(d) In using Method 8, traversing shall be conducted according to Method 1 as described in part 60 of this chapter. The minimum sampling volume for each two hour test shall be 40 ft 3 corrected to standard conditions, dry basis.
(e) The velocity of the total effluent from each stack evaluated shall be determined by using Method 2 as described in part 60 of this chapter and traversing according to Method 1. Gas analysis shall be performed by using the integrated sample technique of Method 3 as described in part 60 of thi8s chapter. Moisture content can be considered to be zero.
(f) The gas sample shall be extracted at a rate proportional to gas velocity at the sampling point.
(g) The sulfur dioxide concentration in parts per million-maximum 6-hour average for each stack is determined by calculating the arithmetic average of the results of the three 2-hour tests.
(iv) Notwithstanding the requirements of paragraph (e)(6)(ii) of this section, compliance with the requirements of paragraph (e)(4)(i)(b) of this section shall also be determined by using the methods described below at such times as may be specified by the Administrator. For all stacks equipped with the measurement system(s) required by paragraph (e)(5) of this section, a 6-hour average sulfur dioxide emission rate (lbs SO2/hr) shall be determined as follows:
(a) The test of each stack emission rate shall be conducted while the processing units vented through such stack are operating at or above the maximum rate at which they will be operated and under such other conditions as the Administrator shall specify.
(b) Concentrations of sulfur dioxide in emissions shall be determined by using Method 8 as described in part 60 of this chapter. The analytical, and computational portions of Method 8 as they relate to determination of sulfuric acid mist and sulfur trioxide as well as isokinetic sampling may be omitted from the over-all test procedure.
(c) Three independent sets of measurements of sulfur dioxide concentrations and stack gas volumetric flow rates shall be conducted during three consecutive 2-hour periods for each stack. Measurements need not necessarily be conducted simultaneously of emissions from all stacks on the smelter premises.
(d) In using Method 8, Traversing shall be conducted according to Method 1 as described in part 60 of this chapter. The minimum sampling volume for each 2-hour test shall be 40 ft 3 corrected to standard conditions, dry basis.
(e) The volumetric flow rate of the total effluent from each stack evaluated shall be determined by using Method 2 as described in part 60 of this chapter and by traversing according to Method 1. Gas analysis shall be performed by using the integrated sample technique of Method 3 as described in part 60 of this chapter. Moisture content shall be determined by use of Method 4 as described in part 60 of this chapter except that stack gases arising only from a sulfuric acid production unit may be considered to have zero moisture content.
(f) The gas sample shall be extracted at a rate proportional to the gas velocity at the sampling point.
(g) For each 2-hour test period, the sulfur dioxide emission rate for each stack shall be determined by multiplying the stack gas volumetric flow rate (ft 3 /hr at standard conditions, dry basis) by the sulfur dioxide concentration (lb/ft 3 at standard conditions, dry basis). The emission rate in lbs/hr-maximum 6-hour average for each stack is determined by calculating the arithmetic average of the results of the three 2-hour tests.
(h) The sum total of sulfur dioxide emissions from the smelter premises in lbs/hr is determined by adding together the emission rates (lbs/hr) from all stacks equipped with the measurement system(s) required by paragraph (e)(5) of this section.
(7) The owner or operator of the smelter subject to this paragraph, in addition to meeting the emission limitation requirements of paragraph (e)(4) of this section, shall employ supplementary control systems and/or such additional control measures as may be necessary to assure the attainment and maintenance of the National Ambient Air Quality Standards for sulfur dioxide.
(i) Such measures will be limited to those specified in the application submitted pursuant to paragraph (e)(3)(i)(g) of this section.
(ii) Sulfur oxides emissions shall be curtailed whenever the potential for violating any National Ambient Air Quality Standard for sulfur dioxide is indicated at any point in a designated liability area by either of the following:
(a) Air quality measurement.
(b) Air quality prediction.
(8)(i) For the purposes of this paragraph the designated liability area shall be a circle with a radius of fifteen (15) statute miles (24 km) with the center point of such circle coinciding with the tallest stack serving the affected facility. The owner or operator of the smelter subject to this paragraph may submit a detailed report which justifies redefining the designated liability area specified by the Administrator. Such a justification shall be submitted with the application submitted pursuant to paragraph (e)(3)(i) of this section and shall describe and delineate the requested designated liability area and discuss in detail the method used and the factors taken into account in the development of such area. Upon receipt and evaluation of such report, and after the public hearing described in paragraph (e)(3)(ii) of this section, the Administrator shall issue his final determination.
(ii) If new information becomes available which demonstrates that the designated liability area should be redefined, the Administrator shall consider such and if appropriate, after notice and comment, redefine the designated liability area.
(9) (i) The owner or operator of the smelter subject to the paragraph shall submit with the application submitted pursuant to paragraph (e)(3)(i) of this section, a detailed plan for the establishment of a supplementary control system and/or such other measures as may be proposed. Such plan shall describe all air quality and emission monitoring and meteorological equipment to be used, including instruments installed pursuant to paragraph (e)(5) of this section for continuously monitoring and recording sulfur dioxide emissions and stack gas flow rate, the methods that will be used to determine emission rates to be achieved in association with various meteorological and air quality situations, and the general plan of investigations to be followed in developing the system and the operational manual.
