(3) Any notice of violation shall describe the nature and extent of the violation.
(4) The Department may take appropriate action for the enforcement of any rules or final orders. Any violation of ORS 196.600 to 196.905 or of any rule or final order of the Department under ORS 196.600 to 196.905 may be enjoined in civil abatement proceedings brought in the name of the State of Oregon; and in any such proceedings the Department may seek and the court may award a sum of money sufficient to compensate the public for any destruction or infringement of any public right of navigation, fishery or recreation resulting from such violation. Proceedings thus brought by the Department shall set forth if applicable the dates of notice and hearing and the specific rule or order of the Department, together with the facts of noncompliance, the facts giving rise to the public nuisance, and a statement of the damages to any public right of navigation, fishery or recreation, if any, resulting from such violation.
(5) In addition to the actions described in OAR 141-085-0085(4) and 141-085-0090 the Department may enter an order requiring any person to cease and desist from any violation if the Department determines that such violation presents an imminent and substantial risk of injury, loss or damage to water resources.
(a) An order under this subsection:
(A) May be entered without prior notice or hearing.
(B) Shall be served upon the person by personal service or by registered or certified mail.
(C) Shall state that a hearing will be held on the order if a written request for hearing is filed by the person subject to the order within 10 days after receipt of the order.
(D) Shall not be stayed during the pendency of a hearing conducted under paragraph (b) of this subsection.
(b) If a person subject to an order under this subsection files a timely demand for hearing, the Department shall hold a contested case hearing before a hearings officer according to the applicable provisions of ORS 183.310 to 183.550. If the person fails to request a hearing, the order shall be entered as a final order upon prima facie case made on the record of the agency.
(c) Neither the Department nor any duly authorized representative of the Department shall be liable for any damages a person may sustain as a result of a cease and desist order issued under this subsection.
(d) The state and local police shall cooperate in the enforcement of any order issued under this subsection and shall require no further authority or warrant in executing or enforcing such order. If any person fails to comply with an order issued under this subsection, the circuit court of the county in which the violation occurred or is threatened shall compel compliance with the Department's order in the same manner as with an order of that court.
(6) Proposed Order to Restore, Cease and Desist Order and/or Civil Penalties. Any written request for a hearing concerning a proposed enforcement order shall admit or deny all factual matters stated in the proposed enforcement order and shall state any and all claims or defenses regarding the alleged violation. Any factual matters not denied shall be presumed admitted, and failure to raise a claim or defense shall be presumed to be a waiver of such claim or defense. Evidence shall not be taken at the hearing on any issue not raised in the written request for hearing.
Stat. Auth.: ORS 196.860, 196.870 & 196.875
Stats. Implemented: ORS 196.800 - 196.990
Hist.: LB 15, f. 2-1-74, ef. 2-25-74; LB 6-1984, f. & ef. 12-17-84, Renumbered from 141-085-0435; LB 2-1991, f. & cert. ef. 3-15-91; LB 3-1992, f. & cert. ef. 6-15-92; DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0090
Civil Penalties
(1) In addition to any other remedy allowed by law or these rules (OAR 141-085), the Department may assess a civil penalty for any violation of the removal-fill law or these rules (OAR 141-085).
(2) More than one civil penalty may be assessed for an unauthorized removal or fill activity.
Example: A civil penalty assessed on an initial violation may be followed by a separate civil penalty for failure to comply with a restoration order issued on the same violation.
(3) Required notice; contents of notice. The Department shall give written notice of Intent to Assess a civil penalty by personal service or by registered or certified mail to the permitholder or person (hereinafter referred to as 'party') incurring the civil penalty. The notice shall include, but not be limited to, the following:
(a) The particular section of the statute, rule, order or authorization involved;
(b) A short and plain statement of the matter asserted or charged;
(c) A statement of the party's right to request a hearing within twenty (20) calendar days of receiving the notice; and
(d) A statement of the amount of civil penalty assessed and terms and conditions of payment.
(e) The party may request a contested case hearing in accordance with procedures described in OAR 141-085-0075.
(4) Calculating the civil penalty.
(a) The amount of civil penalty (F), as expressed in U.S. currency dollars, shall be determined by the Department using the following formula: F = BPCI.
(A) B is the base fine factor of $600;
(B) "P" is the prior knowledge factor to be determined as follows:
(i) A value of 1 shall be applied if the alleged violator was unaware of the removal-fill law at the time of the alleged violation; or
(ii) A value of 2 shall be applied if the alleged violator was aware of the removal-fill law at the time of the alleged violation (e.g., permit non-compliance, prior penalties or other exposure to the Removal-Fill Law);
(iii) A value of 5 shall be applied if the alleged violator had a previous violation. A previous violation exists, for example, if there was an adjudication (either in court or administrative hearing), or the violator failed to appeal an enforcement order (and a final order was issued), or the violator signed a consent order or consent agreement. This value shall not be imposed if the previous violation occurred more than (5) five years prior to the current incident.
