Loading (50 kb)...'
(continued)
P Inorganic Arsenic Emissions From .............. X ..............
Arsenic Trioxide and Metallic
Arsenic Production Facilities.
Q Radon Emissions From Department .............. .............. ..............
of Energy Facilities.
R Radon Emissions From .............. .............. ..............
Phosphogypsum Stacks.
S (Reserved)....................... .............. .............. ..............
T Radon Emissions From the Disposal .............. .............. ..............
of Uranium Mill Tailings.
U (Reserved)....................... .............. .............. ..............
V Equipment Leaks (Fugitive .............. X ..............
Emission Sources).
W Radon Emissions From Operating .............. .............. ..............
Mill Tailings.
X (Reserved)....................... .............. .............. ..............
Y Benzene Emissions From Benzene .............. X ..............
Storage Vessels.
Z-AA (Reserved)....................... .............. .............. ..............
BB Benzene Emissions From Benzene .............. X ..............
Transfer Operations.
CC-EE (Reserved)....................... .............. .............. ..............
FF Benzene Waste Operations......... .............. X ..............
----------------------------------------------------------------------------------------------------------------
(iii) Hawaii. The following table identifies delegations as of October 21, 2004:
Delegation Status for National Emissions Standards for Hazardous Air
Pollutants for Hawaii
------------------------------------------------------------------------
Subpart Hawaii
------------------------------------------------------------------------
A.................. General Provisions................... X
B.................. Radon Emissions From Underground
Uranium.
C.................. Beryllium............................ X
D.................. Beryllium Rocket Motor Firing........ X
E.................. Mercury.............................. X
F.................. Vinyl Chloride.......................
G.................. (Reserved)...........................
H.................. Emissions of Radionuclides Other Than
Radon From Department of Energy
Facilities.
I.................. Radionuclide Emissions From Federal
Facilities Other Than Nuclear
Regulatory Commission Licensees and
Not Covered by Subpart H.
J.................. Equipment Leaks (Fugitive Emission X
Sources) of Benzene.
K.................. Radionuclide Emissions From Elemental
Phosphorus Plants.
L.................. Benzene Emissions from Coke By-
Product Recovery Plants.
M.................. Asbestos............................. X
N.................. Inorganic Arsenic Emissions From
Glass Manufacturing Plants.
O.................. Inorganic Arsenic Emissions From
Primary Copper Smelters.
P.................. Inorganic Arsenic Emissions From
Arsenic Trioxide and Metallic
Arsenic Production Facilities.
Q.................. Radon Emissions From Department of
Energy Facilities.
R.................. Radon Emissions From Phosphogypsum
Stacks.
S.................. (Reserved)...........................
T.................. Radon Emissions From the Disposal of
Uranium Mill Tailings.
U.................. (Reserved)...........................
V.................. Equipment Leaks (Fugitive Emission X
Sources).
W.................. Radon Emissions From Operating Mill
Tailings.
X.................. (Reserved)...........................
Y.................. Benzene Emissions From Benzene X
Storage Vessels.
Z-AA............... (Reserved)...........................
BB................. Benzene Emissions From Benzene X
Transfer Operations.
CC-EE.............. (Reserved)...........................
FF................. Benzene Waste Operations............. X
------------------------------------------------------------------------
(iv) Nevada. The following table identifies delegations as of October 21, 2004:
Delegation Status for National Emissions Standards for Hazardous Air Pollutants for Nevada
----------------------------------------------------------------------------------------------------------------
Air Pollution Control Agency
-----------------------------------------
Subpart Clark Washoe
Nevada DEP County County
----------------------------------------------------------------------------------------------------------------
A............................. General Provisions.................... X X
B............................. Radon Emissions From Underground ............ ............
Uranium.
C............................. Beryllium............................. X X X
D............................. Beryllium Rocket Motor Firing......... X X
E............................. Mercury............................... X X X
F............................. Vinyl Chloride........................ X X
G............................. (Reserved)............................ ............ ............
H............................. Emissions of Radionuclides Other Than ............ ............
Radon From Department of Energy
Facilities.
I............................. Radionuclide Emissions From Federal ............ ............
Facilities Other Than Nuclear
Regulatory Commission Licensees and
Not Covered by Subpart H.
J............................. Equipment Leaks (Fugitive Emission X ............
Sources) of Benzene.
K............................. Radionuclide Emissions From Elemental ............ ............
Phosphorus Plants.
L............................. Benzene Emissions from Coke By Product ............ ............
Recovery Plants.
