(continued) fish and wildlife agencies.

(e) Where occupancy of United States lands or reservations has been permitted by a Federal agency having supervision over such lands, the exemption holder must concurrently notify that agency of the petition to surrender and of the steps that will be taken to restore the affected U.S. lands or reservations.

[Order 413, 50 FR 11688, Mar. 25, 1985]

§ 4.103 General provisions for case-specific exemption.
top
(a) Exemptible projects. Subject to the provisions in paragraph (b) of this section, §4.31(c), and §§4.105 and 4.106, the Commission may exempt on a case-specific basis any small hydroelectric power project from all or part of Part I of the Act, including licensing requirements. Any applications for exemption for a project shall conform to the requirements of §§4.107 or 4.108, as applicable.

(b) Limitation for licensed water power project. The Commission will not accept for filing an application for exemption from licensing for any project that is only part of a licensed water power project.

(c) Waiver. In applying for case-specific exemption from licensing, a qualified exemption applicant may petition under §385.207 of this chapter for waiver of any specific provision of §§4.102 through 4.107. The Commission will grant a waiver only if consistent with section 408 of the Energy Security Act of 1980.

[Order 413, 50 FR 11688, Mar. 25, 1985, as amended by Order 503, 53 FR 36568, Sept. 21, 1988]

§ 4.104 Amendment of exemption.
top
(a) An exemption holder must construct and operate its project as described in the exemption application approved by the Commission or its delegate.

(b) If an exemption holder desires to change the design, location, method of construction or operation of its project, it must first notify the appropriate Federal and state fish and wildlife agencies and inform them in writing of the changes it intends to implement. If these agencies determine that the changes would not cause the project to violate the terms and conditions imposed by the agencies, and if the changes would not materially alter the design, location, method of construction or operation of the project, the exemption holder may implement the changes. If any of these agencies determines that the changes would cause the project to violate the terms and conditions imposed by that agency, or if the changes would materially alter the design, location, method of construction or the operation of the project works, the exemption holder may not implement the changes without first acquiring authorization from the Commission to amend its exemption or acquiring a license for the project works that authorizes the project, as changed.

(c) An application to amend an exemption may be filed only by the holder of an exemption. An application to amend an exemption will be governed by the Commission's regulations governing applications for exemption. The Commission will not accept applications in competition with an application to amend an exemption, unless the Director of the Office of Hydropower Licensing determines that it is in the public interest to do so.

[Order 413, 50 FR 11688, Mar. 25, 1985]

§ 4.105 Action on exemption applications.
top
(a) Exemption from provisions other than licensing. An application for exemption of a small hydroelectric power project from provisions of Part I of the Act other than the licensing requirement will be processed and considered as part of the related application for license or amendment of license.

(b)(1) Consultation. The Commission will circulate a notice of application for exemption from licensing to interested agencies and Indian tribes at the time the applicant is notified that the application is accepted for filing.

(2) Non-standard terms and conditions. In approving any application for exemption from licensing, the Commission may prescribe terms or conditions in addition to those set forth in §4.106 in order to:

(i) Protect the quality or quantity of the related water supply;

(ii) Otherwise protect life, health, or property;

(iii) Avoid or mitigate adverse environmental impact; or

(iv) Better conserve, develop, or utilize in the public interest the water resources of the region.

(Energy Security Act of 1980, Pub. L. 96–294, 94 Stat. 611; Federal Power Act, as amended (16 U.S.C. 792–828c); Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2601–2645); and the Department of Energy Organization Act (42 U.S.C. 7101–7352); E.O. 12009, 3 CFR 142 (1978))

[Order 106, 45 FR 76123, Nov. 18, 1980, as amended by Order 202, 47 FR 4246, Jan. 29, 1982; Order 413, 50 FR 11688, Mar. 25, 1985; Order 533, 56 FR 23154, May 20, 1991]

§ 4.106 Standard terms and conditions of case-specific exemption from licensing.
top
Any case-specific exemption from licensing granted for a small hydroelectric power project is subject to the following standard terms and conditions:

(a) Article 1. The Commission reserves the right to conduct investigations under sections 4(g), 306, 307, and 311 of the Federal Power Act with respect to any acts, complaints, facts, conditions, practices, or other matters related to the construction, operation, or maintenance of the exempt project. If any term or condition of the exemption is violated, the Commission may revoke the exemption, issue a suitable order under section 4(g) of the Federal Power Act, or take appropriate action for enforcement, forfeiture, or penalties under Part III of the Federal Power Act.