(C) The cooperation value (C) shall be determined by the Department after reviewing the past history of the person in taking all feasible steps or procedures necessary or appropriate to correct the violation for which the penalty is being assessed. The value shall be assessed as follows:
(i) A value of 1 shall be applied where the person complies with restoration as requested by the Department without the need for an enforcement order or court action by the Department, or where the Department determines that restoration efforts would be unlikely to benefit the resource;
(ii) A value of 3 shall be applied where the person is not cooperative in complying with restoration as requested by the Department and the Department must issue an enforcement order or obtain a court order to restore.
(D) "I" is water resource impact factor to be determined as follows:
(i) A value of 1 shall be applied if the damaged resource is expected to naturally self-restore within one year; or
(ii) A value of 3 shall be applied if the adverse effects are not expected to naturally self-restore within one year.
(b) In cases where the prior knowledge (P) factor is greater than one (1) and the cooperation (C) factor is greater than one (1), the total amount of the civil penalty (F), in dollars U.S. currency, as determined by applying the calculation methods described in OAR 141-085-0090(4) shall be doubled, not to exceed $10,000 per day.
(5) Failure to pay civil penalty. Once the final adjudication of any civil penalty calculated in the manner described in OAR 141-085-0090(4) has been completed in accordance with OAR 141-085-0090(3), the amount of the civil penalty shall increase by the amount of the original civil penalty for every twenty (20) calendar days that pass without the alleged violator remitting payment to the Department for the full amount of the civil penalty and the Department taking receipt of the payment. In no case shall the amount of the civil penalty be increased by more than ten times the original civil penalty amount. If a civil penalty or any portion of the civil penalty is not paid as required by OAR 141-085-0090(5), interest shall accrue at the rate of nine percent per annum pursuant to ORS 82.010 on the unpaid balance.
(6) Civil penalty relief. The Department may, upon written request of the alleged violator assess a civil penalty as described in OAR 141-085-0090 and including evidence of financial hardship, remit or mitigate the amount of any civil penalty. The request shall be received within twenty (20) calendar days from the date of personal service or mailing of the notice of civil penalty as described in OAR 141-085-0090(3). Evidence provided as to the alleged violator's economic and financial condition may be presented without prejudice to any claim by the person that no violation has occurred or that the person is not responsible for the violation.
Stat. Auth.: ORS 196.890
Stats. Implemented: ORS 196.800 - 196.990
Hist.: LB 4-1986, f. & ef. 4-8-86; LB 3-1991, f. 6-14-91, cert. ef. 7-1-91; LB 3-1992, f. & cert. ef. 6-15-92; DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 1-2004, f. & cert. ef. 5-21-04
141-085-0095
Request to Close Specified Waters of the State to the Issuance of Removal-Fill Authorizations
(1) The Department may request the Oregon Water Resources Commission (OWRC) to close, by administrative rule, specified waters of the state to the issuance of removal-fill authorizations (ORS 196.840).
(2) Any state resource agency listed in ORS 196.825 may make such a request of the Department. In determining whether or not to submit a request to the OWRC the Department shall consider:
(a) The reasons for requesting a closure;
(b) The specific waters of the state to be affected;
(c) The effect, including economic effects, of the proposed closure on potential future applicants;
(d) The effect, including benefits, of the proposed closure on aquatic life, water quality and public use of the waters; and
(e) The time period the closure should be recommended to be in effect.
(3) Prior to submitting a closure request to the OWRC, the Department shall hold at least one public hearing within the affected watershed. Interested and affected parties, including local government and watershed councils are to be notified at least thirty (30) calendar days prior to the hearing date. Public comment on the proposal shall be accepted at least fourteen (14) calendar days following the last hearing. The Department shall issue a report explaining the proposal and outlining the reasons for considering a closure. Notice of the Department's final decision shall be provided all participating parties and parties of interest as identified by the Department.
Stat. Auth.: ORS 196.840
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2004, f. & cert. ef. 5-21-04
141-085-0096
Monitoring; Annual Report; Public Information and Education
(1) Program Monitoring. Pursuant to ORS 196.910, the Department will monitor removal and fill authorized under these rules to determine:
(a) Compliance with permit conditions;
(b) The effectiveness of permit conditions in achieving the policies of these rules; and
(c) The adverse impacts of authorized activities on salmonid spawning and rearing habitat and wetland functional attributes.