(ii) Such plan shall include detailed specifications of any modifications to existing equipment including new stacks, stack extensions, stack heating systems or any process changes to be applied.
(iii) The monitoring described in the detailed plan submitted in accordance with this subparagraph and the appropriate recordkeeping requirements of paragraph (e)(12) of this section shall commence and become applicable as of the date specified in paragraph (e)(14)(i)(b)(5) of this section.
(10) The owner or operator of the smelter subject to this paragraph shall submit to the Administrator a comprehensive report of a study which demonstrates the capability of the supplementary control system, in conjunction with any other control measures, to reduce air pollution levels. The report shall describe a study conducted during a period of at least 120 days during which the supplementary control system was being developed and operated and shall be submitted no later than the date specified in paragraph (e)(14)(i)(b)(6) of this section. The report shall:
(i) Describe the emission monitoring system and the air quality monitoring network.
(ii) Describe the meteorological sensing network and the meteorological prediction program.
(iii) Identify the frequency, characteristics, times of occurrence and durations of meteorological conditions associated with high ground-level concentrations.
(iv) Describe the methodology (e.g., disperson modeling and measured air quality data) by which the source determines the degree of control needed under each meteorological situation.
(v) Describe the method chosen to vary the emission rate, the basis for the choice, and the time required to effect a sufficient reduction in the emission rate to avoid violations of National Ambient Air Quality Standards.
(vi) Contain an estimate of the frequency that emission rate reduction is required to prevent National Ambient Air Quality Standards from being exceeded and the basis for the estimate.
(vii) Include data and results of objective reliability tests. “Reliability,” as the term is applied here, refers to the ability of the supplementary control system to protect against violations of the National Ambient Air Quality Standards.
(viii) Demonstrate that the supplementary control system and other measures expected to be employed after the date specified in paragraph (e)(14)(i)(b)(6) of this section will result in attainment and maintenance of National Ambient Air Quality Standards.
(11) The owner or operator of the smelter subject to this paragraph shall submit to the Administrator an operational manual for the supplementary control system. Such manual shall be submitted no later than the date specified in paragraph (e)(14)(i)(b)(6) of this section and is subject to the approval of the Administrator as satisfying the specific requirements of this paragraph. Such approval shall not relieve the owner or operator of the smelter subject to this paragraph from its assumed liability for violations of any National Ambient Air Quality Standards for sulfur oxides in the designated liability area. Prior to making his final decision, the Administrator shall, after reasonable notice, provide an opportunity of not less than forty-five (45) days for public inspection and comment upon the manual. Such manual shall:
(i) Specify the number, type, and location of ambient air quality monitors, instack monitors and meteorological instruments to be used.
(ii) Describe techniques, methods, and criteria to be used to anticipate the onset of meteorological situations associated with ground-level concentrations in excess of National Ambient Air Quality Standards and to systematically evaluate and, as needed, improve the reliability of the supplementary control system.
(iii) Describe the criteria and procedures that will be used to determine the degree of emission control needed for each class of meteorological and air quality situations.
(iv) Specify maximum emission rates which may prevail during all probable meteorological and air quality situations, which rates shall be such that National Ambient Air Quality Standards will not be exceeded in the designated liability area. Such emission rates shall be determined by in-stack monitors. Data from such monitors shall be the basis for determining whether the emission rate provisions of the approved operational manual are adhered to.
(v) Describe specific actions that will be taken to curtail emissions when various meteorological conditions described in paragraph (c)(11)(ii) of this section exist or are predicted and/or when specified air quality levels occur.
(vi) Identify the company personnel responsible for initiating and supervising the actions that will be taken to curtail emissions. Such personnel must be responsible, knowledgeable and able to apprise the Administrator of the status of the supplementary control system at any time the source is operating.
(vii) Be modified only if approval by the Administrator is first obtained.
(12) The owner or operator of the smelter subject to this paragraph shall:
(i) Maintain, in a usable manner, records of all measurements and reports prepared as part of the supplementary control system described in the approved operational manual. Such records shall be retained for at least two years.
(ii) Submit, on a monthly basis, the hour by hour measurements made of air quality, emissions and meteorological parameters, and all other measurements made on a periodic basis, as part of the approved supplementary control system.
(iii) Submit a monthly summary indicating all places, dates, and times when National Ambient Air Quality Standards for sulfur oxides were exceeded and the concentrations of sulfur dioxide at such times.
(iv) Notify the Administrator of any violation of National Ambient Air Quality Standards within 24 hours of the occurrence of such violation.
(v) Submit a monthly summary report describing and analyzing how the supplementary control system was operated as related to the approved operations manual and how the system will be improved, if necessary, to prevent violations of the National Ambient Air Quality Standards for sulfur oxides or to prevent any other conditions which are not in accordance with the approved operational manual.
