(a) The owner may order the contractor in writing to suspend, delay, or interrupt all or any part of the work for such period of time as he may determine to be appropriate for the convenience of the owner.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the owner in administration of this contract, or by his failure to act within the time specfied in this contract (or if no time is specified, within a reasonable time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent (1) that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the contractor or (2) for which an equitable adjustment is provided for or excluded under any other provision of this contract.

(c) No claim under this clause shall be allowed (1) for any costs incurred more than 20 days before the contractor shall have notified the owner in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of such suspension, delay, or interruption, but not later than the date of final payment under the contract.

5. termination for default; damages for delay; time extensions

(a) If the contractor refuses or fails to prosecute the work, or any separable part of the work, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the owner may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the owner may take over the work and prosecute the same to completion, by contract or otherwise, and may take possession of and use in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. Whether or not the contractor's right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the owner resulting from his refusal or failure to complete the work within the specified time.

(b) If the contract provides for liquidated damages, and if the owner terminates the contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs the owner incurs in completing the work.

(c) If the contract provides for liquidated damages and if the owner does not terminate the contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted.

(d) The contractor's right to proceed shall not be terminated nor the contractor charged with resulting damage if:

(1) The delay in the completion of the work arises from causes other than normal weather beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, acts of the public enemy, acts of the owner in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from causes other than normal weather beyond the control and without the fault or negligence of both the contractor and such subcontractors or suppliers; and

(2) The contractor, within 10 days from the beginning of any such delay (unless the owner grants a further period of time before the date of final payment under the contract), notifies the owner in writing of the causes of delay. The owner shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension. His findings of fact shall be final and conclusive on the parties, subject only to appeal as the remedies clause of this contract provides.

(e) If, after notice of termination of the contractor's right to proceed under the provisions of this clause, it is determined for any reason that the contractor was not in default under this clause, or that the delay was excusable under this clause, the rights and obligations of the parties shall be the same as if the notice of termination has been issued under the clause providing for termination for convenience of the owner.

(f) The rights and remedies of the owner provided in this clause are in addition to any other rights and remedies provided by law or under this contract.

(g) As used in paragraph (d)(1) of this clause, the term “subcontractors or suppliers” means subcontractors or suppliers at any tier.

6. termination for convenience

(a) The owner may terminate the performance of work under this contract in accordance with this clause in whole, or from time to time in part, whenever the owner shall determine that such termination is in the best interest of the owner. Any such termination shall be effected by delivery to the contractor of a notice of termination specifying the extent to which performance of work under the contract is terminated, and the date upon which such termination becomes effective.

(b) After receipt of a notice of termination, and except as otherwise directed by the owner, the contractor shall:

(1) Stop work under the contract on the date and to the extent specified in the notice of termination;

(2) Place no further orders or subcontracts for materials, services, or facilities except as necessary to complete the portion of the work under the contract which is not terminated;

(3) Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the notice of termination;

(4) Assign to the owner, in the manner, at the times, and to the extent directed by the owner, all of the right, title, and interest of the contractor under the orders and subcontracts so terminated. The owner shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(5) Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the owner to the extent he may require. His approval or ratification shall be final for all the purposes of this clause;

(6) Transfer title to the owner, and deliver in the manner, at the times, and to the extent, if any, directed by the owner, (i) the fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in connection with the performance of, the work terminated by the notice of termination, and (ii) the completed or partially completed plans, drawings, information, and other property which, if the contract had been completed, would have been required to be furnished to the owner;

(7) Use his best efforts to sell, in the manner, at the times, to the extent, and at the price or prices that the owner directs or authorizes, any property of the types referred to in paragraph (b)(6) of this clause, but the contractor (i) shall not be required to extend credit to any purchaser, and (ii) may acquire any such property under the conditions prescribed and at a price or prices approved by the owner. The proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the owner to the contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the owner may direct;

(8) Complete performance of such part of the work as shall not have been terminated by the notice of termination; and

(9) Take such action as may be necessary, or as the owner may direct, for the protection and preservation of the property related to this contract which is in the possession of the contractor and in which the owner has or may acquire an interest.

