the engineer shall be furnished without the written authorization of the owner.

(c) In the event that there is a modification of EPA requirements relating to the services to be performed under this agreement after the date of execution of this agreement, the increased or decreased cost of performance of the services provided for in this agreement shall be reflected in an appropriate modification of this agreement.

5. termination

(a) Either party may terminate this agreement, in whole or in part, in writing, if the other party substantially fails to fulfill its obligations under this agreement through no fault of the terminating party. However, no such termination may be affected unless the other party is given (1) not less than ten (10) calendar days written notice (delivered by certified mail, return receipt requested) of intent to terminate and (2) an opportunity for consultation with the terminating party before termination.

(b) The owner may terminate this agreement, in whole or in part, in writing, for its convenience, if the termination is for good cause (such as for legal or financial reasons, major changes in the work or program requirements, initiation of a new step) and the engineer is given (1) not less than ten (10) calendar days written notice (delivered by certified mail, return receipt requested) of intent to terminate, and (2) an opportunity for consultation with the terminating party before termination.

(c) If the owner terminates for default, an equitable adjustment in the price provided for in this agreement shall be made, but (1) no amount shall be allowed for anticipated profit on unperformed services or other work, and (2) any payment due to the engineer at the time of termination may be adjusted to the extent of any additional costs the owner incurs because of the engineer's default. If the engineer terminates for default or if the owner terminates for convenience, the equitable adjustment shall include a reasonable profit for services or other work performed. The equitable adjustment for any termination shall provide for payment to the engineer for services rendered and expenses incurred before the termination, in addition to termination settlement costs the engineer reasonably incurs relating to commitments which had become firm before the termination.

(d) Upon receipt of a termination action under paragraph (a) or (b) of this section 5., the engineer shall (1) promptly discontinue all services affected (unless the notice directs otherwise), and (2) deliver or otherwise make available to the owner all data, drawings, specifications, reports, estimates, summaries, and such other information and materials as the engineer may have accumulated in performing this agreement, whether completed or in process.

(e) Upon termination under paragraph (a) or (b) of this section 5., the owner may take over the work and prosecute the same to completion by agreement with another party or otherwise. Any work the owner takes over for completion will be completed at the owner's risk, and the owner will hold harmless the engineer from all claims and damages arising out of improper use of the engineer's work.

(f) If, after termination for failure of the engineer to fulfill contractual obligations, it is determined that the engineer had not so failed, the termination shall be deemed to have been effected for the convenience of the owner. In such event, adjustment of the price provided for in this agreement shall be made as paragraph (c) of this clause provides.

6. remedies

Except as this agreement otherwise provides, all claims, counter-claims, disputes, and other matters in question between the owner and the engineer arising out of or relating to this agreement or the breach of it will be decided by arbitration if the parties hereto mutually agree, or in a court of competent jurisdiction within the State in which the owner is located.

7. payment

(a) Payment shall be made in accordance with the payment schedule incorporated in this agreement as soon as practicable upon submission of statements requesting payment by the engineer to the owner. If no such payment schedule is incorporated in this agreement, the payment provisions of paragraph (b) of this clause shall apply.

(b) The engineer may request monthly progress payments and the owner shall make them as soon as practicable upon submission of statements requesting payment by the engineer to the owner. When such progress payments are made, the owner may withhold up to ten (10) percent of the vouchered amount until satisfactory completion by the engineer of work and services within a step called for under this agreement. When the owner determines that the work under this agreement or any specified task hereunder is substantially complete and that the amount of retained percentages is in excess of the amount considered by him to be adequate for his protection, he shall release to the engineer such excess amount.

(c) No payment request made under paragraph (a) or (b) of this clause shall exceed the estimated amount and value of the work and services performed by the engineer under this agreement. The engineer shall prepare the estimates of work performed and shall supplement them with such supporting data as the owner may require.

(d) Upon satisfactory completion of the work performed under this agreement, as a condition precedent to final payment under this agreement or to settlement upon termination of the agreement, the engineer shall execute and deliver to the owner a release of all claims against the owner arising under or by virtue of this agreement, other than such claims, if any, as may be specifically exempted by the engineer from the operation of the release in stated amounts to be set forth therein.