M............................. Asbestos.............................. ............ X X
N............................. Inorganic Arsenic Emissions From Glass X ............
Manufacturing Plants.
O............................. Inorganic Arsenic Emissions From X ............
Primary Copper Smelters.
P............................. Inorganic Arsenic Emissions From X ............
Arsenic Trioxide and Metallic Arsenic
Production Facilities.
V............................. Equipment Leaks (Fugitive Emission X ............
Sources).
BB............................ Benzene Emissions From Benzene X ............
Transfer Operations.
FF............................ Benzene Waste Operations.............. X ............ ............
----------------------------------------------------------------------------------------------------------------
(10) The following table lists the delegation status of specific Part 61 Subparts that have been delegated unchanged to state and local air pollution control agencies in Region 10. An “X” indicates the subpart has been delegated, subject to all the conditions and limitations set forth in federal law, regulations, policy, guidance, and determinations. Some authorities cannot be delegated and are retained by EPA. These include certain General Provisions authorities and specific parts of some standards. The dates noted at the end of this table indicate the effective dates of federal rules that have been delegated. Any amendments made to these rules after this effective date are not delegated.
Delegation Status for Part 61 Standards_Region 10 \1\
--------------------------------------------------------------------------------------------------------------------------------------------------------
AK ID Oregon Washington
--------------------------------------------------------------------------------------------------------------------------
Subpart \2\ LRAPA NWAPA OAPCA PSCAA SCAPCA SWAPCA YRCAA
ADEC \3\ IDEQ \4\ ODEQ \5\ \6\ Ecology \7\ BCAA \8\ \9\ \10\ \11\ \12\ \13\ \14\
--------------------------------------------------------------------------------------------------------------------------------------------------------
A General Provisions \15\.... X X \4\ X X X X X X X X X X
B Radon from Underground
Uranium Mines...............
C Beryllium.................. ........ X \4\ X X X X X X X X X X
D Beryllium Rocket Motor ........ X \4\ X X X X X X X X X X
Firing......................
E Mercury.................... X X \4\ X X X X X X X X X X
F Vinyl Chloride............. ........ X \4\ X X X X X X X X X X
H Emissions of Radionuclides
other than Radon from Dept
of Energy facilities........
I Radionuclides from Federal
Facilities other than
Nuclear Regulatory
Commission Licensees and not
covered by Subpart H........
J Equipment Leaks of Benzene. X X \4\ X X X X X X X X X X
K Radionuclides from
Elemental Phosphorus Plants.
L Benzene from Coke Recovery. ........ X \4\ X X X X X X X X X X
M Asbestos................... X \3,4\ ........ ........ X \7\ X \8\ X X \10\ X X X X
N Arsenic from Glass Plants.. ........ X \4\ X X X X X X X X X X
O Arsenic from Primary Copper ........ X \4\ X X X X X X X X X X
Smelters....................
P Arsenic from Arsenic ........ X \4\ X X X X X X X X X X
Production Facilities.......
Q Radon from Dept of Energy
facilities..................
R Radon from Phosphogypsum
Stacks......................
T Radon from Disposal of ........ X \4\
Uranium Mill Tailings.......
V Equipment Leaks............ X X \4\ X X X X X X X X X X
W Radon from Operating Mill
Tailings....................
Y Benzene from Benzene X X \4\ X X X X X X X X X X
Storage Vessels.............
BB Benzene from Benzene ........ X \4\ X X X X X X X X X X
Transfer Operations.........
FF Benzene Waste Operations.. X ........ X X X X X X X X X X
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\ Table last updated on August 9, 2002.
\2\ Any authority within any subpart of this part (i.e. under ``Delegation of Authority'') that is identified as not delegatable, is not delegated.
\3\ Alaska Department of Environmental Conservation (01/18/1997) Note: Alaska received delegation for § 61.145 and § 61.154 of subpart M
(Asbestos), along with other sections and appendices which are referenced in § 61.145, as § 61.145 applies to sources required to obtain an
operating permit under Alaska's regulations. Alaska has not received delegation for subpart M for sources not required to obtain an operating permit
under Alaska's regulations.
\4\ Idaho Department of Environmental Quality (07/01/2000) Note: Delegation of these part 61, Subparts applies only to those sources in Idaho required
to obtain an operating permit under Title V of the Clean Air Act.