(13)(i) The owner or operator of the smelter subject to this paragraph shall participate in a research program to develop and apply constant emission reduction technology adequate to attain and maintain the national standards. Such program shall be carried out in accordance with the plan submitted pursuant to paragraph (e)(3)(i)(f) of this section.
(ii) The owner or operator of the smelter subject to this paragraph shall submit annual reports on the progress of the research and development program required by paragraph (e)(13)(i) of this section. Each report shall also include, but not be limited to, a description of the projects underway, information on the qualifications of the personnel involved, information on the funds and personnel that have been committed, and an estimated date for the installation of the constant emission reduction technology necessary to attain and maintain the National Ambient Air Quality Standards.
(14) (i) The owner or operator of the smelter subject to this paragraph shall comply with the compliance schedules specified below.
(a) Compliance schedule for meeting the emission reduction requirements of paragraph (e)(4) of this section:
(1) No later than thirty (30) days after the date of approval to meet the requirements of this paragraph—submit a final plan and schedule to the Administrator for meeting the requirements of paragraph (e)(4) of this section.
(2) No later than thirty (30) days after the date of approval to meet the requirements of this paragraph—let contracts or issue purchase order for emission control systems or process modifications or provide evidence that such contracts have been let.
(3) July 1, 1975. Initiate on-site construction or installation of emission control equipment or process change.
(4) July 1, 1976. Complete on-site construction or installation of constant emission control equipment or process change.
(5) January 1, 1977. Achieve final compliance with the requirements of paragraph (4) of this paragraph (e)(14)(i)(a).
(b) Compliance schedule for implementing a supplementary control system or other measures which meet the requirements of paragraphs (e) (7), (9), (10), and (11) of this section.
(1) No later than sixty (60) days after approval to meet the requirements of this paragraph—submit to the Administrator a detailed schedule for establishment and implementation of the supplementary control system and other measures in accordance with paragraph (e)(9) of this section.
(2) No later than ninety (90) days after approval to meet the requirements of this paragraph—let contracts or issue purchase orders, or provide evidence that such contracts have been let, for ambient air quality monitors, meteorological instruments, and other component parts necessary to establish a supplementary control system.
(3) No later than ninety (90) days after approval to meet the requirements of this paragraph—let contracts or issue purchase orders, or provide evidence that such contracts have been let, for any stack extensions or modifications of equipment approved pursuant to paragraph (e)(3) of this section.
(4) November 1, 1975. Complete installation of air quality and emission monitors and meteorological equipment.
(5) January 1, 1976. Complete installation of any stack extensions or modifications of equipment approved pursuant to paragraph (e)(3) of this section.
(6) May 1, 1976. Submit to the Administrator the comprehensive report on the supplementary control system required by paragraph (e)(10) of this section, and submit to the Administrator for his approval the operational manual required by paragraph (e)(11) of this section.
(7) January 1, 1977. The National Ambient Air Quality Standards for sulfur dioxide shall not be violated in the designated liability area.
(ii) Any owner or operator subject to the requirements of this subparagraph shall certify to the Administrator within five (5) days after the deadline for each increment of progress whether or not the required increment of progress has been met.
(iii) Notice must be given to the Administrator at least ten (10) days prior to conducting a performance test to afford him the opportunity to have an observer present.
(iv) If the source subject to this paragraph is presently in compliance with any of the increments of progress set forth in this paragraph, the owner or operator of such source shall certify such compliance to the Administrator within thirty (30) days of the effective date of this paragraph. The Administrator may request whatever supporting information he considers necessary to determine the validity of the certification.
(v) The owner or operator of the smelter subject to this paragraph may submit to the Administrator proposed alternative compliance schedules. Each such proposed compliance schedule shall be submitted with the application submitted pursuant to paragraph (e)(3)(i) of this section. No such compliance schedule may provide for final compliance after January 1, 1977. If approved by the Administrator, such schedule shall replace the compliance schedule set forth in this paragraph.
(vi) Any such compliance schedule submitted to the Administrator shall provide for increments of progress toward compliance. The dates for achievement of such increments of progress shall be specified. Increments of progress shall include, but not be limited to, the increments specified in the appropriate compliance schedule set forth in paragraphs (e)(14)(i) (a) and (b) of this section.
(15) (i) The Administrator shall annually review the supplementary control system and shall deny continued use of the supplementary control system if he determines that:
(a) The review indicates that constant emission control technology has become available or that other factors which may bear on the conditions for use of a supplementary control system have changed to the extent that continued use of the supplementary control system would no longer be deemed approvable within the intent of paragraph (e)(3) of this section; or
(b) The source owner or operator has not demonstrated good faith efforts to follow the stated program for developing constant emission reduction procedures; or
(c) The source owner or operator has not developed and employed a control program that is effective in preventing violations of National Ambient Air Quality Standards.
(ii) Prior to denying the continued use of a supplementary control system pursuant to paragraph (e)(15)(i) of this section, the Administrator shall notify the owner or operator of the smelter subject to this paragraph of his intent to deny such continued use, together with:
(a) The information and findings on which such intended denial is based.