8. project design

(a) In the performance of this agreement, the engineer shall, to the extent practicable, provide for maximum use of structures, machines, products, materials, construction methods, and equipment which are readily available through competitive procurement, or through standard or proven production techniques, methods, and processes, consistent with 40 CFR 35.936–3 and 35.936–13 in effect on the date of execution of this agreement, except to the extent to which innovative technology may be used under 40 CFR 35.908 in effect on the date of execution of this agreement.

(b) The engineer shall not, in the performance of the work under this agreement, produce a design or specification which would require the use of structures, machines, products, materials, construction methods, equipment, or processes which the engineer knows to be available only from a sole source, unless the engineer has adequately justified the use of a sole source in writing.

(c) The engineer shall not, in the performance of the work under this agreement, produce a design or specification which would be restrictive in violation of section 204(a)(6) of the Clean Water Act. This statute requires that no specification for bids or statement of work shall be written in such a manner as to contain proprietary, exclusionary, or discriminatory requirements other than those based upon performance, unless such requirements are necessary to test or demonstrate a specific thing, or to provide for necessary interchangeability of parts and equipment, or at least two brand names or trade names of comparable quality or utility are listed and are followed by the words “or equal.” With regard to materials, if a single material is specified, the engineer must be prepared to substantiate the basis for the selection of the material.

(d) The engineer shall report to the owner any sole-source or restrictive design or specification giving the reason or reasons why it is necessary to restrict the design or specification.

(e) The engineer shall not knowingly specify or approve the performance of work at a facility which is in violation of clean air or water standards and which is listed by the Director of the EPA Office of Federal Activities under 40 CFR part 15.

9. audit; access to records

(a) The engineer shall maintain books, records, documents, and other evidence directly pertinent to performance on EPA grant work under this agreement in accordance with generally accepted accounting principles and practices consistently applied, and 40 CFR 30.605, 30.805, and 35.935–7 in effect on the date of execution of this agreement. The engineer shall also maintain the financial information and data used by the engineer in the preparation or support of the cost submission required under 40 CFR 35.937–6(b) in effect on the date of execution of this agreement and a copy of the cost summary submitted to the owner. The U.S. Environmental Protection Agency, the Comptroller General of the United States, the U.S. Department of Labor, owner, and [the State water pollution control agency] or any of their duly authorized representatives shall have access to such books, records, documents, and other evidence for inspection, audit, and copying. The engineer will provide proper facilities for such access and inspection.

(b) The engineer agrees to include paragraphs (a) through (e) of this clause in all his contracts and all tier subcontracts directly related to project performance that are in excess of $10,000.

(c) Audits conducted under this provision shall be in accordance with generally accepted auditing standards and established procedures and guidelines of the reviewing or audit agency(ies).

(d) The engineer agrees to the disclosure of all information and reports resulting from access to records under paragraphs (a) and (b) of this clause, to any of the agencies referred to in paragraph (a), provided that the engineer is afforded the opportunity for an audit exit conference and an opportunity to comment and submit any supporting documentation on the pertinent portions of the draft audit report and that the final audit report will include written comments of reasonable length, if any, of the engineer.

(e) The engineer shall maintain and make available records under paragraphs (a) and (b) of this clause during performance on EPA grant work under this agreement and until 3 years from the date of final EPA grant payment for the project. In addition, those records which relate to any “Dispute” appeal under an EPA grant agreement, to litigation, to the settlement of claims arising out of such performance, or to costs or items to which an audit exception has been taken, shall be maintained and made available until 3 years after the date of resolution of such appeal, litigation, claim, or exception.

10. price reduction for defective cost or pricing data

(This clause is applicable if the amount of this agreement exceeds $100,000.)

(a) If the owner or EPA determines that any price, including profit, negotiated in connection with this agreement or any cost reimbursable under this agreement was increased by any significant sums because the engineer or any subcontractor furnished incomplete or inaccurate cost or pricing data or data not current as certified in his certification of current cost or pricing data (EPA form 5700–41), then such price, cost, or profit shall be reduced accordingly and the agreement shall be modified in writing to reflect such reduction.

(b) Failure to agree on a reduction shall be subject to the remedies clause of this agreement.

(Note: Since the agreement is subject to reduction under this clause by reason of defective cost or pricing data submitted in connection with certain subcontracts, the engineer may wish to include a clause in each such subcontract requiring the subcontractor to appropriately indemnify the engineer. It is also expected that any subcontractor subject to such indemnification will generally require substantially similar indemnification for defective cost or pricing data required to be submitted by his lower tier subcontractors.)