(c) After receipt of a notice of termination, the contractor shall submit to the owner his termination claim, in the form and with the certification the owner prescribes. Such claim shall be submitted promptly but in no event later than 1 year from the effective date of termination, unless one or more extensions in writing are granted by the owner upon request of the contractor made in writing within such 1-year period or authorized extension. However, if the owner determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such 1-year period or extension. If the contractor fails to submit his termination claim within the time allowed, the owner may determine, on the basis of information available to him, the amount, if any, due to the contractor because of the termination. The owner shall then pay to the contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), the contractor and the owner may agree upon the whole or any part of the amount or amounts to be paid to the contractor because of the total or partial termination of work under this clause. The amount or amounts may include a reasonable allowance for profit on work done. However, such agreed amount or amounts, exclusive of settlement costs, shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. The contract shall be amended accordingly, and the contractor shall be paid the agreed amount. Nothing in paragraph (e) of this clause, prescribing the amount to be paid to the contractor in the event of failure of the contractor and the owner to agree upon the whole amount to be paid to the contractor because of the termination of work under this clause, shall be deemed to limit, restrict, or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the contractor pursuant to this paragraph (d).

(e) If the contractor and the owner fail to agree, as paragraph (d) of this section 6., provides, on the whole amount to be paid to the contractor because of the termination of work under this clause, the owner shall determine, on the basis of information available to him, the amount, if any, due to the contractor by reason of the termination and shall pay to the contractor the amounts determined as follows:

(1) For all contract work performed before the effective date of the notice of termination, the total (without duplication of any items) of—

(i) The cost of such work;

(ii) The cost of settling and paying claims arising out of the termination of work under subcontracts or orders as paragraph (b)(5) of this clause provides. This cost is exclusive of the amounts paid or payable on account of supplies or materials delivered or services furnished by the subcontractor before the effective date of the notice of termination. These amounts shall be included in the cost on account of which payment is made under paragraph (1)(i) of this section 6.; and

(iii) A sum, as profit on paragraph (1)(i) of this section 6., that the owner determines to be fair and reasonable. But, if it appears that the contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed under this paragraph (1)(iii) of this section 6., and an appropriate adjustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss; and

(2) The reasonable cost of the preservation and protection of property incurred under paragraph (b)(9) of this clause; and any other reasonable cost incidental to termination of work under this contract, including expense incidental to the determination of the amount due to the contractor as the result of the termination of work under this contract. The total sum to be paid to the contractor under paragraph (e)(1) of this clause shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. Except for normal spoilage, and except to the extent that the owner shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the contractor under paragraph (1) of this clause 6., the fair value, as determined by the owner of property which is destroyed, lost, stolen, or damaged, to the extent that it is un-deliverable to the owner, or to a buyer under paragraph (b)(7) of this clause.

(f) The contractor shall have the right to dispute under the clause of this contract entitled “Remedies,” from any determination the owner makes under paragraph (c) or (e) of this clause. But, if the contractor has failed to submit his claim within the time provided in paragraph (c) of this clause and has failed to request extension of such time, he shall have no such right of appeal. In any case where the owner has determined the amount due under paragraph (c) or (e) of this clause, the owner shall pay to the contractor the following: (1) If there is no right of appeal hereunder or if no timely appeal has been taken, the amount so determined by the owner or (2) if a “Remedies” proceeding is initiated, the amount finally determined in such “Remedies” proceeding.

(g) In arriving at the amount due the contractor under this clause there shall be deducted (1) all unliquidated advance or other payments on account theretofore made to the contractor, applicable to the terminated portion of this contract, (2) any claim which the owner may have against the contractor in connection with this contract, and (3) the agreed price for, or the proceeds of sale of, any materials, supplies, or other things kept by the contractor or sold, under the provisions of this clause, and not otherwise recovered by or credited to the owner.

(h) If the termination hereunder be partial, before the settlement of the terminated portion of this contract, the contractor may file with the owner a request in writing for an equitable adjustment of the price or prices specified in the contract relating to the continued portion of the contract (the portion not terminated by the notice of termination). Such equitable adjustment as may be agreed upon shall be made in the price or prices. Nothing contained herein shall limit the right of the owner and the contractor to agree upon the amount or amounts to be paid to the contractor for the completion of the continued portion of the contract when the contract does not contain an established contract price for the continued portion.

7. remedies

Unless this contract provides otherwise, all claims, counterclaims, disputes and other matters in question between the owner and the contractor arising out of or relating to this agreement or its breach will be decided by arbitration if the parties mutually agree, or in a court of competent jurisdiction within the State in which the owner is located.