(b) Notice of opportunity for such owner or operator to present, within thirty (30) days, additional information or arguments to the Administrator prior to his final determination.
(iii) The Administrator shall notify the owner or operator of the smelter subject to this paragraph of his final determination within thirty (30) days after the presentation of additional information or arguments, or thirty (30) days after the final datee specified for such presentation if no presentation is made. If the continued usee of the supplementary control system is denied, the final determination shall set forth the specific grounds for such denial.
(16) Upon denial of the continued use of a supplementary control system pursuant to paragraph (e)(15) of this section all the requirements of paragraph (d) of this section shall be immediately applicable to the owner or operator of the Kennecott Copper Company smelter located in White Pine County, Nevada, in the Nevada Intrastate Region and compliance therewith shall be achieved in accordance with such schedule as the Administrator shall order.
(17) The owner or operator of the smelter subject to this paragraph shall be in violation of a requirement of an applicable implementation plan and subject to the penalties specified in section 113 of the Clean Air Act if:
(i) An increment of the compliance schedules set forth in paragraph (e)(14) of this section is not met by the date specified; or
(ii) The total sulfur dioxide concentration determined according to paragraph (e)(6) (i) or (iii) of this section exceeds the emission limitation set forth in paragraph (e)(4)(i)(a) of this section; or
(iii) The total sulfur dioxide emission rate determined according to paragraph (e)(6) (ii) or (iv) of this section exceeds the emission limitation set forth in paragraph (e)(4)(i)(b) of this section; or
(iv) Any National Ambient Air Quality Standards for sulfur oxides are violated in the designated liability area; or
(v) Operations of the supplementary control system are not conducted in accordance with the approved operational manual; or
(vi) Such owner or operator fails to submit any of the information required by this paragraph.
[40 FR 5511, Feb. 6, 1975, as amended at 51 FR 40676, Nov. 7, 1986]
§ 52.1476 Control strategy: Particulate matter.
top
(a) The requirements of subpart G of this chapter are not met since the plan does not provide for the attainment and maintenance of the national standards for particulate matter in the Northwest Nevada and Nevada Intrastate Regions.
(b) The following rule and portions of the control strategy are disapproved since they do not provide the degree of control needed to attain and maintain the National Ambient Air Quality Standards for particulate matter.
(1) NAQR Article 7.2.7, Particulate Matter; Table 4.2, Emissions Inventory Summary for Particulates and Table 5.2, Summary of Control Strategy Analysis for Particulates, from the Nevada Control Strategy, submitted on October 7, 1976.
(c) The following rules are disapproved because they relax the emission limitation on particulate matter.
(1) Clark County District Board of Health, Table 27.1, (Particulate Matter from Process Matter), submitted on July 24, 1979.
(2) Nevada Air Quality Regulations, Article 4, Rule 4.34, (Visible Emission from Stationary Sources), submitted on December 29, 1978, and Rule 4.3.6, (Visible Emission from Stationary Sources), submitted on June 24, 1980.
[37 FR 10877, May 31, 1972, as amended at 45 FR 8011, Feb. 6, 1980; 46 FR 43142, Aug. 27, 1981; 51 FR 40676, Nov. 7, 1986]
§ 52.1477 Nevada air pollution emergency plan.
top
Section 6.1.5 of the Emergency Episode Plan submitted on December 29, 1978 is disapproved since termination of the episode is left to the discretion of the Control Officer and not specified criteria and it does not meet the requirements of 40 CFR 51.16 and Appendix L. The old rule 6.1.5 submitted on January 28, 1972 is retained.
[45 FR 46385, July 10, 1980]
§ 52.1478 Extensions.
top
The Administrator, by the authority delegated under section 186(a)(4) of the Clean Air Act as amended in 1990, hereby extends for one year, until December 31, 1996, the attainment date for the Clark County (Las Vegas Valley), Nevada carbon monoxide nonattainment area.
[61 FR 57333, Nov. 6, 1996]
§ 52.1479 Source surveillance.
top
(a) The requirements of §51.211 of this chapter are not met, except in Clark County, since the plan does not provide adequate legally enforceable procedures for requiring owners or operators of stationary sources to maintain records of, and periodically report, information on the nature and amount of emissions.
(b) The requirements of §51.214 of this chapter are not met since the plan does not provide adequate legally enforceable procedures to require stationary sources subject to emission standards to submit information relating to emissions and operation of the emission monitors to the State as specified in Appendix P of part 51.
[37 FR 10878, May 31, 1972, as amended at 38 FR 12709, May 14, 1973; 40 FR 55331, Nov. 28, 1975; 43 FR 36933, Aug. 21, 1978; 51 FR 40677, Nov. 7, 1986]
§§ 52.1480-52.1481 [Reserved]
top
§ 52.1482 Compliance schedules.
top
(a)–(b) [Reserved]
(c) The compliance schedule revisions submitted for the sources identified below are disapproved as not meeting the requirement of subpart N of this chapter. All regulations cited are air pollution control regulations of the State, unless otherwise noted.