(b) Article 2. The construction, operation, and maintenance of the exempt project must comply with any terms and conditions that the United States Fish and Wildlife Service, the National Marine Fisheries Service, and any state fish and wildlife agencies have determined are appropriate to prevent loss of, or damage to, fish or wildlife resources or otherwise to carry out the purposes of the Fish and Wildlife Coordination Act, as specified in exhibit E of the application for exemption from licensing or in the comments submitted in response to the notice of exemption application.

(c) Article 3. The Commission may revoke this exemption if actual construction of any proposed generating facilities has not begun within two years or has not been completed within four years from the date on which this exemption was granted. If an exemption is revoked under this article, the Commission will not accept from the prior exemption holder a subsequent application for exemption from licensing for the same project within two years of the revocation.

(d) Article 4. This exemption is subject to the navigation servitude of the United States if the project is located on navigable waters of the United States.

(e) Article 5. This exemption does not confer any right to use or occupy any Federal lands that may be necessary for the development or operation of the project. Any right to use or occupy any Federal lands for those purposes must be obtained from the administering Federal land agencies. The Commission may accept a license application submitted by any qualified license applicant and revoke this exemption, if any necessary right to use or occupy Federal lands for those purposes has not been obtained within one year from the date on which this exemption was granted.

(f) Article 6. In order to best develop, conserve, and utilize in the public interest the water resources of the region, the Commission may require that the exempt facilities be modified in structure or operation or may revoke this exemption.

(g) Article 7. The Commission may revoke this exemption if, in the application process, material discrepancies, inaccuracies, or falsehoods were made by or on behalf of the applicant.

(h) Article 8. Any exempted small hydroelectric power project that utilizes a dam that is more than 33 feet in height above streambed, as defined in 18 CFR 12.31(c) of this chapter, impounds more than 2,000 acre-feet of water, or has a significant or high hazard potential, as defined in 33 CFR part 222, is subject to the following provisions of 18 CFR part 12, as it may be amended:

(1) Section 12.4(b)(1) (i) and (ii), (b)(2) (i) and (iii), (b)(iv), and (b)(v);

(2) Section 12.4(c);

(3) Section 12.5;

(4) Subpart C; and

(5) Subpart D.

For the purposes of applying these provisions of 18 CFR part 12, the exempted project is deemed to be a licensed project development and the owner of the exempted project is deemed to be a licensee.

(i) Before transferring any property interests in the exempt project, the exemption holder must inform the transferee of the terms and conditions of the exemption. Within 30 days of transferring the property interests, the exemption holder must inform the Commission of the identity and address of the transferee.

[Order 106, 45 FR 76123, Nov. 18, 1980; 45 FR 77420, Nov. 24, 1980, as amended by Order 202, 47 FR 4246, Jan. 29, 1982; Order 413, 50 FR 11688, Mar. 25, 1985; Order 482, 52 FR 39630, Oct. 23, 1987; Order 413–A, 56 FR 31331, July 10, 1991]

§ 4.107 Contents of application for exemption from licensing.
top
(a) General requirements. An application for exemption from licensing submitted under this subpart must contain the introductory statement, the exhibits described in this section, the fee prescribed in §381.601 of this chapter and, if the project structures would use or occupy any lands other than Federal lands, an appendix containing documentary evidence showing that applicant has the real property interests required under §4.31(c)(2)(ii). The applicant must identify in its application all Indian tribes that may be affected by the project.

(b) Introductory statement. The application must include an introductory statement that conforms to the following format:


Before the Federal Energy Regulatory Commission

Application for Exemption of Small Hydroelectric Power Project From Licensing

(1) [Name of applicant] applies to the Federal Energy Regulatory Commission for an exemption for [name of project], a small hydroelectric power project that is proposed to have an installed capacity of 5 megawatts or less, from licensing under the Federal Power Act. [If applicable: The project is currently licensed as FERC Project No. –—.]