8. labor standards

The contractor agrees that “construction” work (as defined by the Secretary of Labor) shall be subject to the following labor standards provisions, to the extent applicable:

(a) Davis-Bacon Act (40 U.S.C. 276a—276a–7);

(b) Contract Work Hours and Safety Standards Act (40 U.S.C. 327–33);

(c) Copeland Anti-Kickback Act (18 U.S.C. 874); and

(d) Executive Order 11246 (equal employment opportunity);

and implementing rules, regulations, and relevant orders of the Secretary of Labor or EPA. The contractor further agrees that this contract shall include and be subject to the “Labor Standards Provisions for Federally assisted Construction Contracts” (EPA form 5720–4) in effect at the time of execution of this agreement.

9. utilization of small and minority business

In accordance with EPA policy as expressed in 40 CFR 35.936–7, the contractor agrees that small business and minority business enterprises shall have the maximum practicable opportunity to participate in the performance of EPA grant-assisted contracts and subcontracts.

10. audit; access to records

(a) The contractor shall maintain books, records, documents and other evidence directly pertinent to performance on EPA grant work under this contract in accordance with generally accepted accounting principles and practices consistently applied, and 40 CFR 30.605, 30.805, and 35.935–7 in effect on the date of execution of this contract. The contractor shall also maintain the financial information and data used by the contractor in the preparation or support of the cost submission required under 40 CFR 35.938–5 in effect on the date of execution of this contract for any negotiated contract or change order and a copy of the cost summary submitted to the owner. The U.S. Environmental Protection Agency, the Comptroller General of the United States, the U.S. Department of Labor, owner, and (the State water pollution control agency) or any of their authorized representatives shall have access to such books, records, documents and other evidence for the purpose of inspection, audit and copying. The contractor will provide proper facilities for such access and inspection.

(b) If this contract is a formally advertised, competitively awarded, fixed price contract, the contractor agrees to make paragraphs (a) through (f) of this clause applicable to all negotiated change orders and contract amendments affecting the contract price. In the case of all other types of prime contracts, the contractor agrees to include paragraphs (a) through (f) of this clause in all his contracts in excess of $10,000 and all tier subcontracts in excess of $10,000 and to make paragraphs (a) through (f) of this clause applicable to all change orders directly related to project performance.

(c) Audits conducted under this provision shall be in accordance with generally accepted auditing standards and established procedures and guidelines of the reviewing or audit agency(ies).

(d) The contractor agrees to the disclosure of all information and reports resulting from access to records under paragraphs (a) and (b) of this clause, to any of the agencies referred to in paragraph (a) of this clause 10., provided that the contractor is afforded the opportunity for an audit exit conference, and an opportunity to comment and submit any supporting documentation on the pertinent portions of the draft audit report and that the final EPA audit report will include written comments of reasonable length, if any, of the contractor.

(e) Records under paragraphs (a) and (b) of this clause 10., shall be maintained and made available during performance on EPA grant work under this contract and until 3 years from the date of final EPA grant payment for the project. In addition, those records which relate to any “Dispute” appeal under an EPA grant agreement, to litigation, to the settlement of claims arising out of such performance, or to costs or items to which an audit exception has been taken, shall be maintained and made available until three years after the date of resolution of such appeal, litigation, claim or exception.

(f) The right of access which this clause confers will generally be exercised (with respect to financial records) under (1) negotiated prime contracts, (2) negotiated change orders or contract amendments in excess of $10,000 affecting the price of any formally advertised, competitively awarded, fixed price contract, and (3) subcontracts or purchase orders under any contract other than a formally advertised, competitively awarded, fixed price contract. However, this right of access will generally not be exercised with respect to a prime contract, subcontract, or purchase order awarded after effective price competition. In any event, such right of access may be exercised under any type of contract or subcontract (1) with respect to records pertaining directly to contract performance, excluding any financial records of the contractor, (2) if there is any indication that fraud, gross abuse, or corrupt practices may be involved or (3) if the contract is terminated for default or for convenience.

11. price reduction for defective cost or pricing data

(This clause is applicable to (1) any negotiated prime contract in excess of $100,000; (2) negotiated contract amendments or change orders in excess of $100,000 affecting the price of a formally advertised, competitively awarded, fixed price contract; or (3) any subcontract or purchase order in excess of $100,000 under a prime contract other than a formally advertised, competitively awarded, fixed price contract. Change orders shall be determined to be in excess of $100,000 in accordance with 40 CFR 35.938–5(g). However, this clause is not applicable for contracts or subcontracts to the extent that they are awarded on the basis of effective price competition.)