(2) Annual Reporting. Pursuant to ORS 196.885, commencing with fiscal year 2002-2003 and continuing each fiscal year thereafter, the Department shall submit an annual report to the State Land Board on the activities conducted under these rules. The report shall be delivered to the State Land Board and posted on the Department's website no later than 120 days after the end of the fiscal year. The report shall also be provided to the appropriate legislative committee(s). The annual report shall include the following:
(a) The number of removal-fill authorizations applied for, denied and authorized. For all authorizations granted or outstanding during the prior year, a separate summary shall be included for fills and removals, organized by river or other water body that shows:
(A) The total number of authorizations, the number of new authorizations and the number of renewal authorizations.
(B) The volume and/or wetland acreage of removals and fills authorized during the past year, and to the extent possible, the volume and/or wetland acreage of fills and removals completed during the past year.
(C) The areal extent of wetlands lost, by habitat type, and the areal extent of wetlands gained, by habitat type, through compensatory wetland mitigation.
(b) A summary of compensatory mitigation measures, including a description of each compensatory mitigation project approved during the past year including the location and size of each compensatory mitigation project, whether creation, enhancement or restoration, and a report on the status of all compensatory mitigation projects pending or completed during the past year.
(c) A summary of enforcement activities, including:
(A) The number of complaints reported.
(B) The number of compliance investigations conducted.
(C) The results of compliance actions, including:
(i) The number of cases resolved by either voluntary compliance, administrative hearings or judicial enforcement proceedings;
(ii) The penalties assessed; and
(iii) The penalties recovered.
(d) A description of staffing, including the number of full-time equivalent positions devoted to the permit program and, for each position, the qualifications and job description.
(e) The report on the Oregon Wetlands Mitigation Bank Revolving Fund Account as required under ORS 196.640 and 196.655.
(f) The number of and average time for responding to notices received by local governments and the number of responses that took more than thirty (30) calendar days.
(g) The number of wetland conservation plans approved by the Department and a description of each, including the issues raised during the approval process.
(3) Public Information. The Department shall develop and maintain a public information program to educate permit applicants and the general public about:
(a) Wetland functions and values;
(b) The status and trends of Oregon's wetlands;
(c) The Statewide Wetlands Inventory; and
(d) Wetland identification, regulations and permit requirements.
(4) Technical Assistance and Cooperation. Upon request, within the limits of staffing ability and available resources, the Department shall provide technical assistance to other state agencies, local governments and the public in identifying wetlands.
Stat. Auth.: ORS 196.885, 196.910 & 196.688
Stats. Implemented: ORS 196.800 - 196.990 & 196.600 - 196.692
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04
141-085-0115
Compensatory Mitigation
(1) The Department may require compensatory mitigation as a condition of an authorization to compensate for reasonably expected adverse impacts to water resources of the state and navigation, fishing and public recreation uses on waters of the state other than freshwater wetlands or estuarine areas. Such conditions impose obligations on the permit holder beyond the expiration of the authorization.
(2) Such compensatory mitigation may include, but is not limited to:
(a) Offsite or onsite enhancement (e.g., planting or seeding riparian vegetation or exposing enclosed culverted systems) of water resources of the state;
(b) Offsite or onsite improvements to enhance navigation, fishing or public recreation uses of waters of the state; or
(c) Compensation to a third party, as approved by the Department, for the purpose of watershed health or to improve the navigation, fishing or public recreation uses of waters of the state. A permit holder, with the approval of the Department, may contract with a third party to construct, monitor or maintain the compensatory mitigation site. The permit holder remains responsible for compliance with the compensatory mitigation conditions unless the authorization is transferred to another entity in accordance with these rules.
(3) The Department may approve of compensatory mitigation for impacts to waters of the state other than freshwater wetlands or estuarine areas, when the applicant demonstrates in writing that the compensatory mitigation plan will replace or provide comparable substitute for water resources of the state and/or navigation, fishing and public recreation uses lost by project development.
(4) The Department may require some form of long term protection for the compensatory mitigation site.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: LB 7-1994, f. 12-15-94, cert. ef. 1-1-95; DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0121
Freshwater Compensatory Wetland Mitigation (CWM) Applicability, General Requirements; Functional Assessments
(1) The following rule sections, OAR-141-085-0121 to OAR-141-085-0151, apply to removal-fill that occur within freshwater wetlands and do not apply to removal-fill:
(a) Within estuarine wetlands covered by ORS 196.830 and OAR-141-085-0240 thru 141-085-0266, except as specifically noted in the estuarine mitigation rules or where estuarine wetland restoration or enhancement is proposed to compensate for impacts to freshwater wetlands; or
(b) Within areas covered by an approved Wetland Conservation Plan (WCP) authorized under ORS 196.668 to 196.692.
(2) For projects where reasonably expected adverse impacts to the water resources including wetland functions cannot otherwise be avoided, or minimized, a CWM plan will be required to compensate for the reasonably expected adverse impacts of the project by replacing the functional attributes of the wetland impacted by project development. Compensatory wetland mitigation shall be limited to replacement of the functional attributes of the lost wetland. The requirements to provide CWM impose obligations on the permit holder that extend beyond the expiration date of the authorization.