(2) The location of the project is:

[State or territory]____________________
____________________
[County]____________________
[Township or nearby town]____________________
____________________
[Stream or body of water]____________________
____________________

(3) The exact name and business address of each applicant are:

____________________
____________________
____________________

(4) The exact name and business address of each person authorized to act as agent for the applicant in this application are:

____________________
____________________
____________________

(5) [Name of applicant] is [specify, as appropriate: a citizen of the United States or other identified nation; an association of citizens of the United States or other identified nation; a municipality; a state; or a corporation incorporated under the laws of (specify the United States or the state or nation of incorporation, as appropriate).]


(c) Exhibit A. Exhibit A must describe the small hydroelectric power project and its proposed mode of operation. To the extent feasible, the information in this exhibit may be submitted in tabular form. The applicant must submit the following information:

(1) A brief description of any existing dam and impoundment proposed to be utilized by the small hydroelectric power project and any other existing or proposed project works and appurtenant facilities, including intake facilities, diversion structures, powerhouses, primary transmission lines, penstocks, pipelines, spillways, and other structures, and the sizes, capacities, and construction materials of those structures.

(2) The number of existing and proposed generating units at the project, including auxiliary units, the capacity of each unit, any provisions for future units, and a brief description of any plans for retirement or rehabilitation of existing generating units.

(3) The type of each hydraulic turbine of the small hydroelectric power project.

(4) A description of how the power plant is to be operated, that is, run-of-river or peaking.

(5) A graph showing a flow duration curve for the project. Identify stream gauge(s) and period of record used. If a synthetic record is utilized, provide details concerning its derivation. Furnish justification for selection of installed capacity if the hydraulic capacity of proposed generating unit(s) plus the minimum flow requirements, if not usable for power production, is less than the stream flow that is exceeded 25 percent of the time.

(6) Estimations of:

(i) The average annual generation in kilowatt-hours;

(ii) The average and design head of the power plant;

(iii) The hydraulic capacity of each turbine of the power plant (flow through the plant) in cubic feet per second;

(iv) The number of surface acres of the man-made or natural impoundment used, if any, at its normal maximum surface elevation and its net and gross storage capacities in acre-feet.

(7) The planned date for beginning and completing the proposed construction or development of generating facilities.

(8) A description of the nature and extent of any repair, reconstruction, or other modification of a dam that would occur in association with construction or development of the proposed small hydroelectric power project, including a statement of the normal maximum surface area and normal maximum surface elevation of any existing impoundment before and after construction.

(d) Exhibit G. Exhibit G is a map of the project and boundary and must conform to the specifications of §4.41(h) of this chapter.

(e) Exhibit E. This exhibit is an environmental report that must include the following information, commensurate with the scope and environmental impact of the construction and operation of the small hydroelectric power project. See §4.38 for consultation requirements.

(1) A description of the environmental setting of the project, including vegetative cover, fish and wildlife resources, water quality and quantity, land and water uses, recreational uses, historical and archeological resources, and scenic and aesthetic resources. The report must list any endangered or threatened plant and animal species, any critical habitats, and any sites eligible for or included on the National Register of Historic Places. The applicant may obtain assistance in the preparation of this information from state natural resources agencies, the state historic preservation officer, and from local offices of Federal natural resources agencies.

(2) A description of the expected environmental impacts from the proposed construction or development and the proposed operation of the small hydroelectric power project, including any impacts from any proposed changes in the capacity and mode of operation of the project if it is already generating electric power, and an explanation of the specific measures proposed by the applicant, the agencies consulted, and others to protect and enhance environmental resources and values and to mitigate adverse impacts of the project on such resources.

(3) Any additional information the applicant considers important.

(f) Exhibit F. Exhibit F is a set of drawings showing the structures and equipment of the small hydroelectric facility and must conform to the specifications of §4.41(g) of this chapter.