\5\ Oregon Department of Environmental Quality (07/01/2001)
\6\ Lane Regional Air Pollution Authority (07/01/2001)
\7\ Washington Department of Ecology (02/20/2001) Note: Delegation of part 63, subpart M applies only to sources required to obtain an operating permit
under Title V of the Clean Air Act, including Hanford. (Pursuant to RCW 70.105.240, only Ecology can enforce regulations at Hanford)
\8\ Benton Clean Air Authority (02/20/2001) Note: Delegation of part 63, subpart M excludes Hanford, see note #6.
\9\ Northwest Air Pollution Authority (07/01/2000)
\10\ Olympic Air Pollution Control Authority (07/01/2000) Note: Delegation of part 63, subpart M applies only to sources required to obtain an operating
permit under Title V of the Clean Air Act
\11\ Puget Sound Clean Air Agency (07/01/1999)
\12\ Spokane County Air Pollution Control Authority (02/20/2001)
\13\ Southwest Air Pollution Control Authority (08/01/1998)
\14\ Yakima Regional Clean Air Authority (07/01/2000)
\15\ General Provisions Authorities which are not delegated include: §§ 61.04(b); 61.12(d)(1); 61.13(h)(1)(ii) for approval of major
alternatives to test methods; § 61.14(g)(1)(ii) for approval of major alternatives to monitoring; § 61.16; § 61.53(c)(4); and any
sections in the subparts pertaining to approval of alternative standards (i.e., alternative means of emission limitations), or approval of major
alternatives to test methods or monitoring. For definitions of minor, intermediate, and major alternatives to test methods and monitoring, see 40 CFR
63.90.
[40 FR 18170, Apr. 25, 1975]
Editorial Note: For Federal Register citations to §61.04 see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and on GPO Access.
§ 61.05 Prohibited activities.
top
(a) After the effective date of any standard, no owner or operator shall construct or modify any stationary source subject to that standard without first obtaining written approval from the Administrator in accordance with this subpart, except under an exemption granted by the President under section 112(c)(2) of the Act. Sources, the construction or modification of which commenced after the publication date of the standards proposed to be applicable to the sources, are subject to this prohibition.
(b) After the effective date of any standard, no owner or operator shall operate a new stationary source subject to that standard in violation of the standard, except under an exemption granted by the President under section 112(c)(2) of the Act.
(c) Ninety days after the effective date of any standard, no owner or operator shall operate any existing source subject to that standard in violation of the standard, except under a waiver granted by the Administrator under this part or under an exemption granted by the President under section 112(c)(2) of the Act.
(d) No owner or operator subject to the provisions of this part shall fail to report, revise reports, or report source test results as required under this part.
[38 FR 8826, Apr. 6, 1973, as amended at 50 FR 46291, Nov. 7, 1985]
§ 61.06 Determination of construction or modification.
top
An owner or operator may submit to the Administrator a written application for a determination of whether actions intended to be taken by the owner or operator constitute construction or modification, or commencement thereof, of a source subject to a standard. The Administrator will notify the owner or operator of his determination within 30 days after receiving sufficient information to evaluate the application.
[50 FR 46291, Nov. 7, 1985]
§ 61.07 Application for approval of construction or modification.
top
(a) The owner or operator shall submit to the Administrator an application for approval of the construction of any new source or modification of any existing source. The application shall be submitted before the construction or modification is planned to commence, or within 30 days after the effective date if the construction or modification had commenced before the effective date and initial startup has not occurred. A separate application shall be submitted for each stationary source.
(b) Each application for approval of construction shall include—
(1) The name and address of the applicant;
(2) The location or proposed location of the source; and
(3) Technical information describing the proposed nature, size, design, operating design capacity, and method of operation of the source, including a description of any equipment to be used for control of emissions. Such technical information shall include calculations of emission estimates in sufficient detail to permit assessment of the validity of the calculations.
(c) Each application for approval of modification shall include, in addition to the information required in paragraph (b) of this section—
(1) The precise nature of the proposed changes;
(2) The productive capacity of the source before and after the changes are completed; and
(3) Calculations of estimates of emissions before and after the changes are completed, in sufficient detail to permit assessment of the validity of the calculations.
[50 FR 46291, Nov. 7, 1985]
§ 61.08 Approval of construction or modification.
top
(a) The Administrator will notify the owner or operator of approval or intention to deny approval of construction or modification within 60 days after receipt of sufficient information to evaluate an application under §61.07.
(b) If the Administrator determines that a stationary source for which an application under §61.07 was submitted will not cause emissions in violation of a standard if properly operated, the Administrator will approve the construction or modification.