(3) For projects described in (2) requiring CWM and involving project development on 0.2 (two-tenths) of an acre or less of wetlands, there is a rebuttable presumption that on-site CWM is impracticable. The applicant may propose to fulfill CWM requirements through off-site CWM without first considering on-site CWM.
(4) For projects described in (2) requiring CWM involving project development impacts greater than 0.2 (two-tenths) of an acre, the applicant shall first consider on-site CWM to provide the replacement of the functional attributes of the lost wetland. If on-site CWM is impracticable as documented by the applicant, off-site CWM shall be utilized. In considering off-site CWM, the applicant may create, restore or enhance a wetland or if the project development occurs within the service area of an established wetland mitigation bank, the applicant may purchase credits, if available, from the bank to fulfill CWM requirements so long as the functional attributes of the lost wetland are replaced. If no mitigation bank is available, CWM may be fulfilled through payment to provide as described in OAR 141-085-0131.
(5) The Department will review the CWM plan for sufficiency and compliance with these rules. The Department may make recommendations for improvements to CWM plans, at any time prior to the permit decision, based on the demonstrated success of existing CWM projects. The Department will approve the final CWM plan as a part of the individual removal-fill permit. In approving the final CWM plan, the Department may, after consulting with the applicant, require conditions necessary to ensure success of the CWM plan and to ensure the requirements in these rules are met.
(6)To the extent possible, the Department shall develop and make available to the public a listing of known compensatory wetland mitigation sites (e.g., wetland mitigation banks).
(7) The applicant shall complete and include in the application an assessment of wetland functional attributes. The assessment shall assess:
(a) Existing functional attributes of the entire wetland at the proposed project impact site;
(b) Functional attributes reasonably expected to be adversely impacted, including those functional attributes decreased or lost due to the proposed project;
(c) Existing functional attributes at the proposed CWM site, if the site is currently wetland; and
(d) The net gain or loss of specific functional attributes at the direct CWM site as a result of the proposed CWM project.
(8) Wetland functional attributes to be assessed include, but are not limited to:
(a) Water quality and quantity functions;
(b) Fish and wildlife habitat functions;
(c) Native plant communities and species diversity functions; and
(d) Recreational and educational values.
(9) A functional assessment of the impact site is not needed if the proposed CWM plan utilizes payment to provide or the purchase of credits from a wetland mitigation bank to satisfy all the compensatory wetland mitigation requirements.
(10) The Oregon Freshwater Wetland Assessment Method shall not be used to satisfy the requirements of OAR 141-085-0121(7).
(11) HGM is the preferred, but not required, functional assessment method. When HGM is used, the Willamette Valley HGM guidebook should be used for appropriate HGM classes in the Willamette Valley; until additional guidebooks are developed by the Department, the "Judgmental Method" in the Willamette Valley Guidebook may be used to assess wetland functions in other regions. The judgmental method provides a consistent framework to consider the basic functional attributes of wetlands as described in OAR 141-085-0121(8)(a) thru (c). It also offers a list of observable field indicators of the conditions and processes that contribute to these functional attributes and guidance on making qualitative rating of these functional attributes without reference to the data set or numeric scoring models.
(12) If best professional judgment is used to evaluate any or all wetland functional attributes, a discussion of the basis of the conclusions is required. For example, if the water quality function is determined to be "low," a detailed rationale based upon direct measurement or observation of indicators of water quality function must be discussed.
(13) Additional assessments or data may be required by the Department if the functional assessment results, public/agency review comments, or the Department's review indicate that there may be reasonably expected adverse impacts to rare or listed plant or animal species, adjoining property owners, or if the project's effects are not readily apparent.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0126
Requirements for All CWM
(1) CWM shall replace:
(a) Wetland habitat type(s) impacted by the project, as classified per Cowardin system and class (e.g., palustrine forested); and
(b) HGM class/subclass(es) impacted by the project (e.g., riverine impounding), using the Oregon HGM Statewide Classification (Oregon Department of State Lands 2001); and
(c) The functional attributes of the lost wetland (impact wetland).
(2) The Department may approve exceptions to the requirements of OAR 141-085-0126(1) if the applicant demonstrates, in writing, that the alternative CWM:
(a) Is environmentally preferable;
(b) Replaces wetland functions that address problems (such as flooding) that are identified in a watershed management plan or water quality management plan approved by a watershed council or public agency;
(c) Replaces wetland types (Cowardin/HGM) and functions historically lost in the region; or
(d) Replaces rare or uncommon plant communities appropriate to the region, as identified in the most recent ONHP plant community classification.