[Order 106, 45 FR 76123, Nov. 18, 1980, as amended by Order 225, 47 FR 19056, May 3, 1982; Order 413, 50 FR 11689, Mar. 25, 1985; Order 494, 53 FR 15381, Apr. 29, 1988; Order 533, 56 FR 23154, May 20, 1991; Order 2002, 68 FR 51121, Aug. 25, 2003]

§ 4.108 Contents of application for exemption from provisions other than licensing.
top
An application for exemption of a small hydroelectric power project from provisions of Part I of the Act other than the licensing requirement need not be prepared according to any specific format, but must be included as an identified appendix to the related application for license or amendment of license. The application for exemption must list all sections or subsections of Part I of the Act for which exemption is requested.

[Order 106, 45 FR 76123, Nov. 18, 1980]

Subpart L—Application for Amendment of License
top
§ 4.200 Applicability.
top
This part applies to any application for amendment of a license, if the applicant seeks to:

(a) Make a change in the physical features of the project or its boundary, or make an addition, betterment, abandonment, or conversion, of such character as to constitute an alteration of the license;

(b) Make a change in the plans for the project under license; or

(c) Extend the time fixed in the license for commencement or completion of project works.

[Order 184, 46 FR 55943, Nov. 13, 1981, as amended by Order 2002, 68 FR 51121, Aug. 25, 2003]

§ 4.201 Contents of application.
top
An application for amendment of a license for a water power project must contain the following information in the form specified.

(a) Initial statement.


Before the Federal Energy Regulatory Commission

Application for Amendment of License

(1) [Name of applicant] applies to the Federal Energy Regulatory Commission for an amendment of license for the [name of project] water power project.

(2) The exact name, business address, and telephone number of the applicant are:

____________________
____________________
____________________

(3) The applicant is a [citizen of the United States, association of citizens of the United States, domestic corporation, municipality, or state, as appropriate, see 16 U.S.C. 796], licensee for the water power project, designated as Project No. ___ in the records of the Federal Energy Regulatory Commission, issued on the ______ day of _______, 19__.

(4) The amendments of license proposed and the reason(s) why the proposed changes are necessary, are: [Give a statement or description]

(5)(i) The statutory or regulatory requirements of the state(s) in which the project would be located that affect the project as proposed with respect to bed and banks and to the appropriation, diversion, and use of water for power purposes are: [provide citation and brief identification of the nature of each requirement.]

(ii) The steps which the applicant has taken or plans to take to comply with each of the laws cited above are: [provide brief description for each law.]


(b) Required exhibits for capacity related amendments. Any application to amend a license for a hydropower project that involves additional capacity not previously authorized, and that would increase the actual or proposed total installed capacity of the project, would result in an increase in the maximum hydraulic capacity of the project of 15 percent or more, and would result in an increase in the installed name-plate capacity of 2 megawatts or more, must contain the following exhibits, or revisions or additions to any exhibits on file, commensurate with the scope of the licensed project:

(1) For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of more than 5 MW—Exhibits A, B, C, D, E, F, and G under §4.41 of this chapter;

(2) For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of 1.5 MW or less—Exhibits E, F, and G under §4.61 of this chapter;

(3) For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of 5 MW or less, but more than 1.5 MW—Exhibits F and G under §4.61 of this chapter, and Exhibit E under §4.41 of this chapter;

(4) For amendment of a license for a water power project that, at the time the application for amendment is filed, has been constructed, and is proposed to have a total installed generating capacity of 5 MW or less—Exhibit E, F and G under §4.61 of this chapter;

(5) For amendment of a license for a water power project that, at the time the application is filed, has been constructed and is proposed to have a total installed generating capacity of more than 5 MW—Exhibits A, B, C, D, E, F, and G under §4.51 of this chapter.

(c) Required exhibits for non-capacity related amendments. Any application to amend a license for a water power project that would not be a capacity related amendment as described in paragraph (b) of this section must contain those exhibits that require revision in light of the nature of the proposed amendments.

(d) Consultation and waiver. (1) If an applicant for license under this subpart believes that any exhibit required under paragraph (b) of this section is inappropriate with respect to the particular amendment of license sought by the applicant, a petition for waiver of the requirement to submit such exhibit may be submitted to the Commission under §385.207(c)(4) of this chapter, after consultation with the Commission's Division by Hydropower Licensing.

