(7) List of literature. The report must include a list of all publications, reports, and other literature which were cited or otherwise utilized in the preparation of any part of the environmental report.

(g) Exhibit F. See §4.41(g) of this chapter.

(h) Exhibit G. See §4.41(h) of this chapter.

[Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 123, 46 FR 9029, Jan. 28, 1981; Order 183, 46 FR 55251, Nov. 9, 1981; Order 184, 46 FR 55942, Nov. 13, 1981; Order 413, 50 FR 11684, Mar. 25, 1985; Order 464, 52 FR 5449, Feb. 23, 1987; Order 540, 57 FR 21737, May 22, 1992; Order 2002, 68 FR 51120, Aug. 25, 2003; 68 FR 61742, Oct. 30, 2003]

Subpart G—Application for License for Minor Water Power Projects and Major Water Power Projects 5 Megawatts or Less
top
§ 4.60 Applicability and notice to agencies.
top
(a) Applicability. The provisions of this subpart apply to any application for an initial license or a new license for:

(1) A minor water power project, as defined in §4.30(b)(17);

(2) Any major project—existing dam, as defined in §4.30(b)(16), that has a total installed capacity of 5 MW or less; or

(3) Any major unconstructed project or major modified project, as defined in §4.30 (b) (15) and (14) respectively, that has a total installed capacity of 5 MW or less.

(b) Notice to agencies. The Commission will supply interested Federal, state, and local agencies with notice of any application for license for a water power project 5 MW or less and request comment on the application. Copies of the application will be available for inspection at the Commission's Public Reference Room. The applicant shall also furnish copies of the filed application to any Federal, state, or local agency that so requests.

(c) Unless an applicant for a license for a minor water power project requests in its application that the Commission apply the following provisions of Part I of the Federal Power Act when it issues a minor license for a project, the Commission, unless it determines it would not be in the public interest to do so, will waive:

(1) Section 4(b), insofar as it requires a licensee to file a statement showing the actual legitimate costs of construction of a project;

(2) Section 4(e), insofar as it relates to approval by the Chief of Engineers and the Secretary of the Army of plans affecting navigation;

(3) Section 6, insofar as it relates to the acceptance and expression in the license of terms and conditions of the Federal Power Act that are waived in the licensing order;

(4) Section 10(c), insofar as it relates to a licensee's maintenance of depreciation reserves;

(5) Sections 10(d) and 10(f);

(6) Section 14, with the exception of the right of the United States or any state or municipality to take over, maintain, and operate a project through condemnation proceedings; and

(7) Sections 15, 16, 19, 20 and 22.

[Order 413, 50 FR 11685, Mar. 25, 1985, as amended by Order 513, 54 FR 23806, June 2, 1989; Order 2002, 68 FR 51120, Aug. 25, 2003]

§ 4.61 Contents of application.
top
(a) General instructions—(1) Entry upon land. No work may be started on any proposed project works until the applicant receives a signed license from the Commission. Acceptance of an application does not authorize entry upon public lands or reservations of the United States for any purpose. The applicant should determine whether any additional Federal, state, or local permits are required.

(2) Exhibits F and G must be submitted on separate drawings. Drawings for Exhibits F and G must have identifying title blocks and bear the following certification: “This drawing is a part of the application for license made by the undersigned this _______ day of _______, 19__.”

(3) Each application for a license for a water power project 5 megawatts or less must include the information requested in the initial statement and lettered exhibits described by paragraphs (b) through (f) of this section, and must be provided in the form specified. The Commission reserves the right to require additional information, or another filing procedure, if data provided indicate such action to be appropriate.

(b) Initial statement.


Before the Federal Energy Regulatory Commission

Application for License for a [Minor Water Power Project, or Major Water Power Project, 5 Megawatts or Less, as Appropriate]

(1) _____ (Name of Applicant) applies to the Federal Energy Regulatory Commission for _____ (license or new license, as appropriate) for the _____ (name of project) water power project, as described hereinafter. (Specify any previous FERC project number designation.)