(c) Before denying any application for approval of construction or modification, the Administrator will notify the applicant of the Administrator's intention to issue the denial together with—
(1) Notice of the information and findings on which the intended denial is based; and
(2) Notice of opportunity for the applicant to present, within such time limit as the Administrator shall specify, additional information or arguments to the Administrator before final action on the application.
(d) A final determination to deny any application for approval will be in writing and will specify the grounds on which the denial is based. The final determination will be made within 60 days of presentation of additional information or arguments, or 60 days after the final date specified for presentation if no presentation is made.
(e) Neither the submission of an application for approval nor the Administrator's approval of construction or modification shall—
(1) Relieve an owner or operator of legal responsibility for compliance with any applicable provisions of this part or of any other applicable Federal, State, or local requirement; or
(2) Prevent the Administrator from implementing or enforcing this part or taking any other action under the Act.
[50 FR 46291, Nov. 7, 1985]
§ 61.09 Notification of startup.
top
(a) The owner or operator of each stationary source which has an initial startup after the effective date of a standard shall furnish the Administrator with written notification as follows:
(1) A notification of the anticipated date of initial startup of the source not more than 60 days nor less than 30 days before that date.
(2) A notification of the actual date of initial startup of the source within 15 days after that date.
(b) If any State or local agency requires a notice which contains all the information required in the notification in paragraph (a) of this section, sending the Administrator a copy of that notification will satisfy paragraph (a) of this section.
[50 FR 46291, Nov. 7, 1985]
§ 61.10 Source reporting and waiver request.
top
(a) The owner or operator of each existing source or each new source which had an initial startup before the effective date shall provide the following information in writing to the Administrator within 90 days after the effective date:
(1) Name and address of the owner or operator.
(2) The location of the source.
(3) The type of hazardous pollutants emitted by the stationary source.
(4) A brief description of the nature, size, design, and method of operation of the stationary source including the operating design capacity of the source. Identify each point of emission for each hazardous pollutant.
(5) The average weight per month of the hazardous materials being processed by the source, over the last 12 months preceding the date of the report.
(6) A description of the existing control equipment for each emission point including—
(i) Each control device for each hazardous pollutant; and
(ii) Estimated control efficiency (percent) for each control device.
(7) A statement by the owner or operator of the source as to whether the source can comply with the standards within 90 days after the effective date.
(b) The owner or operator of an existing source unable to comply with an applicable standard may request a waiver of compliance with that standard for a period not exceeding 2 years after the effective date. Any request shall be in writing and shall include the following information:
(1) A description of the controls to be installed to comply with the standard.
(2) A compliance schedule, including the date each step toward compliance will be reached. The list shall include as a minimum the following dates:
(i) Date by which contracts for emission control systems or process changes for emission control will be awarded, or date by which orders will be issued for the purchase of component parts to accomplish emission control or process changes;
(ii) Date of initiation of onsite construction or installation of emission control equipment or process change;
(iii) Date by which onsite construction or installation of emission control equipment or process change is to be completed; and
(iv) Date by which final compliance is to be achieved.
(3) A description of interim emission control steps which will be taken during the waiver period.
(c) Any change in the information provided under paragraph (a) of this section or §61.07(b) shall be provided to the Administrator within 30 days after the change. However, if any change will result from modification of the source, §§61.07(c) and 61.08 apply.
(d) A possible format for reporting under this section is included as appendix A of this part. Advice on reporting the status of compliance may be obtained from the Administrator.
(e) For the purposes of this part, time periods specified in days shall be measured in calendar days, even if the word “calendar” is absent, unless otherwise specified in an applicable requirement.
(f) For the purposes of this part, if an explicit postmark deadline is not specified in an applicable requirement for the submittal of a notification, application, report, or other written communication to the Administrator, the owner or operator shall postmark the submittal on or before the number of days specified in the applicable requirement. For example, if a notification must be submitted 15 days before a particular event is scheduled to take place, the notification shall be postmarked on or before 15 days preceding the event; likewise, if a notification must be submitted 15 days after a particular event takes place, the notification shall be postmarked on or before 15 days following the end of the event. The use of reliable non-Government mail carriers that provide indications of verifiable delivery of information required to be submitted to the Administrator, similar to the postmark provided by the U.S. Postal Service, or alternative means of delivery agreed to by the permitting authority, is acceptable.
(g) Notwithstanding time periods or postmark deadlines specified in this part for the submittal of information to the Administrator by an owner or operator, or the review of such information by the Administrator, such time periods or deadlines may be changed by mutual agreement between the owner or operator and the Administrator. Procedures governing the implementation of this provision are specified in paragraph (j) of this section.