(2) A licensee wishing to file an application for amendment of license under this section may seek advice from the Commission staff regarding which exhibits(s) must be submitted and whether the proposed amendment is consistent with the scope of the existing licensed project.

[Order 184, 46 FR 55943, Nov. 13, 1981, as amended by Order 225, 47 FR 19056, May 3, 1982; 48 FR 4459, Feb. 1, 1983; 48 FR 16653, Apr. 19, 1983; Order 413, 50 FR 11689, Mar. 25, 1985; Order 533, 56 FR 23154, May 20, 1991]

§ 4.202 Alteration and extension of license.
top
(a) If it is determined that approval of the application for amendment of license would constitute a significant alteration of license pursuant to section 6 of the Act, 16 U.S.C. 799, public notice of such application shall be given at least 30 days prior to action upon the application.

(b) Any application for extension of time fixed in the license for commencement or completion of construction of project works must be filed with the Commission not less than three months prior to the date or dates so fixed.

[Order 184, 46 FR 55943, Nov. 13, 1981]

Subpart M—Fees Under Section 30(e) of the Act
top
Source: Order 487, 52 FR 48404, Dec. 22, 1987, unless otherwise noted.

§ 4.300 Purpose, definitions, and applicability.
top
(a) Purpose. This subpart implements the amendments of section 30 of the Federal Power Act enacted by section 7(c) of the Electric Consumers Protection Act of 1986 (ECPA). It establishes procedures for reimbursing fish and wildlife agencies for costs incurred in connection with applications for an exemption from licensing and applications for licenses seeking benefits under section 210 of the Public Utility Regulatory Policies Act of 1978, as amended, for a project that would impound or divert the water of a natural watercourse by means of a new dam or diversion.

(b) Definitions. For the purposes of this subpart—

(1) Cost means an expenditure made by a fish and wildlife agency:

(i) On or after the effective date of this regulation for an application filed on or after the effective date of this regulation; and

(ii) Directly related to setting mandatory terms and conditions for a proposed project pursuant to section 30(c) of the Federal Power Act.

(2) Cost statement means a statement of the total costs for which a fish and wildlife agency requests reimbursement including an itemized schedule of costs including, but not limited to, costs of fieldwork and testing, contract costs, travel costs, personnel costs, and administrative and overhead costs.

(3) Mandatory terms and conditions means terms and conditions of a license or exemption that a fish and wildlife agency determines are appropriate to prevent loss of, or damage to, fish and wildlife resources pursuant to section 30(c) of the Federal Power Act.

(4) New dam or diversion license applicant means an applicant for a license for a project that would impound or divert the water of a natural watercourse by means of a new dam or diversion, as defined in section 210(k) of the Public Utility Regulatory Policies Act of 1978, as amended.

(5) PURPA benefits means benefits under section 210 of the Public Utility Regulatory Policies Act of 1978, as amended.

(6) Section 30(c) application means an application for an exemption from licensing or a new dam or diversion license application seeking PURPA benefits.

(c) Applicability. Except as provided in paragraph (d) of this section, this subpart applies to:

(1) Any application for exemption filed on or after the effective date of these regulations for costs incurred by fish and wildlife agencies after the effective date of these regulations;

(2) Any new dam or diversion license application seeking PURPA benefits filed on or after April 16, 1988;

(3) Any new dam or diversion license application seeking PURPA benefits filed after the effective date of this regulation, but before April 16, 1988, if the applicant fails to demonstrate in a monetary resources petition filed with the Commission pursuant to §292.208 of this chapter that, before October 16, 1986, it had committed substantial monetary resources directly related to the development of the proposed project and to the diligent and timely completion of all requirements of the Commission for filing an acceptable application; and

(4) Any new dam or diversion license application seeking PURPA benefits filed after the effective date of this regulation, if the application is not accepted for filing before October 16, 1989.