----------------------------------------------------------------------------------------------------------------
Source Location Regulation involved Date of adoption
----------------------------------------------------------------------------------------------------------------
Jack N. Tedford, Inc................. Fallon................. Not given.............. Aug. 14, 1972.
Basic, Inc........................... Gabbs.................. Article 4.............. Feb. 13, 1973.
Article 7.............. June 26, 1973.
Duval Corp........................... Battle Mountain........ Article 5.............. Feb. 13, 1973.
Mohave Generating Station, Southern Laughlin............... Clark County, Section Jan. 11, 1973.
California Edison Co. 16.
Section 26............. July 17, 1973.
----------------------------------------------------------------------------------------------------------------
[39 FR 14209, Apr. 22, 1974, as amended at 40 FR 3995, Jan. 27, 1975; 51 FR 40676, Nov. 7, 1986; 54 FR 25258, June 14, 1989]
§ 52.1483 Malfunction regulations.
top
(a) The following regulations are disapproved because they would permit the exemption of sources from applicable emission limitations under certain situations and therefore they do not satisfy the enforcement imperatives of section 110 of the Clean Air Act.
(1) Clark County District Board of Health
(i) Previously approved on May 14, 1973 and deleted without replacement on August 27, 1981: Section 12 (Upset, Breakdown, or Scheduled Maintenance).
(ii) Section 25, Rule 25.1, submitted by the Governor on July 24, 1979.
(iii) Section 25, Rules 25.1–25.1.4, submitted by the Governor on November 17, 1981.
[49 FR 10259, Mar. 20, 1984, as amended at 69 FR 54019, Sept. 7, 2004]
§ 52.1484 [Reserved]
top
§ 52.1485 Significant deterioration of air quality.
top
(a) The requirements of sections 160 through 165 of the Clean Air Act are not met, since the plan, except as it applies to the Clark County Health District, does not include approvable procedures for preventing the significant deterioration of air quality.
(b) Regulation for preventing significant deterioration of air quality. The provisions of §52.21 except paragraph (a)(1) are incorporated and made a part of the applicable State plan for the State of Nevada except for that portion applicable to the Clark County Health District.
(c) All applications and other information required pursuant to §52.21 from sources located in the jurisdiction of the State of Nevada shall be submitted to the Director, Department of Conservation and Natural Resources, 201 South Fall Street, Carson City, Nevada instead of the EPA Region 9 Office.
[47 FR 26621, June 21, 1982, as amended at 48 FR 28271, June 21, 1983; 68 FR 11323, Mar. 10, 2003; 68 FR 74489, Dec. 24, 2003]
§ 52.1486 Control strategy: Hydrocarbons and ozone.
top
(a) The requirements of subpart G of this chapter are not met since the plan does not provide for the attainment and maintenance of the national standard for ozone in the Las Vegas Intrastate Region (§81.80 of this chapter).
[45 FR 67347, Oct. 10, 1980, as amended at 51 FR 40676, Nov. 7, 1986]
§ 52.1487 Public hearings.
top
(a) The requirements of §51.102 (a) and (e) of this chapter are not met since NAQR, Article 2.11.4.2 allows variances (compliance schedules), to be renewed without a public hearing, thus allowing further postponement of the final compliance date for sources whose emissions contribute to violations of the national standards. Therefore, NAQR, Article 2.11.4.2 is disapproved.
[43 FR 1343, Jan. 24, 1978, as amended at 51 FR 40675, Nov. 7, 1986]
§ 52.1488 Visibility protection.
top
(a) The requirements of section 169A of the Clean Air Act are not met, because the plan does not include approvable procedures for protection of visibility in mandatory Class I Federal areas.
(b) Regulation for visibility monitoring and new source review. The provisions of §52.26 are hereby incorporated and made a part of the applicable plan for the State of Nevada. The provisions of §52.28 are hereby incorporated and made a part of the applicable plan for the State of Nevada except for that portion applicable to the Clark County Department of Air Quality and Environmental Management.
(c) Long-term strategy. The provisions of §52.29 are hereby incorporated and made part of the applicable plan for the State of Nevada.
(d) This paragraph (d) is applicable to the Mohave Generating Station located in the Las Vegas Intrastate Air Quality Control Region (§81.80 of this chapter).
(1) Definitions.
Administrator means the Administrator of EPA or her/his designee.
Boiler-operating-day shall mean any calendar day in which coal is combusted in the boiler of a unit for more than 12 hours. If coal is combusted for more than 12 but less than 24 hours during a calendar day, the calculation of that day's sulfur dioxide (SO2) emissions for the unit shall be based solely upon the average of hourly Continuous Emission Monitor System data collected during hours in which coal was combusted in the unit, and shall not include any time in which coal was not combusted.
Coal-fired shall mean the combustion of any coal in the boiler of any unit. If the Mohave Generating Station is converted to combust a fuel other than coal, such as natural gas, it shall not emit pollutants in greater amounts than that allowed by paragraph (d) of this section.
Current owners shall mean the owners of the Mohave Generating Station on December 15, 1999.