(2) The location of the project is:

State or territory:____________________
County:____________________
Township or nearby town:____________________
Stream or other body of water:____________________

(3) The exact name, address, and telephone number of the applicant are:

____________________
____________________
____________________

(4) The exact name, address, and telephone number of each person authorized to act as agent for the applicant in this application, if applicable, are:

____________________
____________________
____________________

(5) The applicant is a ___ [citizen of the United States, association of citizens of the United States, domestic corporation, municipality, or State, as appropriate] and (is/is not) claiming preference under section 7(a) of the Federal Power Act. See 16 U.S.C. 796.

(6)(i) The statutory or regulatory requirements of the state(s) in which the project would be located that affect the project as proposed with respect to bed and banks and the appropriation, diversion, and use of water for power purposes, and with respect to the right to engage in the business of developing, transmitting, and distributing power and in any other business necessary to accomplish the purposes of the license under the Federal Power Act, are: [provide citation and brief identification of the nature of each requirement; if the applicant is a municipality, the applicant must submit copies of applicable state or local laws or a municipal charter or, if such laws or documents are not clear, any other appropriate legal authority, evidencing that the municipality is competent under such laws to engage in the business of developing, transmitting, utilizing, or distributing power.]

(ii) The steps which the applicant has taken or plans to take to comply with each of the laws cited above are: [provide brief description for each requirement]

(7) Brief project description

(i) Proposed installed generating capacity ___ MW.

(ii) Check appropriate box:

o existing dam o unconstructed dam

o existing dam, major modified project (see §4.30(b)(14))

(8) Lands of the United States affected (shown on Exhibit G):




(Name) (Acres)

(i) National Forest................ ........................ .......
(ii) Indian Reservation............ ........................ .......
(iii) Public Lands Under ........................ .......
Jurisdiction of.
(iv) Other......................... ........................ .......
(v) Total U.S. Lands............... ........................ .......



(vi) Check appropriate box:

o Surveyed land o Unsurveyed land

(9) Construction of the project is planned to start within __ months, and is planned to be completed within __ months, from the date of issuance of license.


(c) Exhibit A is a description of the project and the proposed mode of operation.

(1) The exhibit must include, in tabular form if possible, as appropriate:

(i) The number of generating units, including auxiliary units, the capacity of each unit, and provisions, if any, for future units;

(ii) The type of hydraulic turbine(s);

(iii) A description of how the plant is to be operated, manual or automatic, and whether the plant is to be used for peaking;

(iv) The estimated average annual generation in kilowatt-hours or mechanical energy equivalent;

(v) The estimated average head on the plant;

(vi) The reservoir surface area in acres and, if known, the net and gross storage capacity;

(vii) The estimated minimum and maximum hydraulic capacity of the plant (flow through the plant) in cubic feet per second and estimated average flow of the stream or water body at the plant or point of diversion; for projects with installed capacity of more than 1.5 megawatts, monthly flow duration curves and a description of the drainage area for the project site must be provided;

(viii) Sizes, capacities, and construction materials, as appropriate, of pipelines, ditches, flumes, canals, intake facilities, powerhouses, dams, transmission lines, and other appurtenances; and

(ix) The estimated cost of the project.

(x) The estimated capital costs and estimated annual operation and maintenance expense of each proposed environmental measure.

(2) State the purposes of project (for example, use of power output).

(3) An estimate of the cost to develop the license application; and

(4) The on-peak and off-peak values of project power, and the basis for estimating the values, for projects which are proposed to operate in a mode other than run-of-river.

(5) The estimated average annual increase or decrease in project generation, and the estimated average annual increase or decrease of the value of project power due to a change in project operations (i.e., minimum bypass flows, limiting reservoir fluctuations) for an application for a new license;

(6) The remaining undepreciated net investment, or book value of the project;

(7) The annual operation and maintenance expenses, including insurance, and administrative and general costs;

(8) A detailed single-line electrical diagram;

(9) A statement of measures taken or planned to ensure safe management, operation, and maintenance of the project.

(d) Exhibit E is an Environmental Report.