(h) If an owner or operator of a stationary source in a State with delegated authority is required to submit reports under this part to the State, and if the State has an established timeline for the submission of reports that is consistent with the reporting frequency(ies) specified for such source under this part, the owner or operator may change the dates by which reports under this part shall be submitted (without changing the frequency of reporting) to be consistent with the State's schedule by mutual agreement between the owner or operator and the State. The allowance in the previous sentence applies in each State beginning 1 year after the source is required to be in compliance with the applicable subpart in this part. Procedures governing the implementation of this provision are specified in paragraph (j) of this section.
(i) If an owner or operator supervises one or more stationary sources affected by standards set under this part and standards set under part 60, part 63, or both such parts of this chapter, he/she may arrange by mutual agreement between the owner or operator and the Administrator (or the State with an approved permit program) a common schedule on which reports required by each applicable standard shall be submitted throughout the year. The allowance in the previous sentence applies in each State beginning 1 year after the source is required to be in compliance with the applicable subpart in this part, or 1 year after the source is required to be in compliance with the applicable part 60 or part 63 standard, whichever is latest. Procedures governing the implementation of this provision are specified in paragraph (j) of this section.
(j)(1)(i) Until an adjustment of a time period or postmark deadline has been approved by the Administrator under paragraphs (j)(2) and (j)(3) of this section, the owner or operator of an affected source remains strictly subject to the requirements of this part.
(ii) An owner or operator shall request the adjustment provided for in paragraphs (j)(2) and (j)(3) of this section each time he or she wishes to change an applicable time period or postmark deadline specified in this part.
(2) Notwithstanding time periods or postmark deadlines specified in this part for the submittal of information to the Administrator by an owner or operator, or the review of such information by the Administrator, such time periods or deadlines may be changed by mutual agreement between the owner or operator and the Administrator. An owner or operator who wishes to request a change in a time period or postmark deadline for a particular requirement shall request the adjustment in writing as soon as practicable before the subject activity is required to take place. The owner or operator shall include in the request whatever information he or she considers useful to convince the Administrator that an adjustment is warranted.
(3) If, in the Administrator's judgment, an owner or operator's request for an adjustment to a particular time period or postmark deadline is warranted, the Administrator will approve the adjustment. The Administrator will notify the owner or operator in writing of approval or disapproval of the request for an adjustment within 15 calendar days of receiving sufficient information to evaluate the request.
(4) If the Administrator is unable to meet a specified deadline, he or she will notify the owner or operator of any significant delay and inform the owner or operator of the amended schedule.
[38 FR 8826, Apr. 6, 1973, as amended at 50 FR 46292, Nov. 7, 1985; 59 FR 12430, Mar. 16, 1994]
§ 61.11 Waiver of compliance.
top
(a) Based on the information provided in any request under §61.10, or other information, the Administrator may grant a waiver of compliance with a standard for a period not exceeding 2 years after the effective date of the standard.
(b) The waiver will be in writing and will—
(1) Identify the stationary source covered;
(2) Specify the termination date of the waiver;
(3) Specify dates by which steps toward compliance are to be taken; and
(4) Specify any additional conditions which the Administrator determines necessary to assure installation of the necessary controls within the waiver period and to assure protection of the health of persons during the waiver period.
(c) The Administrator may terminate the waiver at an earlier date than specified if any specification under paragraphs (b)(3) and (b)(4) of this section are not met.
(d) Before denying any request for a waiver, the Administrator will notify the owner or operator making the request of the Administrator's intention to issue the denial, together with—
(1) Notice of the information and findings on which the intended denial is based; and
(2) Notice of opportunity for the owner or operator to present, within the time limit the Administrator specifies, additional information or arguments to the Administrator before final action on the request.
(e) A final determination to deny any request for a waiver will be in writing and will set forth the specific grounds on which the denial is based. The final determination will be made within 60 days after presentation of additional information or argument; or within 60 days after the final date specified for the presentation if no presentation is made.
(f) The granting of a waiver under this section shall not abrogate the Administrator's authority under section 114 of the Act.
[50 FR 46292, Nov. 7, 1985]
§ 61.12 Compliance with standards and maintenance requirements.
top
(a) Compliance with numerical emission limits shall be determined in accordance with emission tests established in §61.13 or as otherwise specified in an individual subpart.
(b) Compliance with design, equipment, work practice or operational standards shall be determined as specified in an individual subpart.