Owner or operator means the owner(s) or operator(s) of the Mohave Generating Station to which paragraph (d) of this section is applicable.
Rolling average shall mean an average over the specified period of boiler-operating-days, such that, at the end of the first specified period, a new daily average is generated each successive boiler-operating-day for each unit.
(2) Emission controls and limitations. The owner or operator shall install the following emission control equipment, and shall achieve the following air pollution emission limitations for each coal-fired unit at the Mohave Generating Station, in accordance with the deadlines set forth in paragraphs (d) (3) and (4) of this section.
(i) The owner or operator shall install and operate lime spray dryer technology on Unit 1 and Unit 2 at the Mohave Generating Station. The owner or operator shall design and construct such lime spray dryer technology to comply with the SO2 emission limitations, including the percentage reduction and pounds per million BTU in the following requirements:
(A) SO2 emissions shall be reduced at least 85% on a 90-boiler-operating-day rolling average basis. This reduction efficiency shall be calculated by comparing the total pounds of SO2 measured at the outlet flue gas stream after the baghouse to the total pounds of SO2 measured at the inlet flue gas stream to the lime spray dryer during the previous 90 boiler-operating-days.
(B) SO2 emissions shall not exceed .150 pounds per million BTU heat input on a 365-boiler-operating-day rolling average basis. This average shall be calculated by dividing the total pounds of SO2 measured at the outlet flue gas stream after the baghouse by the total heat input for the previous 365 boiler-operating-days.
(C) Compliance with the SO2 percentage reduction emission limitation above shall be determined using continuous SO2 monitor data taken from the inlet flue gas stream to the lime spray dryer compared to continuous SO2 monitor data taken from the outlet flue gas stream after the baghouse for each unit separately. Compliance with the pounds per million BTU limit shall be determined using continuous SO2 monitor data taken from the outlet flue gas stream after each baghouse. The continuous SO2 monitoring system shall comply with all applicable law (e.g., 40 CFR Part 75, or such other provisions as may be enacted). The inlet SO2 monitor shall also comply with the quality assurance-quality control procedures in 40 CFR part 75, appendix B.
(D) For purposes of calculating rolling averages, the first boiler-operating-day of a rolling average period for a unit shall be the first boiler-operating-day that occurs on or after the specified compliance date for that unit. Once the unit has operated the necessary number of days to generate an initial 90 or 365 day average, consistent with the applicable limit, each additional day the unit operates a new 90 or 365 day (“rolling”) average is generated. Thus, after the first 90 boiler-operating-days from the compliance date, the owner or operator must be in compliance with the 85 percent sulfur removal limit based on a 90-boiler-operating-day rolling average each subsequent boiler-operating-day. Likewise, after the first 365 boiler-operating-days from the compliance date, the owner or operator must be in compliance with the .150 sulfur limit based on a 365-boiler-operating-day rolling average each subsequent boiler-operating-day.
(E) Nothing in this paragraph (d) shall prohibit the owner or operator from substituting equivalent or superior control technology, provided such technology meets applicable emission limitations and schedules, upon approval by the Administrator.
(ii) The owner or operator shall install and operate fabric filter dust collectors (also known as FFDCs or baghouses), without a by-pass, on Unit 1 and Unit 2 at the Mohave Generating Station. The owner or operator shall design and construct such FFDC technology (together with or without the existing electrostatic precipitators) to comply with the following emission limitations:
(A) The opacity of emissions shall be no more than 20.0 percent, as averaged over each separate 6-minute period within an hour, beginning each hour on the hour, measured at the stack.
(B) In the event emissions from the Mohave Generating Station exceed the opacity limitation set forth in paragraph (d) of this section, the owner or operator shall not be considered in violation of this paragraph if they submit to the Administrator a written demonstration within 15 days of the event that shows the excess emissions were caused by a malfunction (a sudden and unavoidable breakdown of process or control equipment), and also shows in writing within 15 days of the event or immediately after correcting the malfunction if such correction takes longer than 15 days:
(1) To the maximum extent practicable, the air pollution control equipment, process equipment, or processes were maintained and operated in a manner consistent with good practices for minimizing emissions;
(2) Repairs were made in an expeditious fashion when the operator knew or should have known that applicable emission limitations would be exceeded or were being exceeded. Individuals working off-shift or overtime were utilized, to the maximum extent practicable, to ensure that such repairs were made as expeditiously as possible;
(3) The amount and duration of excess emissions were minimized to the maximum extent practicable during periods of such emissions;
(4) All reasonable steps were taken to minimize the impact of the excess emissions on ambient air quality; and
(5) The excess emissions are not part of a recurring pattern indicative of inadequate design, operation, or maintenance.
(C) Notwithstanding the foregoing, the owner or operator shall be excused from meeting the opacity limitation during cold startup (defined as the startup of any unit and associated FFDC system after a period of greater than 48 hours of complete shutdown of that unit and associated FFDC system) if they demonstrate that the failure to meet such limit was due to the breakage of one or more bags caused by condensed moisture.