(a) If the owner or EPA determines that any price (including profit) negotiated in connection with this contract, or any cost reimbursable under this contract, was increased by any significant sums because the contractor, or any subcontractor furnished incomplete or inaccurate cost or pricing data or data not current as certified in his certification of current cost or pricing data (EPA form 5700–41), then such price or cost or profit shall be reduced accordingly and the contract shall be modified in writing to reflect such reduction.

(b) Failure to agree on a reduction shall be subject to the Remedies clause of this contract.

(Note: Since the contract is subject to reduction under this clause by reason of defective cost or pricing data submitted in connection with certain subcontracts, the contractor may wish to include a clause in each such subcontract requiring the subcontractor to appropriately indemnify the contractor. It is also expected that any subcontractor subject to such indemnification will generally require substantially similar indemnification for defective cost or pricing data required to be submitted by his lower tier subcontractors.)

12. covenant against contingent fees

The contractor warrants that no person or selling agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee, excepting bona fide employees or bona fide established commercial or selling agencies maintained by the contractor for the purpose of securing business. For breach or violation of this warranty the owner shall have the right to annul this contract without liability or in its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage, or contingent fee.

13. gratuities

(a) If the owner finds, after notice and hearing, that the contractor or any of the contractor's agents or representatives offered or gave gratuities (in the form of entertainment, gifts, or otherwise) to any official, employee or agent of the owner, of the State, or of EPA in an attempt to secure a contract or favorable treatment in the awarding, amending, or making any determinations related to the performance of this contract, the owner may, by written notice to the contractor, terminate the right of the contractor to proceed under this contract. The owner may also pursue other rights and remedies that the law or this contract provides. However, the existence of the facts upon which the owner makes such findings shall be in issue and may be reviewed in proceedings under the remedies clause of this contract.

(b) In the event this contract is terminated as provided in paragraph (a) of this clause, the owner shall be entitled (1) to pursue the same remedies against the contractor as it could pursue in the event of a breach of the contract by the contractor, and (2) as a penalty in addition to any other damages to which it may be entitled by law, to exemplary damages in an amount (as determined by the owner) which shall be not less than 3 nor more than 10 times the costs the contractor incurs in providing any such gratuities to any such officer or employee.

14. patents

If this contract involves research, developmental, experimental, or demonstration work, and any discovery or invention arises or is developed in the course of or under this contract, such invention or discovery shall be subject to the reporting and rights provisions of subpart D of 40 CFR part 30, in effect on the date of execution of this contract, including appendix B of part 30. In such case, the contractor shall report the discovery or invention to EPA directly or through the owner, and shall otherwise comply with the owner's responsibilities in accordance with subpart D of 40 CFR part 30. The contractor agrees that the disposition of rights to inventions made under this contract shall be in accordance with the terms and conditions of appendix B. The contractor shall include appropriate patent provisions to achieve the intent of this condition in all subcontracts involving research, developmental, experimental, or demonstration work.

15. copyrights and rights in data

The contractor agrees that any plans, drawings, designs, specifications, computer programs (which are substantially paid for with EPA grant funds), technical reports, operating manuals, and other work submitted with a proposal or grant application or which are specified to be delivered under this contract or which are developed or produced and paid for under this contract (referred to in this clause as “Subject Data”) are subject to the rights in the United States, as set forth in subpart D of 40 CFR part 30 and in appendix C to 40 CFR part 30, in effect on the date of execution of this contract. These rights include the right to use, duplicate and disclose such Subject Data, in whole or in part, in any manner for any purpose whatsoever, and to have others do so. For purposes of this clause, “grantee” as used in appendix C refers to the contractor. If the material is copyrightable, the contractor may copyright it, as appendix C permits, subject to the rights in the Government as set forth in appendix C, but the owner and the Federal Government reserve a royalty-free, nonexclusive, and irrevocable license to reproduce, publish and use such materials, in whole or in part, and to authorize others to do so. The contractor shall include provisions appropriate to achieve the intent of this condition in all subcontracts expected to produce copyrightable Subject Data.

16. prohibition against listed violating facilities

(Applicable only to a contract in excess of $100,000 and when otherwise applicable under 40 CFR part 15.)