(1) For major unconstructed and major modified projects 5 MW or less. Any application must contain an Exhibit E conforming with the data and consultation requirements of §4.41(f) of this chapter, if the application is for license for a water power project which has or is proposed to have a total installed generating capacity greater than 1.5 MW but not greater than 5 MW, and which:

(i) Would use the water power potential of a dam and impoundment which, at the time of application, has not been constructed (see §4.30(b)(15)); or

(ii) Involves any repair, modification or reconstruction of an existing dam that would result in a significant change in the normal maximum surface area or elevation of an existing impoundment or involves any change in existing project works or operations that would result in a significant environmental impact (see §4.30(b)(14)).

(2) For minor projects and major projects at existing dams 5 MW or less. An application for license for either a minor water power project with a total proposed installed generating capacity of 1.5 MW or less or a major project—existing dam with a proposed total installed capacity of 5 MW or less must contain an Exhibit E under this subparagraph. See §4.38 for consultation requirements. The Environmental Report must contain the following information:

(i) A description, including any maps or photographs which the applicant considers appropriate, of the environmental setting of the project, including vegetative cover, fish and wildlife resources, water quality and quantity, land and water uses, recreational uses, historical and archeological resources, and scenic and aesthetic resources. The report must include a discussion of endangered or threatened plant and animal species, any critical habitats, and any sites included in, or eligible for inclusion in, the National Register of Historic Places. The applicant may obtain assistance in the preparation of this information from state natural resources agencies, the state historic preservation officer, and from local offices of Federal natural resources agencies.

(ii) A description of the expected environmental impacts from proposed construction or development and the proposed operation of the power project, including any impacts from any proposed changes in the capacity and mode of operation of the project if it is already generating electric power, and an explanation of the specific measures proposed by the applicant, the agencies, and others to protect and enhance environmental resources and values and to mitigate adverse impacts of the project on such resources. The applicant must explain its reasons for not undertaking any measures proposed by any agency consulted.

(iii) A description of the steps taken by the applicant in consulting with Federal, state, and local agencies with expertise in environmental matters during the preparation of this exhibit prior to filing the application for license with the Commission. In this report, the applicant must:

(A) Indicate which agencies were consulted during the preparation of the environmental report and provide copies of letters or other documentation showing that the applicant consulted or attempted to consult with each of the relevant agencies (specifying each agency) before filing the application, including any terms or conditions of license that those agencies have determined are appropriate to prevent loss of, or damage to, natural resources; and

(B) List those agencies that were provided copies of the application as filed with the Commission, the date or dates provided, and copies of any letters that may be received from agencies commenting on the application.

(iv) Any additional information the applicant considers important.

(e) Exhibit F. See §4.41(g) of this chapter.

(f) Exhibit G. See §4.41(h) of this chapter.

[Order 185, 46 FR 55949, Nov. 13, 1981, as amended by Order 413, 50 FR 11685, Mar. 25, 1985; Order 464, 52 FR 5449, Feb. 23, 1987; Order 513, 54 FR 23806, June 2, 1989; Order 2002, 68 FR 51120, Aug. 25, 2003; 68 FR 61742, Oct. 30, 2003]

Subpart H—Application for License for Transmission Line Only
top
§ 4.70 Applicability.
top
This subpart applies to any application for license issued solely for a transmission line that transmits power from a licensed water power project to the point of junction with the distribution system or with the interconnected primary transmission system.

[Order 184, 46 FR 55942, Nov. 13, 1981, as amended by Order 2002, 68 FR 51120, Aug. 25, 2003; 68 FR 61742, Oct. 30, 2003]

§ 4.71 Contents of application.
top
An application for license for transmission line only must contain the following information in the form specified.

(a) Initial statement.


Before the Federal Energy Regulation Commission

Application for License for Transmission Line Only

(1) [Name of applicant] applies to the Federal Energy Regulatory Commission for a [license or new license, as appropriate] for the [name of project] transmission line only, as described in the attached exhibits, that is connected with FERC Project No. ___, for which a license [was issued, or application was made, as appropriate] on the _______ day of _______, 19__.

(2) The location of the transmission line would be:

State or territory:____________________
County:____________________
Township or nearby town:____________________

(3) The proposed use or market for the power to be transmitted.