(D) Compliance with the opacity emission limitation shall be determined using a continuous opacity monitor installed, calibrated, maintained and operated consistent with applicable law (e.g., 40 CFR Part 60, or such other provisions as may be enacted).
(iii) The owner or operator shall install and operate low-NOX burners and overfire air on Unit 1 and Unit 2 at the Mohave Generating Station.
(3) Emission control construction deadlines. The owner or operator shall meet the following deadlines for design and construction of the emission control equipment required by paragraph (d)(2) of this section. These deadlines and the design and construction deadlines set forth in paragraph (d)(4)(iii) of this section are not applicable if the emission limitation compliance deadlines of paragraph (d)(4) of this section are nonetheless met; or coal-fired units at the Mohave Generating Station are not in operation after December 31, 2005; or coal-fired units at the Mohave Generating Station are not in operation after December 31, 2005 and thereafter recommence operation in accordance with the emission controls and limitations obligations of paragraph (d)(2) of this section.
(i) Issue a binding contract to design the SO2, opacity and NOX control systems for Unit 1 and Unit 2 by March 1, 2003.
(ii) Issue a binding contract to procure the SO2, opacity and NOX control systems for Unit 1 and Unit 2 by September 1, 2003.
(iii) Commence physical, on-site construction of SO2 and opacity equipment for Unit 1 and Unit 2 by April 1, 2004.
(iv) Complete construction of SO2, opacity and NOX control equipment and complete tie in for first unit by July 1, 2005.
(v) Complete construction of SO2, opacity and NOX control equipment and complete tie in for second unit by December 31, 2005.
(4) Emission limitation compliance deadlines. (i) The owner's or operator's obligation to meet the SO2 and opacity emission limitations and NOX control obligations set forth in paragraph (d)(2) of this section shall commence on the dates listed below, unless subject to a force majeure event as provided for in paragraph (d)(7) of this section:
(A) For one unit, January 1, 2006; and
(B) For the other unit, April 1, 2006.
(ii) The unit that is to meet the emission limitations by April 1, 2006 may only be operated after December 31, 2005 if the control equipment set forth in paragraph (d)(2) of this section has been installed on that unit and the equipment is in operation. However, the control equipment may be taken out of service for one or more periods of time between December 31, 2005 and April 1, 2006 as necessary to assure its proper operation or compliance with the final emission limits.
(iii) If the current owners' entire (i.e., 100%) ownership interest in the Mohave Generating Station is sold either contemporaneously, or separately to the same person or entity or group of persons or entities acting in concert, and the closing date or dates of such sale occurs on or before December 30, 2002, then the emission limitations set forth in paragraph (d)(2) of this section shall become effective for one unit three years from the date of the last closing, and for the other unit three years and three months from the date of the last closing. With respect to interim construction deadlines, the owner or operator shall issue a binding contract to design the SO2, opacity and NOX control systems within six months of the last closing, issue a binding contract to procure such systems within 12 months of such closing, commence physical, on-site construction of SO2 and opacity control equipment within 19 months of such closing, and complete installation and tie-in of such control systems for the first unit within 36 months of the last closing and for the second unit within 39 months of the last closing.
(5) Interim emission limits. (i) For the period of time between the date of the consent decree (December 15, 1999) and the date on which each unit must commence compliance with the final emission limitations set forth in paragraph (d)(2) of this section (“interim period”), the following SO2 and opacity emission limits shall apply:
(i) SO2: SO2 emissions shall not exceed 1.0 pounds per million BTU of heat input calculated on a 90-boiler-operating-day rolling average basis for each unit;
(ii) Opacity: The opacity of emissions shall be no more than 30 percent, as averaged over each separate 6-minute period within an hour, beginning each hour on the hour, measured at the stack, with no more than 375 exceedances of 30 percent allowed per calendar quarter (including any pro rated portion thereof), regardless of reason. If the total number of excess opacity readings from the date of the consent decree (December 15, 1999) to the time the owner or operator demonstrates compliance with the final opacity limit in paragraph (d)(2) of this section, divided by the total number of quarters in the interim period (with a partial quarter included as a fraction), is equal to or less than 375, the owner or operator shall be in compliance with this interim limit.
(6) Reporting. (i) Commencing on January 1, 2001, and continuing on a bi-annual basis through April 1, 2006, or such earlier time as the owner or operator demonstrates compliance with the final emission limits set forth in paragraph (d)(2) of this section, the owner or operator shall provide to the Administrator a report that describes all significant events in the preceding six month period that may or will impact the installation and operation of pollution control equipment described in this paragraph, including the status of a full or partial sale of the Mohave Generating Station based upon non-confidential information. The owner's or operator's bi-annual reports shall also set forth for the immediately preceding two quarters: all opacity readings in excess of 30 percent, and all SO2 90-boiler-operating-day rolling averages in BTUs for each unit for the preceding two quarters.