(c) The owner or operator of each stationary source shall maintain and operate the source, including associated equipment for air pollution control, in a manner consistent with good air pollution control practice for minimizing emissions. Determination of whether acceptable operating and maintenance procedures are being used will be based on information available to the Administrator which may include, but is not limited to, monitoring results, review of operating and maintenance procedures, and inspection of the source.
(d)(1) If, in the Administrator's judgment, an alternative means of emission limitation will achieve a reduction in emissions of a pollutant from a source at least equivalent to the reduction in emissions of that pollutant from that source achieved under any design, equipment, work practice or operational standard, the Administrator will publish in the Federal Register a notice permitting the use of the alternative means for purposes of compliance with the standard. The notice will restrict the permission to the source(s) or category(ies) of sources on which the alternative means will achieve equivalent emission reductions. The notice may condition permission on requirements related to the operation and maintenance of the alternative means.
(2) Any notice under paragraph (d)(1) shall be published only after notice and an opportunity for a hearing.
(3) Any person seeking permission under this subsection shall, unless otherwise specified in the applicable subpart, submit a proposed test plan or the results of testing and monitoring, a description of the procedures followed in testing or monitoring, and a description of pertinent conditions during testing or monitoring.
(e) For the purpose of submitting compliance certifications or establishing whether or not a person has violated or is in violation of any standard in this part, nothing in this part shall preclude the use, including the exclusive use, of any credible evidence or information, relevant to whether a source would have been in compliance with applicable requirements if the appropriate performance or compliance test had been performed.
[50 FR 46292, Nov. 7, 1985, as amended 62 FR 8328, Feb. 24, 1997]
§ 61.13 Emission tests and waiver of emission tests.
top
(a) If required to do emission testing by an applicable subpart and unless a waiver of emission testing is obtained under this section, the owner or operator shall test emissions from the source—
(1) Within 90 days after the effective date, for an existing source or a new source which has an initial startup date before the effective date; or
(2) Within 90 days after initial startup, for a new source which has an initial startup date after the effective date.
(b) The Administrator may require an owner or operator to test emissions from the source at any other time when the action is authorized by section 114 of the Act.
(c) The owner or operator shall notify the Administrator of the emission test at least 30 days before the emission test to allow the Administrator the opportunity to have an observer present during the test.
(d) If required to do emission testing, the owner or operator of each new source and, at the request of the Administrator, the owner or operator of each existing source shall provide emission testing facilities as follows:
(1) Sampling ports adequate for test methods applicable to each source.
(2) Safe sampling platform(s).
(3) Safe access to sampling platform(s).
(4) Utilities for sampling and testing equipment.
(5) Any other facilities that the Administrator needs to safely and properly test a source.
(e) Each emission test shall be conducted under such conditions as the Administrator shall specify based on design and operational characteristics of the source.
(f) Unless otherwise specified in an applicable subpart, samples shall be analyzed and emissions determined within 30 days after each emission test has been completed. The owner or operator shall report the determinations of the emission test to the Administrator by a registered letter sent before the close of business on the 31st day following the completion of the emission test.
(g) The owner or operator shall retain at the source and make available, upon request, for inspection by the Administrator, for a minimum of 2 years, records of emission test results and other data needed to determine emissions.
(h)(1) Emission tests shall be conducted as set forth in this section, the applicable subpart and appendix B unless the Administrator—
(i) Specifies or approves the use of a reference method with minor changes in methodology; or
(ii) Approves the use of an alternative method; or
(iii) Waives the requirement for emission testing because the owner or operator of a source has demonstrated by other means to the Administrator's satisfaction that the source is in compliance with the standard.
(2) If the Administrator finds reasonable grounds to dispute the results obtained by an alternative method, he may require the use of a reference method. If the results of the reference and alternative methods do not agree, the results obtained by the reference method prevail.
(3) The owner or operator may request approval for the use of an alternative method at any time, except—
(i) For an existing source or a new source that had an initial startup before the effective date, any request for use of an alternative method during the initial emission test shall be submitted to the Administrator within 30 days after the effective date, or with the request for a waiver of compliance if one is submitted under §60.10(b); or
(ii) For a new source that has an initial startup after the effective date, any request for use of an alternative method during the initial emission test shall be submitted to the Administrator no later than with the notification of anticipated startup required under §60.09.
(i)(1) Emission tests may be waived upon written application to the Administrator if, in the Administrator's judgment, the source is meeting the standard, or the source is being operated under a waiver or compliance, or the owner or operator has requested a waiver of compliance and the Administrator is still considering that request.