(a) The contractor agrees as follows:

(1) To comply with all the requirements of section 114 of the Clean Air Act, as amended (42 U.S.C. 1857, et seq., as amended by Pub. L. 92–604) and section 308 of the Clean Water Act (33 U.S.C. 1251, as amended), respectively, which relate to inspection, monitoring, entry, reports, and information, as well as other requirements specified in section 114 and section 308 of the Air Act and the Water Act, respectively, and all regulations and guidelines issued thereunder before the award of this contract.

(2) That no portion of the work required by this prime contract will be performed in a facility listed on the Environmental Protection Agency list of violating facilities on the date when this contract was awarded unless and until the EPA eliminates the name of such facility or facilities from the listing.

(3) To use his best efforts to comply with clean air and clean water standards at the facilities in which the contract is being performed.

(4) To insert the substance of the provisions of this clause, including this paragraph (4), in any nonexempt subcontract.

(b) The terms used in this clause have the following meanings:

(1) The term Air Act means the Clean Air Act, as amended (42 U.S.C. 1857 et seq.).

(2) The term Water Act means the Clean Water Act, as amended (33 U.S.C. 1251 et seq.).

(3) The term Clean Air Standards means any enforceable rules, regulations, guidelines, standards, limitations, orders, controls, prohibitions, or other requirements which are contained in, issued under, or otherwise adopted under the Air Act or Executive Order 11738, an applicable implementation plan as described in section 110(d) of the Air Act (42 U.S.C. 1857c–5(d)), an approved implementation procedure or plan under section 111(c) or section 111(d), or an approved implementation procedure under section 112(d) of the Air Act (42 U.S.C. 1857c–7(d)).

(4) The term Clean Water Standards means any enforceable limitation, control, condition, prohibition, standard, or other requirement which is promulgated under the Water Act or contained in a permit issued to a discharger by the Environmental Protection Agency or by a State under an approved program, as authorized by section 402 of the Water Act (33 U.S.C. 1342), or by a local government to ensure compliance with pretreatment regulations as required by section 307 of the Water Act (33 U.S.C. 1317).

(5) The term Compliance means compliance with clean air or water standards. Compliance shall also mean compliance with a schedule or plan ordered or approved by a court of competent jurisdiction, the Envrionmental Protection Agency or an Air or Water Pollution Control Agency in accordance with the requirements of the Air Act or Water Act and regulations.

(6) The term Facility means any building, plant, installation, structure, mine, vessel, or other floating craft, location, or site of operations, owned, leased, or supervised by a contractor or subcontractor, to be used in the performance of a contract or subcontract. Where a location or site of operations contains or includes more than one building, plant, installation, or structure, the entire location or site shall be deemed to be a facility except where the Director, Office of Federal Activities, Environmental Protection Agency, determines that independent facilities are located in one geographical area.

17. buy american

In accordance with section 215 of the Clean Water Act, and implementing EPA regulations and guidelines, the contractor agrees that preference will be given to domestic construction material by the contractor, subcontractors, materialmen, and suppliers in the performance of this contract.

[43 FR 44049, Sept. 27, 1978, as amended at 44 FR 37596, June 27, 1979; 44 FR 39340, July 5, 1979]

Appendix D to Subpart E of Part 35—EPA Transition Policy—Existing Consulting Engineering Agreements
top
a. access to records—audit

1. Access clause. After June 30, 1975, a construction grant for Steps 1, 2 or 3 will not be awarded nor will initiation of Step 1 work be approved under 40 CFR 35.917(e) or 35.925–18(a)(3), unless an acceptable records and access clause is included in the consulting engineering subagreement. The clause contained in appendix C–1 shall be used on or after March 1, 1976. The clause required by former PG–53 or approved as an alternate thereto may be used for all contracts under grants awarded before March 1, 1976.

2. EPA exercise of right of access to records. Under applicable statutory and regulatory provisions, EPA has a broad right of access to grantees' consulting engineers' records pertinent to performance of EPA project work. The extent to which EPA will exercise this right of access will depend upon the nature of the records and upon the type of agreement.

a. In order to determine where EPA shall exercise its right of access, engineers' project-related records have been divided into three categories:

(1) Category A: Records that pertain directly to the professional, technical and other services performed, excluding any type of financial records of the consulting engineer.

(2) Category B: Financial records of the consulting engineer pertaining to the direct costs of professional, technical and other services performed, excluding financial records pertaining to profit and overhead or other indirect costs.