(ii) Within 30 days after the end of the first calendar quarter for which the emission limitations in paragraph (d)(2) of this section first take effect, but in no event later than April 30, 2006, the owner or operator shall provide to the Administrator on a quarterly basis the following information:
(A) The percent SO2 emission reduction achieved at each unit during each 90-boiler-operating-day rolling average for each boiler-operating-day in the prior quarter. This report shall also include a list of the days and hours excluded for any reason from the determination of the owner's or operator's compliance with the SO2 removal requirement.
(B) All opacity readings in excess of 20.0 percent, and a statement of the cause of each excess opacity reading and any documentation with respect to any claimed malfunction or bag breakage.
(C) Each unit's 365-boiler-operating-day rolling average for each boiler-operating-day in the prior quarter following the first full 365 boiler-operating-days after the .150 pound SO2 limit in paragraph (d)(2) of this section takes effect.
(7) Force majeure provisions. (i) For the purpose of this paragraph (d), a “force majeure event” is defined as any event arising from causes wholly beyond the control of the owner or operator or any entity controlled by the owner or operator (including, without limitation, the owner's or operator's contractors and subcontractors, and any entity in active participation or concert with the owner or operator with respect to the obligations to be undertaken by the owner or operator pursuant to paragraph (d)), that delays or prevents or can reasonably be anticipated to delay or prevent compliance with the deadlines in paragraphs (d)(3) and (4) of this section, despite the owner's or operator's best efforts to meet such deadlines. The requirement that the owner or operator exercise “best efforts” to meet the deadline includes using best efforts to avoid any force majeure event before it occurs, and to use best efforts to mitigate the effects of any force majeure event as it is occurring, and after it has occurred, such that any delay is minimized to the greatest extent possible.
(ii) Without limitation, unanticipated or increased costs or changed financial circumstances shall not constitute a force majeure event. The absence of any administrative, regulatory, or legislative approval shall not constitute a force majeure event, unless the owner or operator demonstrates that, as appropriate to the approval: they made timely and complete applications for such approval(s) to meet the deadlines set forth in paragraph (d)(3) of this section or paragraph (d)(4) of this section; they complied with all requirements to obtain such approval(s); they diligently sought such approval; they diligently and timely responded to all requests for additional information; and without such approval, the owner or operator will be required to act in violation of law to meet one or more of the deadlines in paragraph (d)(3) of this section or paragraph (d)(4) of this section.
(iii) If any event occurs which causes or may cause a delay by the owner or operator in meeting any deadline in paragraphs (d) (3) or (4) of this section and the owner or operator seeks to assert the event is a force majeure event, the owner or operator shall notify the Administrator in writing within 30 days of the time the owner or operator first knew that the event is likely to cause a delay (but in no event later than the deadline itself). The owner or operator shall be deemed to have notice of any circumstance of which their contractors or subcontractors had notice, provided that those contractors or subcontractors were retained by the owner or operator to implement, in whole or in part, the requirements of paragraph (d) of this section. Within 30 days of such notice, the owner or operator shall provide in writing to the Administrator a report containing: an explanation and description of the reasons for the delay; the anticipated length of the delay; a description of the activity(ies) that will be delayed; all actions taken and to be taken to prevent or minimize the delay; a timetable by which those measures will be implemented; and a schedule that fully describes when the owner or operator proposes to meet any deadlines in paragraph (d) of this section which have been or will be affected by the claimed force majeure event. The owner or operator shall include with any notice their rationale and all available documentation supporting their claim that the delay was or will be attributable to a force majeure event.
(iv) If the Administrator agrees that the delay has been or will be caused by a force majeure event, the Administrator and the owner or operator shall stipulate to an extension of the deadline for the affected activity(ies) as is necessary to complete the activity(ies). The Administrator shall take into consideration, in establishing any new deadline(s), evidence presented by the owner or operator relating to weather, outage schedules and remobilization requirements.
(v) If the Administrator does not agree in her sole discretion that the delay or anticipated delay has been or will be caused by a force majeure event, she will notify the owner or operator in writing of this decision within 20 days after receiving the owner's or operator's report alleging a force majeure event. If the owner or operator nevertheless seeks to demonstrate a force majeure event, the matter shall be resolved by the Court.
(vi) At all times, the owner or operator shall have the burden of proving that any delay was caused by a force majeure event (including proving that the owner or operator had given proper notice and had made “best efforts” to avoid and/or mitigate such event), and of proving the duration and extent of any delay(s) attributable to such event.
(vii) Failure by the owner or operator to fulfill in any way the notification and reporting requirements of this Section shall constitute a waiver of any claim of a force majeure event as to which proper notice and/or reporting was not provided.
(viii) Any extension of one deadline based on a particular incident does not necessarily constitute an extension of any subsequent deadline(s) unless directed by the Administrator. No force majeure event caused by the absence of any administrative, regulatory, or legislative approval shall allow the Mohave Generating Station to operate after December 31, 2005, without installation and operation of the control equipment described in paragraph (d)(2) of this section.
(ix) If the owner or operator fails to perform an activity by a deadline in paragraphs (d)(3) or (4) of this section due to a force majeure event, the owner or operator may only be excused from performing that activity or activities for that period of time excused by the force majeure event. (continued)