(2) If application for waiver of the emission test is made, the application shall accompany the information required by §61.10 or the notification of startup required by §61.09, whichever is applicable. A possible format is contained in appendix A to this part.
(3) Approval of any waiver granted under this section shall not abrogate the Administrator's authority under the Act or in any way prohibit the Administrator from later cancelling the waiver. The cancellation will be made only after notice is given to the owner or operator of the source.
[50 FR 46292, Nov. 7, 1985]
§ 61.14 Monitoring requirements.
top
(a) Unless otherwise specified, this section applies to each monitoring system required under each subpart which requires monitoring.
(b) Each owner or operator shall maintain and operate each monitoring system as specified in the applicable subpart and in a manner consistent with good air pollution control practice for minimizing emissions. Any unavoidable breakdown or malfunction of the monitoring system should be repaired or adjusted as soon as practicable after its occurrence. The Administrator's determination of whether acceptable operating and maintenance procedures are being used will be based on information which may include, but not be limited to, review of operating and maintenance procedures, manufacturer recommendations and specifications, and inspection of the monitoring system.
(c) When required by the applicable subpart, and at any other time the Administrator may require, the owner or operator of a source being monitored shall conduct a performance evaluation of the monitoring system and furnish the Administrator with a copy of a written report of the results within 60 days of the evaluation. Such a performance evaluation shall be conducted according to the applicable specifications and procedures described in the applicable subpart. The owner or operator of the source shall furnish the Administrator with written notification of the date of the performance evaluation at least 30 days before the evaluation is to begin.
(d) When the effluents from a single source, or from two or more sources subject to the same emission standards, are combined before being released to the atmosphere, the owner or operator shall install a monitoring system on each effluent or on the combined effluent. If two or more sources are not subject to the same emission standards, the owner or operator shall install a separate monitoring system on each effluent, unless otherwise specified. If the applicable standard is a mass emission standard and the effluent from one source is released to the atmosphere through more than one point, the owner or operator shall install a monitoring system at each emission point unless the installation of fewer systems is approved by the Administrator.
(e) The owner or operator of each monitoring system shall reduce the monitoring data as specified in each applicable subpart. Monitoring data recorded during periods of unavoidable monitoring system breakdowns, repairs, calibration checks, and zero and span adjustments shall not be included in any data average.
(f) The owner or operator shall maintain records of monitoring data, monitoring system calibration checks, and the occurrence and duration of any period during which the monitoring system is malfunctioning or inoperative. These records shall be maintained at the source for a minimum of 2 years and made available, upon request, for inspection by the Administrator.
(g)(1) Monitoring shall be conducted as set forth in this section and the applicable subpart unless the Administrator—
(i) Specifies or approves the use of the specified monitoring requirements and procedures with minor changes in methodology; or
(ii) Approves the use of alternatives to any monitoring requirements or procedures.
(2) If the Administrator finds reasonable grounds to dispute the results obtained by an alternative monitoring method, the Administrator may require the monitoring requirements and procedures specified in this part.
[50 FR 46293, Nov. 7, 1985]
§ 61.15 Modification.
top
(a) Except as provided under paragraph (d) of this section, any physical or operational change to a stationary source which results in an increase in the rate of emission to the atmosphere of a hazardous pollutant to which a standard applies shall be considered a modification.
(b) Upon modification, an existing source shall become a new source for each hazardous pollutant for which the rate of emission to the atmosphere increases and to which a standard applies.
(c) Emission rate shall be expressed as kg/hr of any hazardous pollutant discharged into the atmosphere for which a standard is applicable. The Administrator shall use the following to determine the emission rate:
(1) Emission factors as specified in the background information document (BID) for the applicable standard, or in the latest issue of “Compilation of Air Pollutant Emission Factors,” EPA Publication No. AP–42, or other emission factors determined by the Administrator to be superior to AP–42 emission factors, in cases where use of emission factors demonstrates that the emission rate will clearly increase or clearly not increase as a result of the physical or operational change.
(2) Material balances, monitoring data, or manual emission tests in cases where use of emission factors, as referenced in paragraph (c)(1) of this section, does not demonstrate to the Administrator's satisfaction that the emission rate will clearly increase or clearly not increase as a result of the physical or operational change, or where an interested person demonstrates to the Administrator's satisfaction that there are reasonable grounds to dispute the result obtained by the Administrator using emission factors. When the emission rate is based on results from manual emission tests or monitoring data, the procedures specified in appendix C of 40 CFR part 60 shall be used to determine whether an increase in emission rate has occurred. Tests shall be conducted under such conditions as the Administrator shall specify to the owner or operator. At least three test runs must be conducted before and at least three after the physical or operational change. If the Administrator approves, the results of the emission tests required in §61.13(a) may be used for the test runs to be conducted before the physical or operational change. All operating parameters which may affect emissions must be held constant to the maximum degree feasible for all test runs.