(3) A permit holder, with the approval of the Department, may at any time contract with a third party to construct, monitor or maintain the CWM site. The permit holder cannot delegate responsibility for compliance with the CWM requirements unless the authorization has been transferred in accordance with OAR 141-085-0034.
(4) For linear projects (e.g., roads or utility lines with wetland impacts in several watersheds), the applicant may compensate for all wetland impacts at a single CWM site.
(5) CWM:
(a) Shall be completed prior to or concurrent with the authorized removal-fill project. The Department may approve non-concurrent CWM if the applicant clearly demonstrates, in writing, the reason for the delay or that there is benefit to the water resources in doing so. The ratio of CWM required for delayed projects may be increased according to the provisions of OAR-141-085-0136.
(b) Shall include native vegetation plantings aimed at re-establishment of a dominance of native plants.
(c) Shall not rely on features or facilities that require frequent and regular long-term maintenance and management. For example, permanent water control structures may be acceptable, whereas pumping from a groundwater well to provide hydrology is not.
(6) CWM sites may fulfill multiple purposes including stormwater retention or detention provided:
(a) The requirements of OAR 141-085-0126(1) and (2) are met;
(b) No alteration is required to maintain the stormwater functions that would degrade the functional attributes; and
(c) The runoff water entering the CWM site has been pretreated to the level necessary to assure that state water quality standards and criteria are met in the mitigation area.
(7) CWM using wetland enhancement must conform to the following additional requirements. The CWM shall:
(a) Be conducted only on degraded wetlands as defined in OAR 141-085-0010;
(b) Result in a demonstrable net gain in wetland functions at the CWM site as compared to those functions lost or diminished at the wetland conversion site and those functional attributes previously existing at the CWM site;
(c) Not replace or diminish existing wetland functional attributes with different wetland functional attributes unless the applicant justifies, in writing, that it is environmentally preferable to do so;
(d) Not consist solely of the conversion of one HGM or Cowardin class of wetland to another unless the applicant can demonstrate that it is environmentally preferable to do so;
(e) Identify the causes of wetland degradation at the CWM site and the means by which the CWM plan will reverse, minimize or control those causes of degradation in order to ensure self-sustaining success; and
(f) Not consist solely of removal of non-native, invasive vegetation and replanting or seeding of native plant species.
(8) A conservation easement, deed restriction or similar legally binding instrument shall be part of a CWM plan.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0131
Requirements for CWM Involving Wetland Mitigation Banks, Payment-to-Provide or Conservation
(1) The requirements in this section are in addition to the general requirements in OAR 141-084-0121.
(2) Mitigation Bank Credits. Purchase of mitigation bank credits from an appropriate and approved mitigation bank is preferable to payment to provide mitigation. The Department will approve the bank option only after on-site mitigation has been examined and found to be impracticable. Documentation of the purchase of the required number of mitigation bank credits must be received by the Department prior to issuance of the authorization.
(3) Payment to provide mitigation:
(a) The individual removal-fill permit or letter of authorization for an activity shall not be issued until payment has been made in the amount identified in the CWM plan as approved by the Department. Once an approved removal-fill permit activity has begun as proposed, the payment to provide mitigation payment shall be considered as non-refundable.
(b) The amount to pay to the Department to provide CWM shall be the average cost of credits available from all active mitigation banks in the state as compiled annually by the Department.
(4) Conservation in lieu:
(a) Conservation of wetlands may be used for meeting the CWM requirement when the wetland proposed for conservation:
(A) Supports a significant population of rare plant or animal species; and/or
(B) Is a rare wetland type (S1 or S2 according to the Oregon Natural Heritage Program); or
(C) Is a vernal pool, fen or bog.
(b) Conservation in lieu should be encouraged as the preferred CWM option when the impact site is a wetland type that is exceptionally difficult to replace, such as vernal pools, fens and bogs.
(c) There is no established ratio for indirect CWM using conservation in lieu. The acreage needed under conservation in lieu will be determined on a case-by-case basis through negotiation between the applicant and the Department.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0136
Ratio Requirements for CWM
(1) The purpose of CWM ratios is to:
(a) Ensure that the state's wetland resource base is maintained as required in ORS 196.672;
(b) Offset the temporal loss of wetland functions as compensatory mitigation sites mature (i.e., become fully functional replacement of the lost, impacted wetland);
(c) Replace wetland functions that may be size dependent; and
(d) Compensate for the likelihood of success in the different CWM methods (creation, restoration, enhancement). The methods are techniques used to achieve the replacement of functional attributes lost from the impacted wetland.
(2) Except as provided in Sections (3) through (6) of this section, the following minimum ratios shall be used in the development of CWM plans:
(a) Restoration: One (1) acre of restored wetland for one (1) acre of impacted wetland.
(b) Creation: One and one-half (1.5) acres of created wetland for one (1) acre of impacted wetland.