(3) Category C: Financial records of the consulting engineer excluded from category B.

b. In all cases, EPA will exercise its right of access to Category A records. Also, where there is an indication that fraud, gross abuse, or corrupt practices may be involved, EPA will exercise its right of access to records in all categories. Otherwise, access to consulting engineers' financial records (categories B and C) will depend principally upon the method(s) of compensation stipulated in the agreement:

(1) Agreements based upon a percentage of construction cost. Category B and C records will not be audited. However, terms of the agreement, including the total amount of compensation, will be evaluated for fairness, reasonableness, and consistency with historical and advisory guidelines in general use and acceptable locally. These guidelines include those in ASCE manual 45 or other analyses or data which the contracting parties relied on or used in negotiation of the agreement. Such evaluation shall also consider comparable contracts for which EPA grants have been awarded.

(2) Agreements based upon salary cost times a multiplier including profit. Category B records will be audited. Category C records will not be audited. However, terms of the agreement, including the total amount of compensation and the multiplier, will be evaluated for fairness and reasonableness and consistency with historical and advisory guidelines in general use and acceptable locally. These guidelines include those in ASCE manual 45 or other analyses or data which the contracting parties relied on or used in negotiation of the agreement. Such evaluation shall also consider comparable contracts for which EPA grants have been awarded. Items of overhead or other indirect costs will only be audited to the extent necessary to assure that types of costs found both in overhead and reimbursable direct costs, if any, are properly charged.

(3) Per diem agreements. Category B records will be audited. Category C records will not be audited. Audit will be performed to the extent necessary to determine that hours claimed and classes of personnel used were properly supported. The per diem rates will be evaluated according to the appropriate portions of paragraphs A.2.b. (1) and (2) of this appendix.

(4) Cost plus a fixed fee (profit). All direct costs, overhead, and other indirect costs claimed will be audited to determine that they are reasonable, allowable, and properly supported by the consulting engineer's records. The amount of fixed fee will not be questioned unless the total compensation appears unreasonable when evaluated according to paragraphs A.2.b. (1) and (2) of this appendix.

(5) Fixed price lump sum contracts. Category B and C records will not be audited. The contract amount will not be questioned unless the total compensation appears unreasonable when evaluated in accordance with appropriate portions of paragraphs A.2.b. (1) and (2) of this appendix.

c. If an agreement covers both grant-eligible and ineligible work, access to records will be exercised to the extent necessary to allocate contract work or costs between work grant-eligible for title II construction grant assistance and ineligible work or costs.

d. Under agreements that use two or more methods of compensation, each part of the agreement will be separately audited according to the appropriate paragraph of paragraph (b)(2) of this section.

e. Any audited firm and the grantee will be afforded opportunity for an audit exit conference and an opportunity to receive and comment upon the pertinent portions of each draft audit report. The final audit report will include the written comments, if any, of the audited parties in addition to those of the appropriate State and/or Federal agency(ies).

b. type of contract

1. The percentage-of-construction-cost type of contract, and the multiplier contract, where the multiplier includes profit, may not be used for step 1 or step 2 work initiated after June 30, 1975, when the step 1 or step 2 grant is awarded after June 30, 1975. (A multiplier type of compensation may be used only under acceptable types of contracts; see 40 CFR 35.937–1(d).)

2. Step 1 and step 2 work performed under the percentage-of-construction-cost type of contract and the multiplier contract, where the multiplier includes profit, will be reimbursed and such contracts will not be questioned where such costs are reimbursed in conjunction with a step 3 grant award within the scope of step 2 work contracted for prior to July 1, 1975. However, the current step 2 work will not be continued indefinitely for multiple, subsequent step 3 projects in order to avoid modifying the consultant agreement.

3. Where step 2 work is initiated after June 30, 1975, under contracts prohibited by paragraphs B.1. and B.2. of this appendix, EPA approval may not be given nor grant assistance awarded until the contract's terms of compensation have been renegotiated.

4. Establishing an “upset” figure (an upper limit which cannot be exceeded without a formal amendment to the agreement) under a multiplier contract, where the multiplier includes profit, is not acceptable where renegotiation of such contracts is required. In such renegotiation, the amount of profit must be specifically identified.