(d) The following shall not, by themselves, be considered modifications under this part:
(1) Maintenance, repair, and replacement which the Administrator determines to be routine for a source category.
(2) An increase in production rate of a stationary source, if that increase can be accomplished without a capital expenditure on the stationary source.
(3) An increase in the hours of operation.
(4) Any conversion to coal that meets the requirements specified in section 111(a)(8) of the Act.
(5) The relocation or change in ownership of a stationary source. However, such activities must be reported in accordance with §61.10(c).
[50 FR 46294, Nov. 7, 1985]
§ 61.16 Availability of information.
top
The availability to the public of information provided to, or otherwise obtained by, the Administrator under this part shall be governed by part 2 of this chapter.
[38 FR 8826, Apr. 6, 1973. Redesignated at 50 FR 46294, Nov. 7, 1985]
§ 61.17 State authority.
top
(a) This part shall not be construed to preclude any State or political subdivision thereof from—
(1) Adopting and enforcing any emission limiting regulation applicable to a stationary source, provided that such emission limiting regulation is not less stringent than the standards prescribed under this part; or
(2) Requiring the owner or operator of a stationary source to obtain permits, licenses, or approvals prior to initiating construction, modification, or operation of the source.
[50 FR 46294, Nov. 7, 1985]
§ 61.18 Incorporations by reference.
top
The materials listed below are incorporated by reference in the corresponding sections noted. These incorporations by reference were approved by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. These materials are incorporated as they exist on the date of the approval, and a notice of any change in these materials will be published in the Federal Register. The materials are available for inspection at the corresponding address noted below, and at U.S. EPA's Air Docket at 1200 Pennsylvania Avenue, NW, Washington, DC 20460, or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202–741–6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
(a) The following materials are available for purchase from at least one of the following addresses: American Society for Testing and Materials (ASTM) International, 100 Barr Harbor Drive, P.O. Box C700, West Conshohocken, PA, 19428–2959; or University Microfilms International, 300 North Zeeb Road, Ann Arbor, MI 48106.
(1) ASTM D737–75, Standard Test Method for Air Permeability of Textile Fabrics, incorporation by reference (IBR) approved January 27, 1983 for §61.23(a).
(2) ASTM D835–85, Standard Specification for Refined Benzene-485, IBR approved September 14, 1989 for §61.270(a).
(3) ASTM D836–84, Standard Specification for Industrial Grade Benzene, IBR approved September 14, 1989 for §61.270(a).
(4) ASTM D1193–77, 91, Standard Specification for Reagent Water, IBR approved for appendix B: Method 101, Section 7.1.1; Method 101A, Section 7.1.1; and Method 104, Section 7.1; Method 108, Section 7.1.3; Method 108A, Section 7.1.1; Method 108B, Section 7.1.1; Method 108C, Section 7.1.1; and Method 111, Section 7.3.
(5) ASTM D2267–68, 78, 88, Standard Test Method for Aromatics in Light Naphthas and Aviation Gasoline by Gas Chromatography, IBR approved September 30, 1986, for §61.67(h)(1).
(6) ASTM D2359–85a, 93, Standard Specification for Refined Benzene-535, IBR approved September 14, 1989 for §61.270(a).
(7) ASTM D2382–76, 88, Heat of Combustion of Hydrocarbon Fuels by Bomb Calorimeter (High-Precision Method), IBR approved June 6, 1984 for §61.245(e)(3).
(8) ASTM D2504–67, 77, 88 (Reapproved 1993), Noncondensable Gases in C3 and Lighter Hydrocarbon Products by Gas Chromatography, IBR approved June 6, 1984 for §61.245(e)(3).
(9) ASTM D2879–83, Standard Test Method for Vapor Pressure—Temperature Relationship and Initial Decomposition Temperature of Liquids by Isoteniscope, IBR approved December 14, 2000 for §61.241.
(10) ASTM D2986–71, 78, 95a, Standard Method for Evaluation of Air, Assay Media by the Monodisperse DOP (Dioctyl Phthalate) Smoke Test, IBR approved for appendix B: Method 103, Section 6.1.3. (continued)