(c) Enhancement: Three (3) acres of enhanced wetland for one (1) acre of impacted wetland.
(d) Enhancement of cropped wetland as determined by the Department: Two (2) acres of enhanced cropped wetland for one (1) acre of impacted wetland. Cropped wetland is converted wetland that is regularly plowed, seeded and harvested in order to produce a crop for market. Pasture, including lands determined by the Natural Resources and Conservation Service to be "farmed wetland pasture," is not cropped wetland.
(e) Conservation in Lieu: Variable: See OAR 141-085-0131(4).
(3) The Department shall double the minimum ratio requirements for project development impacting existing CWM sites; for example, using enhancement to compensate for impacts to an existing CWM site will require a ratio of six (6) acres enhanced for every one (1) acre impacted.
(4) The Department may increase the ratios when:
(a) Mitigation is proposed to compensate for an unauthorized removal or fill activity; and/or
(b) Mitigation is not proposed for implementation concurrently with the authorized impact.
(5) At the option of the applicant, CWM may consist of any one or a combination of the following CWM ratios for commercial aggregate mining operations where both the mining operation and the CWM are conducted on converted wetlands (not including pasture):
(a) One (1) acre of wetland and open water habitat, with depths less than thirty-five (35) feet, for one (1) acre of wetland impacted;
(b) Three (3) acres of wetland and open water habitat, with depths greater than thirty-five (35) feet, for one (1) acre of wetland impacted;
(c) One (1) acre of a combination of restored, created or enhanced wetland and upland, comprising at least fifty percent (50%) wetland, for one (1) acre of wetland impacted.
(6) The Department may also apply the following CWM measures for commercial aggregate mining operations on converted wetland (not including pasture):
(a) Allow for staged CWM or mined land reclamation required under ORS 517.700; or
(b) Based on the value the Department determines under OAR 141-085-0131(3), allow the applicant, upon approval by the Department, to pay the entire cost of CWM:
(A) On an annual basis for a period not to exceed twenty (20) years over the life expectancy of the operation, whichever is less; or
(B) On an annual basis over time at a monetary rate per cubic yard or ton of aggregate material removed annually from the site.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0141
Requirements for All CWM Plans/Application Requirements
(1) On-site or off-site CWM involving the creation, restoration and/or enhancement of wetlands by the applicant. A CWM plan shall, at a minimum, include:
(a) CWM site information including:
(A) Area (size) of the CWM wetland proposed for impact relative to the total area of the wetland.
(B) CWM site ownership information (name, address, phone). If this is different from the applicant, copies of legal agreements granting permission to conduct the CWM and willingness of the property owner to provide long-term protection are required;
(C) Physical Location (Township, Range, Quarter Quarter Section and tax lot(s)) and a USGS or similar map showing the CWM site location relative to the impact site.
(b) Existing physical and biological baseline information of CWM site including:
(A) A wetland determination/delineation report (OAR 141-090).
(B) A functional assessment, except when PTP or purchase of credits from a wetland mitigation bank is proposed, of any existing wetlands at the CWM site, proposed for enhancement or other alteration, including a description of the factors leading to the degraded condition of the site (OAR 141-085-0121).
(C) A description of the major plant communities and their relative distribution, including the abundance of exotic species.
(D) A general description of water source, duration, frequency of inundation or saturation, depth of surface or subsurface water and approximate location of all water features (wetlands, streams, lakes) within 500 feet of the CWM site.
(E) HGM and Cowardin classification of any wetlands present within the CWM site.
(c) CWM plan description including:
(A) CWM plan goals, objectives and success criteria.
(B) The CWM concept in general terms including a description of how the plan, when implemented, will restore, reverse, minimize or control the causes of wetland degradation and ensure that the wetland functions of the impacted wetland are replaced.
(C) A description of the rationale for the CWM site selection.
(D) Proposed water source, duration, frequency of inundation or saturation of the CWM project.
(E) Any known CWM site constraints or limitations.
(F) Proposed HGM and Cowardin classification.
(G) Proposed net losses and gains of wetland functions.
(H) A description of how the applicant will maintain and protect the direct CWM site beyond the monitoring period.
(I) CWM construction plans including:
(i) Scaled site plan showing CWM project boundaries, existing wetlands, restoration, creation and enhancement areas.
(ii) Scaled grading plan with existing and proposed contours and cross section locations.
(iii) Description of construction methods (access, equipment).
(iv) Schematic of any proposed hydrological structures.
(v) Scaled cross sections showing elevations, distance.
(vi) Planting plan (with species, size, number, spacing and installation methods).
(vii) Monitoring plan (schedule, timetable, methods).
(viii) Contingency plan for CWM failures.
(ix) Implementation schedule and construction sequence.