5. Total allowable contract costs for grant payment for a contract based on a percentage-of-construction-cost will be based on the following:

a. Where work for the design step is essentially continuous from start of design to bidding, and bid opening for step 3 construction occurs within 1 year after substantial completion of step 2 design work, the total allowable contract costs for grant payment may not exceed an amount based upon the low, responsive, responsible bid for construction.

b. Where work for the design step is not essentially continuous from start of design to bidding, or 1 year or more elapses between substantial completion of step 2 design work and bid opening for step 3 construction, the total allowable contract costs for grant payment may not exceed an amount based upon the lower of:

(1) The consulting engineer's construction cost estimate provided at the time of such substantial completion plus an escalation of this construction cost estimate of up to 5 percent, but not to exceed the consulting engineer's total compensation based on the low, responsive, responsible bid for construction, or

(2) The consulting engineer's construction cost estimate provided at the time of such substantial completion plus a consulting engineer's compensation esclation not to exceed $50,000, but not to exceed the consulting engineer's total compensation based upon the low, responsive, responsible bid for construction.

c. Where the low, responsive, responsible bid for construction would have resulted in a higher consulting engineer's total compensation than paragraph b. of this clause, provides, the Regional Administrator may also consider a reasonable additional compensation for updating the plans and specifications, revising cost estimates, or similar services.

d. The limitations of paragraph B5 apply to all grants awarded under subpart E except that—

(1) If the Regional Administrator had made final payment on a project before December 17, 1975, the limitations do not apply; and

(2) For other projects on which construction for the building and erection of a treatment works was initiated prior to December 17, 1975, the limitations do not apply to any request for engineering fee increases attributable to construction contract awards or change orders approved by the grantee prior to December 17, 1975.

6. Where renegotiation is required under this appendix D, such renegotiation is subject to 40 CFR 35.937–1, 35.937–6, 35.937–7, 35.937–9, and 35.937–10.

c. announcement and selection

The requirements of 40 CFR 35.937–2 through 35.937–4 shall not apply to step 1 work where the step 1 grant was awarded or the initiation of step 1 work was approved by EPA (under 40 CFR 35.917(e)) before March 1, 1976, nor to subsequent step 2 and step 3 work in accordance with 40 CFR 35.937–2(d), if the grantee is satisfied with the qualifications and performance of the engineer employed.

d. required consulting engineering provisions

Effective March 1, 1976, the subagreement clauses required under appendix C–1 must be included in the consulting engineering subagreement before grant assistance for step 1, 2 or 3 will be awarded and before initiation of step 1 work will be approved under 40 CFR 35.917(e) or 35.925–18(a) 3.

e. enforcement

1. Refusal by a consulting engineer to insert the required access clause, or to allow access to its records, or to renegotiate a consulting engineering contract according to the foregoing requirements, will render costs incurred under such contract unallowable. Accordingly, all such costs will be questioned and disallowed pending compliance with this appendix.

2. Where the Regional Administrator determines that the time required to comply with the access to records and type of contract provisions of this appendix will unduly delay award of grant assistance, he may award the grant assistance conditioned upon compliance with this appendix within a specified period of time. In such event, no grant payments for the affected engineering work may be made until such compliance has been obtained.

Appendix E to Subpart E of Part 35—Innovative and Alternative Technology Guidelines
top
1. Purpose. These guidelines provide the criteria for identifying and evaluating innovative and alternative waste water treatment processes and techniques. The Administrator may publish additional information.

2. Authority. These guidelines are provided under section 304(d)(3) of the Clean Water Act.

3. Applicability. These guidelines apply to:

a. The analysis of innovative and alternative treatment processes and techniques under §35.917–1(d)(8);

b. Increased grants for eligible treatment works under §§35.930–5 (b) and (c) and 35.908(b)(1);

c. The funding available for innovative and alternative processes and techniques under §35.915–1(b);

d. The funding available for alternatives to conventional treatment works for small communities under §35.915–1(e);

e. The cost-effectiveness preference given innovative and alternative processes and techniques in section 7 of appendix A to this subpart;

f. The treatment works that may be given higher priority on State project priority lists under §35.915(a)(1)(iii);

g. Alternative and innovative treatment systems in connection with Federal facilities;

h. Individual systems authorized by §35.918, as modified in that section to include unconventional or innovative sewers;

i. The access and reports conditions in §35.935–20.