(d) Exceptions. (1) This subpart does not apply to any new dam or diversion license application seeking PURPA benefits if the moratorium described in section 8(e) of ECPA is in effect. The moratorium will end at the expiration of the first full session of Congress following the session during which the Commission reports to Congress on the results of the study required under section 8(d) of ECPA.

(2) This subpart does not apply to any new dam or diversion license application seeking PURPA benefits for a project located at a Government dam, as defined in section 3(10) of the Federal Power Act, at which non-Federal hydroelectric development is permissible.

§ 4.301 Notice to fish and wildlife agencies and estimation of fees prior to filing.
top
(a) Notice to agencies—(1) New dam or diversion license applicants. During the initial stage or pre-filing agency consultation under §4.38(b)(1), a prospective new dam or diversion license applicant must inform each fish and wildlife agency consulted in writing with a copy to the Commission whether it will seek PURPA benefits.

(2) Exemption applicants. During the initial stage of pre-filing agency consultation under §4.38(b)(1), a prospective exemption applicant must notify each fish and wildlife agency consulted that it will seek an exemption from licensing.

(b) Estimate of fees. Within the comment period provided in §4.38(b)(2)(iv), a fish and wildlife agency must provide a prospective section 30(c) applicant with a reasonable estimate of the total costs the agency anticipates it will incur to set mandatory terms and conditions for the proposed project. An agency may provide an applicant with an updated estimate as it deems necessary. If an agency believes that its most recent estimate will be exceeded by more than 25 percent, it must supply the prospective applicant or applicant with a new estimate and submit a copy to the Commission.

§ 4.302 Fees at filing.
top
(a) Filing requirement. A section 30(c) application must be accompanied by a fee or a bond, together with copies of the most recent cost estimates provided by fish and wildlife agencies pursuant to §4.301(b).

(b) Amount. The fee required under paragraph (a) of this section must be in an amount equal to 50 percent of the most recent cost estimates provided by fish and wildlife agencies pursuant to §4.301(b). In lieu of this amount, an applicant may provide an unlimited term surety bond from a company on the Department of Treasury's list of companies certified to write surety bonds. Applicants bonded by a company whose certification by the Department of the Treasury lapses must provide evidence of purchase of another bond from a certified company. A bond must be for an amount no less than 100 percent of the agencies' most recent cost estimates pursuant to §4.301(b).

(c) Failure to file. The Commission will reject a section 30(c) application if the applicant fails to comply with the provisions of paragraphs (a) and (b) of this section.

§ 4.303 Post-filing procedures.
top
(a) Submission of cost statement—1) Accepted applications. Within 60 days after the last date for filing mandatory terms and conditions pursuant to §4.32(c)(4) for a new dam or diversion license application seeking PURPA benefits, §4.93(b) for an application for exemption of a small conduit hydroelectric facility, or §4.105(b)(1) for an application for case-specific exemption of a small hydroelectric power project, a fish and wildlife agency must file with the Commission a cost statement of the reasonable costs the agency incurred in setting mandatory terms and conditions for the proposed project. An agency may request, in writing, along with any supporting documentation an extension of this 60-day period.

(2) Rejected, withdrawn or dismissed applications. The Director of the Office of Energy Projects (Director) will, by letter, notify each fish and wildlife agency if a section 30(c) application is rejected, withdrawn or dismissed. Within 60 days from the date of notification, a fish and wildlife agency must file with the Commission a cost statement of the reasonable costs the agency incurred prior to the date the application was rejected, withdrawn, or dismissed. An agency may submit a written request for an extension of this 60-day period along with any supporting documentation.

(b) If an agency has not submitted a cost statement or extension request within the time provided in paragraph (a)(2) of this section, it waives its right to receive fees for that project pursuant to this subpart.

(c) Billing. After the Commission receives a cost statement from all fish and wildlife agencies as required by paragraph (a) of this section, the Commission will bill the section 30(c) applicant. The bill will show:

(1) The cost statement submitted to the Commission by each fish and wildlife agency;

(2) Any amounts already paid by the applicant pursuant to §4.302; and

(3)(i) The amount due, if the amount already paid by the applicant pursuant to §4.302 is less than the total of all the cost statements; or

(ii) The amount to be refunded to the applicant, if the amount already paid by the applicant pursuant to §4.302 is more than the total of all the cost statements.