11. subcontracts

(a) Any subcontractors and outside associates or consultants required by the engineer in connection with services under this agreement will be limited to such individuals or firms as were specifically identified and agreed to during negotiations, or as the owner specifically authorizes during the performance of this agreement. The owner must give prior approval for any substitutions in or additions to such subcontractors, associates, or consultants.

(b) The engineer may not subcontract services in excess of thirty (30) percent (or ___ percent, if the owner and the engineer hereby agree) of the contract price to subcontractors or consultants without the owner's prior written approval.

12. labor standards

To the extent that this agreement involves “construction” (as defined by the Secretary of Labor), the engineer agrees that such construction work shall be subject to the following labor standards provisions, to the extent applicable:

(a) Davis-Bacon Act (40 U.S.C. 276a—276a–7);

(b) Contract Work Hours and Safety Standards Act (40 U.S.C. 327–333);

(c) Copeland Anti-Kickback Act (18 U.S.C. 874); and

(d) Executive Order 11246 (Equal Employment Opportunity);

and implementing rules, regulations, and relevant orders of the Secretary of Labor or EPA. The engineer further agrees that this agreement shall include and be subject to the “Labor Standards Provisions for Federally Assisted Construction Contracts” (EPA form 5720–4) in effect at the time of execution of this agreement.

13. equal employment opportunity

In accordance with EPA policy as expressed in 40 CFR 30.420–5, the engineer agrees that he will not discriminate against any employee or applicant for employment because of race, religion, color, sex, age, or national origin.

14. utilization of small and minority business

In accordance with EPA policy as expressed in 40 CFR 35.936–7, the engineer agrees that qualified small business and minority business enterprises shall have the maximum practicable opportunity to participate in the performance of EPA grant- assisted contracts and subcontracts.

15. covenant against contingent fees

The engineer warrants that no person or selling agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee, excepting bona fide employees. For breach or violation of this warranty the owner shall have the right to annul this agreement without liability or in its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage, or contingent fee.

16. gratuities

(a) If it is found, after notice and hearing, by the owner that the engineer, or any of the engineer's agents or representatives, offered or gave gratuities (in the form of entertainment, gifts, or otherwise), to any official, employee, or agent of the owner, of the State, or of EPA in an attempt to secure a contract or favorable treatment in awarding, amending, or making any determinations related to the performance of this agreement, the owner may, by written notice to the engineer, terminate the right of the engineer to proceed under this agreement. The owner may also pursue other rights and remedies that the law or this agreement provides. However, the existence of the facts upon which the owner bases such findings shall be in issue and may be reviewed in proceedings under the remedies clause of this agreement.

(b) In the event this agreement is terminated as provided in paragraph (a) hereof, the owner shall be entitled: (1) To pursue the same remedies against the engineer as it could pursue in the event of a breach of the contract by the engineer, and (2) as a penalty, in addition to any other damages to which it may be entitled by law, to exemplary damages in an amount (as determined by the owner) which shall be not less than 3 nor more than 10 times the costs the engineer incurs in providing any such gratuities to any such officer or employee.

17. patents

If this agreement involves research, developmental, experimental, or demonstration work and any discovery or invention arises or is developed in the course of or under this agreement, such invention or discovery shall be subject to the reporting and rights provisions of subpart D of 40 CFR part 30, in effect on the date of execution of this agreement, including appendix B of part 30. In such case, the engineer shall report the discovery or invention to EPA directly or through the owner, and shall otherwise comply with the owner's responsibilities in accordance with subpart D of 40 CFR part 30. The engineer agrees that the disposition of rights to inventions made under this agreement shall be in accordance with the terms and conditions of appendix B. The engineer shall include appropriate patent provisions to achieve the purpose of this condition in all subcontracts involving research, developmental, experimental, or demonstration work.