4. Alternative processes and techniques. Alternative waste water treatment processes and techniques are proven methods which provide for the reclaiming and reuse of water, productively recycle waste water constituents or otherwise eliminate the discharge of pollutants, or recover energy.

a. In the case of processes and techniques for the treatment of effluents, these include land treatment, aquifer recharge, aquaculture, silviculture, and direct reuse for industrial and other nonpotable purposes, horticulture and revegetation of disturbed land. Total containment ponds and ponds for the treatment and storage of waste water prior to land application and other processes necessary to provide minimum levels of preapplication treatment are considered to be part of alternative technology systems for the purpose of this section.

b. For sludges, these include land application for horticultural, silvicultural, or agricultural purposes (including supplemental processing by means such as composting or drying), and revegetation of disturbed lands.

c. Energy recovery facilities include codisposal measures for sludge and refuse which produce energy; anaerobic digestion facilities (Provided, That more than 90 percent of the methane gas is recovered and used as fuel); and equipment which provides for the use of digester gas within the treatment works. Self-sustaining incineration may also be included provided that the energy recovered and productively used is greater than the energy consumed to dewater the sludge to an autogenous state.

d. Also included are individual and other onsite treatment systems with subsurface or other means of effluent disposal and facilities constructed for the specific purpose of septage treatment.

e. The term “alternative” as used in these guidelines includes the terms “unconventional” and “alternative to conventional” as used in the Act.

f. The term “alternative” does not include collector sewers, interceptors, storm or sanitary sewers or the separation thereof; or major sewer rehabilitation, except insofar as they are alternatives to conventional treatment works for small communities under §35.915–1(e) or part of individual systems under §35.918.

5. Innovative processes and techniques. Innovative waste water treatment processes and techniques are developed methods which have not been fully proven under the circumstances of their contemplated use and which represent a significant advancement over the state of the art in terms of meeting the national goals of cost reduction, increased energy conservation or recovery, greater recycling and conservation of water resources (including preventing the mixing of pollutants with water), reclamation or reuse of effluents and resources (including increased productivity of arid lands), improved efficiency and/or reliability, the beneficial use of sludges or effluent constituents, better management of toxic materials or increased environmental benefits. For the purpose of these guidelines, innovative waste water treatment processes and techniques are generally limited to new and improved applications of those alternative processes and techniques identified in accordance with paragraph 4 of these guidelines, including both treatment at centralized facilities and individual and other onsite treatment. Treatment processes based on the conventional concept of treatment (by means of biological or physical/chemical unit processes) and discharge to surface waters shall not be considered innovative waste water treatment processes and techniques except where it is demonstrated that these processes and techniques, as a minimum, meet either the cost-reduction or energy-reduction criterion described in section 6 of these guidelines. Treatment and discharge systems include primary treatment, suspended-growth or fixed-growth biological systems for secondary or advance waste water treatment, physical/chemical treatment, disinfection, and sludge processing. The term “innovative” does not include collector sewers, interceptors, storm or sanitary sewers or the separation of them, or major sewer rehabilitation, except insofar as they meet the criteria in paragraph 6 of these guidelines and are alternatives to conventional treatment works for small communities under §35.915–1(e) or part of individual systems under §35.918.

6. Criteria for determining innovative processes and techniques. a. The Regional Administrator will use the following criteria in determining whether a waste water treatment process or technique is innovative. The criteria should be read in the context of paragraph 5. These criteria do not necessarily preclude a determination by the Regional Administrator that a treatment system is innovative because of local variations in geographic or climatic conditions which affect treatment plant design and operation or because it achieves significant public benefits through the advancement of technology which would otherwise not be possible. The Regional Administrator should consult with EPA headquarters about determinations made in other EPA regions on similar processes and techniques.

b. New or improved applications of alternative waste water treatment processes and techniques may be innovative for the purposes of this regulation if they meet one or more of the criteria in paragraphs e(1) through e(6) of this paragraph. Treatment and discharge systems (i.e., systems which are not new or improved applications of alternative waste water treatment processes and techniques in accordance with paragraph 4 of these guidelines) must meet the criteria of either paragraph 6e(1) or 6e(2), as a minimum, in order to be innovative for the purposes of these guidelines.

c. These six criteria are essentially the same as those used to evaluate any project proposed for grant assistance. The principal difference is that some newly developed processes and techniques may have the potential to provide significant advancements in the state of the art with respect to one or more of these criteria. Inherent in the concept of advancement of technology is a degree of risk which is necessary to initially demonstrate a method on a full, operational scale under the circumstances of its contemplated use. This risk, while recognized to be a necessary element in the implementation of innovative technology, must be minimized by limiting the projects funded to those which have been fully developed and shown to be feasible through operation on a smaller scale. The risk must also be commensurate with the potential benefits (i.e., greater potential benefits must be possible in thecase of innovative technology projects where greater risk is involved). (continued)