(J) A reference site, combination of reference sites, or reference data of the same HGM class or subclass (e.g. from the Willamette Valley HGM Guidebook) and representing a less functionally-altered condition than the CWM site. Compare and relate the sites and/or data to the CWM goal.
(K) Provisions for a financial security instrument (OAR 141-085-0176), if the impact is greater than .2 (two-tenths) of an acre. The financial security instrument is not required for the application but will be required prior to permit issuance.
(L) Plans for restoration projects shall include data substantiating that the site was formerly, but is not currently, a wetland (e.g. a wetland delineation report).
(M) Plans for vegetated buffers, if needed, to protect the viability and functions of the CWM site.
(N) Plans for the long term protection of the CWM site:
(i) The individual removal-fill permit along with site access control (e.g. fencing, signing) is usually sufficient legal means to achieve maintenance and long-term protection of mitigation sites. However, in some instances compensatory mitigation sites and compensatory wetland mitigation sites will need to be permanently protected from destruction with appropriate real estate instruments or agreements (e.g. conservation easements, deed restrictions, long-term management agreements with land trusts or public ownership). Situations where such protection will be required include but are not limited to:
(A) When the permit holder is likely to sell the mitigation site within five (5) years of project completion;
(B) When the permit holder is an absentee owner of the mitigation site;
(C) When the permit holder is not likely to actively participate in managing and maintaining the mitigation site; or
(D) When the permit holder is not the owner of the mitigation site.
(ii) The applicant shall offer a preferred method and justification.
(iii) The Department will make the final determination for the need and type of long-term protection.
(2) Other CWM. A CWM plan using conservation in lieu must include:
(a) Written documentation that the requirements in OAR141-085-0131(4) are met.
(b) A conservation plan that shall include:
(A) Maps showing the wetland conservation area including all delineated wetlands to be conserved;
(B) The surrounding land uses and an analysis of the probable effects of those land uses and activities on the conserved wetlands;
(C) Measures that may be necessary to minimize the effects of surrounding land uses and activities on the conserved wetlands;
(D) Identification of the party(ies) responsible for long term protection of the conserved wetlands;
(E) A draft legally binding long term protection instrument (e.g. conservation easement); and
(F) A draft long-term management plan that addresses the specific requirements of the wetlands to be conserved.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 1-2003, f. & cert. ef. 7-10-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0146
Removal-Fill Authorization Conditions for CWM Plans
(1) For permits involving CWM:
(a) The approved CWM plan shall become part of the removal fill authorization and, by reference, all portions of the CWM plan shall become conditions of the authorization.
(b) Additional compensatory mitigation conditions may be included in the authorization.
(c) All compensatory mitigation conditions shall be enforceable until the CWM is deemed successful by the Department in accordance with OAR 141-085-0151, regardless of the authorization expiration date.
(2) Conditions for authorizations shall also state:
(a) If applicable, the amount of the payment to provide mitigation made by the applicant and how it was calculated; and
(b) If applicable, the mitigation bank utilized; and
(c) The loss of wetland by area, Cowardin and HGM class(es), and function(s) of wetland(s) expected to be lost or impaired; and
(d) The applicant's remaining responsibility after payment to provide mitigation payment was made, if any; and
(e) No removal or fill of any amount of material shall be permitted within compensatory wetland mitigation sites without prior authorization of the Department.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04
141-085-0151
Monitoring Requirements for CWM Plans Involving On-site or Off-site Creation, Restoration or Enhancement of Wetlands
(1) The purpose of the CWM monitoring requirement is to provide information for the Department to:
(a) Determine if the CWM complies with the conditions of the authorization;
(b) Evaluate whether the CWM meets the goals, objectives and success criteria of the CWM plan; and
(c) Provide information for removal/fill program monitoring.
(2) The permitholder shall monitor the CWM site and provide to the Department:
(a) A post construction report demonstrating "as-built" conditions including grading and discussing any variation from the approved plan. Unless waived by the Department, the post construction report shall be submitted within ninety (90) calendar days of completing grading;
(b) An annual written monitoring report that includes all data necessary to document compliance with CWM conditions and success in meeting the CWM goals. These data may include photographs, topographic surveys, plant survival data, botanical surveys, results from functional assessment, hydrologic data and other information as required to demonstrate compliance. The report shall include the following sections:
(A) Introduction;
(B) Goals, objectives and success criteria;
(C) Methods;
(D) Results;
(E) Summary and recommendations;
(F) Figures;
(G) Appendices with data and photographs.
(3) Monitoring shall be conducted for 5 years unless otherwise specified by the Department.
(4) The Department may require modifications to the CWM plan as well as require additional monitoring any time the CWM is failing to meet the CWM goals.
(5) At the end of the five (5) year monitoring period, the Department shall determine if the mitigation project meets the CWM success criteria. If it fails to meet the success criteria, the Department may require modifications to the CWM site as well as additional site monitoring.