(d) Within 45 days from the date of a bill issued under paragraph (b) of this section, a section 30(c) applicant must pay in full to the Commission any remaining amounts due on the cost statements regardless of whether any of these amounts are in dispute.

(e) Dispute procedures—(1) When to dispute. Any dispute regarding the reasonableness of any fish and wildlife agency cost statement must be made within 45 days from the date of a bill issued under paragraph (b) of this section.

(2) Assessment of disputed cost statements The burden of showing that an agency's cost statement is unreasonable is on the applicant. However, a fish and wildlife agency must supply the disputing applicant and the Commission with the documentation necessary to support its cost statement. The Director of the Office of Energy Projects will determine the reasonableness of a disputed fish and wildlife agency cost statement. The Director's decision will be in writing. The Director will notify the disputing applicant and the fish and wildlife agency of the decision by letter. Any decision of the Director may be appealed by either party pursuant to 18 CFR 385.1902. In deciding whether or not a disputed cost statement is reasonable, the Director will review the application, the disputed cost statement and any other documentation relating to the particular environmental problems associated with the disputing applicant's proposed project. The Director will consider such factors as:

(i) The time the fish and wildlife agency spent reviewing the application;

(ii) The proportion of the cost statement to the time the fish and wildlife agency spent reviewing the application;

(iii) Whether the fish and wildlife agency's expenditures conform to Federal expenditure guidelines for such items as travel, per diem, personnel, and contracting; and

(iv) Whether the studies conducted by the agency, if any, are duplicative, limited to the proposed project area, unnecessary to determine the impacts to or mitigation measures for the particular fish and wildlife resources affected by the proposed project, or otherwise unnecessary to set terms and conditions for the proposed project.

(3) Unreasonable cost statements. If the Director determines that a disputed fish and wildlife agency cost statement is unreasonable, the disputing applicant and the fish and wildlife agency will be afforded 45 days from the date of notification to attempt to reach an agreement regarding the reimbursable costs of the agency. If the disputing applicant and the fish and wildlife agency fail to reach an agreement on the disputed cost statement within 45 days from the date of notification, the Director will determine the costs that the agency should reasonably have incurred.

(f) Refunds. (1) If the amount paid by a section 30(c) applicant under §4.302 exceeds the total amount of the cost statements submitted by fish and wildlife agencies under paragraph (a) of this section, the Commission will notify the Treasury to refund the difference to the applicant within 45 days from the date of the bill issued to the applicant under paragraph (b) of this section.

(2) If the amount paid by a section 30(c) applicant exceeds the amount determined to be reasonable by the Director pursuant to paragraph (d)(2) of this section, the Commission will notify the Treasury to refund the difference to the applicant within 45 days of the resolution of all dispute proceedings.

[Order 487, 52 FR 48404, Dec. 22, 1987, as amended by Order 647, 69 FR 32438, June 10, 2004]

§ 4.304 Payment.
top
(a) A payment required under this subpart must be made by check payable to the United States Treasury. The check must indicate that the payment is for ECPA Fees.

(b) If a payment required under this subpart is not made within the time period prescribed for making such payment, interest and penalty charges will be assessed. Interest and penalty charges will be computed in accordance with 31 U.S.C. 3717 and 4 CFR part 102.

(c) The Commission will not issue a license or exemption, unless the applicant has made full payments of any fees due under §4.303(c).

§ 4.305 Enforcement.
top
(a) The Commission may take any appropriate action permitted by law if a section 30(c) applicant does not make a payment required under this subpart. The Commission will not be liable to any fish and wildlife agency for failure to collect any amounts under this subpart.

(b) If the Commission is unable to collect the full amount due by a section 30(c) applicant on behalf of more than one agency, the amount the Commission does collect will be distributed to the agencies on a pro-rata basis except if an agency's cost statement is greater than its most recent estimate to the applicant under §4.301(b), then the difference between the estimate and the cost statement will not be reimbursed until any amounts owed to other agencies have been paid.