18. copyrights and rights in data

(a) The engineer agrees that any plans, drawings, designs, specifications, computer programs (which are substantially paid for with EPA grant funds), technical reports, operating manuals, and other work submitted with a step 1 facilities plan or with a step 2 or step 3 grant application or which are specified to be delivered under this agreement or which are developed or produced and paid for under this agreement (referred to in this clause as “Subject Data”) are subject to the rights in the United States, as set forth in subpart D of 40 CFR part 30 and in appendix C to 40 CFR part 30, in effect on the date of execution of this agreement. These rights include the right to use, duplicate, and disclose such subject data, in whole or in part, in any manner for any purpose whatsoever, and to have others do so. For purposes of this clause, “grantee” as used in appendix C refers to the engineer. If the material is copyrightable, the engineer may copyright it, as appendix C permits, subject to the rights in the Government in appendix C, but the owner and the Federal Government reserve a royalty-free, nonexclusive, and irrevocable license to reproduce, publish, and use such materials, in whole or in part, and to authorize others to do so. The engineer shall include appropriate provisions to achieve the purpose of this condition in all subcontracts expected to produce copyrightable subject data.

(b) All such subject data furnished by the engineer pursuant to this agreement are instruments of his services in respect of the project. It is understood that the engineer does not represent such subject data to be suitable for reuse on any other project or for any other purpose. If the owner reuses the subject data without the engineer's specific written verification or adaptation, such reuse will be at the risk of the owner, without liability to the engineer. Any such verification or adaptation will entitle the engineer to further compensation at rates agreed upon by the owner and the engineer.

Appendix C–2 to Subpart E of Part 35—Required Provisions—Construction Contracts
top
supplemental general conditions

1. General

2. Changes

3. Differing Site Conditions

4. Suspension of Work

5. Termination for Default; Damages for Delay; Time Extensions

6. Termination for Convenience

7. Remedies

8. Labor Standards

9. Utilization of Small or Minority Business

10. Audit; Access to Records

11. Price Reduction for Defective Cost or Pricing Data

12. Covenant Against Contingent Fees

13. Gratuities

14. Patents

15. Copyrights and Rights in Data

16. Prohibition Against Listed Violating Facilities

17. Buy American

1. general

(a) The owner and the contractor agree that the following supplemental general provisions apply to the work to be performed under this contract and that these provisions supersede any conflicting provisions of this contract.

(b) This contract is funded in part by a grant from the U.S. Environmental Protection Agency. Neither the United States nor any of its departments, agencies or employees is a party to this contract. This contract is subject to regulations contained in 40 CFR 35.936, 35.938, and 35.939 in effect on the date of execution of this contract.

(c) The owner's rights and remedies provided in these clauses are in addition to any other rights and remedies provided by law or under this contract.

2. changes

(a) The owner may, at any time, without notice to the sureties, by written order designated or indicated to be a change order, make any change in the work within the general scope of the contract, including but not limited to changes—

(1) In the specifications (including drawings and designs);

(2) In the method or manner of performance of the work;

(3) In the owner-furnished facilities, equipment, materials, services, or site; or

(4) Directing acceleration in the performance of the work.

(b) Any other written order or an oral order (which terms as used in this paragraph (b) shall include direction, instruction, interpretation, or determination) from the owner, which causes any such change, shall be treated as a change order under this clause, if the contractor gives the owner written notice stating the date, circumstances, and source of the order and if the contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement, or conduct of the owner shall be treated as a change under this clause or shall entitle the contractor to an equitable adjustment.

(d) If any change under this clause causes an increase or decrease in the contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment shall be made and the contract modified in writing accordingly. However, except for claims based on defective specifications, no claim for any change under paragraph (b) of this section 2., shall be allowed for any costs incurred more than 20 days before the contractor gives written notice as there required. Also, in the case of defective specifications for which the owner is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the contractor in attempting to comply with such defective specifications.

(e) If the contractor intends to assert a claim for an equitable adjustment under this clause, he must, within 30 days after receipt of a written change order under (a) above or the furnishing of a written notice under paragraph (b) of this section 2., submit to the owner a written statement setting forth the general nature and monetary extent of such claim, unless the owner extends this period. The statement of claim hereunder may be included in the notice under paragraph (b) of this section 2.

(f) No claim by the contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.

3. differing site conditions

(a) The contractor shall promptly, and before such conditions are disturbed, notify the owner in writing of: (1) Subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract. The owner shall promptly investigate the conditions. If he finds that such conditions do materially differ and cause an increase or decrease in the contractor's cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly.

(b) No claim of the contractor under this clause shall be allowed unless the contractor has given the notice required in paragraph (a) of this clause, except that the owner may extend the prescribed time.

(c) No claim by the contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.

4. suspension of work (continued)