(6) When the CWM complies with the compensatory mitigation success criteria, as described in the approved removal-fill authorization, the Department shall notify the permit holder in writing of compliance with the authorization's conditions and that additional monitoring is not required. If the Department fails to notify the permitholder within ninety (90) calendar days of the Department's receipt of the final monitoring report, the permit shall be deemed in compliance and no further monitoring required.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04; DSL 1-2006, f. 3-21-06, cert. ef. 3-27-06
141-085-0156
Payments; Expenditure of Funds for Compensatory Wetland Mitigation Payment to Provide; Agency Accounting of Payment to Provide Funds and Expenditures
(1) The Department shall utilize the Oregon Wetlands Mitigation Bank Revolving Fund Account authorized pursuant to ORS 196.640 et seq. to hold and disperse money collected from the program.
(a) The Department shall expend funds collected under the payment to provide option of compensatory wetland mitigation only to:
(A) Restore, enhance, or create wetlands (including acquisition of land or easements as necessary to conduct restoration, enhancement or creation projects) as compensatory mitigation to compensate or replace wetland functional attributes lost or diminished as result of an approved removal-fill authorization activity;
(B) Purchase credits from an approved wetland mitigation bank for the purpose of fulfilling the CWM requirements of an approved removal-fill authorization activity.
(C) Monitor the compensatory wetland mitigation; or
(D) Conduct site management for the compensatory mitigation project as necessary to assure that the mitigation is successful.
(2) The Department shall expend funds collected under the payment to provide option of compensatory wetland mitigation only within the geographic region, as defined by OAR-141-085-0010 of these rules, in which the wetland functional attributes occur, unless the Department determines, in writing that expending the funds is not feasible or appropriate within a respective region.
(3) The Department shall expend funds collected from specific approved removal-fill activities within two (2) years from the authorization issuance date unless the Department determines, in writing, that meeting the two year time limit is not feasible.
(4) Third party recipients of funds collected under the payment to provide option of a compensatory wetland mitigation plan shall sign a written agreement provided by the Department that requires the recipient(s) to utilize the funds for specific wetland compensatory mitigation that has been reviewed and approved by the Department. Such review and approval will also be contingent on the submission of a specific monitoring program that is acceptable to the Department.
(5) All payment to provide monies collected and expended, as well as the success of the compensatory wetland mitigation, authorized by the Department in accordance with these rules, shall be recorded by the Department and shall include:
(a) A description of the compensatory wetland mitigation funded and including an evaluation of the success of these projects in meeting project goals.
(b) A description of the wetland functional attributes lost or diminished from approved removal-fill activities summarized individually and cumulatively by basin;
(c) A summary of the amount of payments collected and expended on individual compensatory wetland mitigation projects as well as cumulatively by basin.
(d) A description of the wetland functions expected to accrue as a result of compensatory wetland mitigation projects funded in accordance with these rules and summarized by basin and statewide.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04
141-085-0161
Department Responsibilities Under Payment to Provide Option
(1) The Department, by eliminating the applicant's responsibility for compensatory wetland mitigation by approving a removal-fill authorization including a payment to provide option, assumes the following responsibilities to:
(a) Defend the sufficiency of the compensatory wetland mitigation plan to compensate or replace the wetland functional attributes lost or diminished; and
(b) Monitor, manage, and otherwise assure the success of the compensatory wetland mitigation project performed by the Agency Department or designated third party(ies) under these rules.
(2) The Department, as part of an intergovernmental agreement, may transfer or extend the Department's responsibility for the compensatory wetland mitigation plan to another person or governmental agency.
Stat. Auth.: ORS 196.825
Stats. Implemented: ORS 196.800 - 196.990
Hist.: DSL 6-2002, f. 11-25-02 cert. ef. 1-15-03; DSL 2-2003(Temp) f. & cert. ef. 11-26-03 thru 5-23-04; DSL 1-2004, f. & cert. ef. 5-21-04
141-085-0166
Advance Mitigation
(1) As part of an existing, active individual removal-fill permit application process, an applicant may request that the Department consider the possibility that the applicant's proposed CWM project, if successful, could result in producing potential mitigation credits in excess of those needed to satisfy the requirements of OAR 141-085-0029(5).
(2) If the applicant desires to preserve the option of possibly receiving additional mitigation credit for future projects from the excess credits identified under subsection (1) above, then the following additional information shall be submitted as a part of the applicant's Compensatory Wetland Mitigation Plan:
(a) Identify the specific area(s) of the CWM site that compensates for the specific permitted impact, and identify the specific areas of the CWM site that are proposed for credit in future projects;
(b) Include separate protection instruments for each area of the CWM site (existing and proposed);
(c) Provide a separate monitoring program foreach section of the CWM site (existing and proposed); (continued)