(4) The exact name, business address, and telephone number of the applicant are:

____________________
____________________
____________________

(5) The applicant is a [citizen of the United States, association of citizens of the United States, domestic corporation, municipality, or State, as appropriate] and (is/is not) claiming preference under section 7(a) of the Federal Power Act. See 16 U.S.C. 796.

(6)(i) [For any applicant which, at the time of application for license for transmission line only, is a non-licensee.] The statutory or regulatory requirements of the state(s) in which the project would be located and that affect the project as proposed with respect to bed and banks and to the appropriation, diversion, and use of water for power purposes, and with respect to the right to engage in the business of developing, transmitting, and distribution power and in any other business necessary to accomplish the purposes of the license under the Federal Power Act, are: [provide citation and brief identification of the nature of each requirement; if the applicant is a municipality, the applicant must submit copies of applicable state or local laws or a municipal charter or, if such laws or documents are not clear, other appropriate legal authority, evidencing that the municipality is competent under such laws to engage in the business of developing, transmitting, utilizing, or distributing power.]

(ii) [For any applicant which, at the time of application for license for transmission line only, is a licensee.] The statutory or regulatory requirements of the state(s) in which the transmission line would be located and that affect the project as proposed with respect to bed and banks and to the appropriation, diversion, and use of water for power purposes, are: [provide citations and brief identification of the nature of each requirement.]

(iii) The steps which the applicant has taken or plans to take to comply with each of the laws cited above are: [provide brief descriptions for each law.]


(b) Required exhibits. The application must contain the following exhibits, as appropriate:

(1) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 5 MW—Exhibits A, B, C, D, E, F, and G under §4.41 of this chapter;

(2) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of 5 MW or less—Exhibits E, F, and G under §4.61 of this chapter; and

(3) For any transmission line that, at the time the application is filed, has been constructed and is proposed to be connected to any licensed water power project—Exhibits E, F, and G under §4.61 of this chapter.

[Order 184, 46 FR 55942, Nov. 13, 1981, as amended by Order 413, 50 FR 11685, Mar. 25, 1985]

Subpart I—Application for Preliminary Permit; Amendment and Cancellation of Preliminary Permit
top
Authority: Federal Power Act, as amended 16 U.S.C. 792–828c; Department of Energy Organization Act, 42 U.S.C. 7101–7352; E.O. 12009, 42 FR 46267; Public Utility Regulatory Policies Act of 1978, 16 U.S.C. 2601–2645, unless otherwise noted.

§ 4.80 Applicability.
top
Sections 4.80 through 4.83 pertain to preliminary permits under Part I of the Federal Power Act. The sole purpose of a preliminary permit is to secure priority of application for a license for a water power project under Part I of the Federal Power Act while the permittee obtains the data and performs the acts required to determine the feasibility of the project and to support an application for a license.

[Order 54, 44 FR 61336, Oct. 25, 1979, as amended by Order 413, 50 FR 11685, Mar. 25, 1985]

§ 4.81 Contents of application.
top
Each application for a preliminary permit must include the following initial statement and numbered exhibits containing the information and documents specified:

(a) Initial statement:


Before the Federal Energy Regulatory Commission

Application for Preliminary Permit

(1) [Name of applicant] applies to the Federal Energy Regulatory Commission for a preliminary permit for the proposed [name of project] water power project, as described in the attached exhibits. This application is made in order that the applicant may secure and maintain priority of application for a license for the project under Part I of the Federal Power Act while obtaining the data and performing the acts required to determine the feasibility of the project and to support an application for a license.

(2) The location of the proposed project is:

State or territory: ____________________
County: ____________________
Township or nearby town: ____________________
Stream or other body of water: ____________________
____________________

(3) The exact name, business address, and telephone number of the applicant are:

____________________
____________________
____________________

The exact name and business address of each person authorized to act as agent for the applicant in this application are:

____________________
____________________
____________________

(4) [Name of applicant] is a [citizen, association, citizens, domestic corporation, municipality, or State, as appropriate] and (is/is not) claiming preference under section 7(a) of the Federal Power Act. [If the applicant is a municipality, the applicant must submit copies of applicable state or local laws or a municipal charter or, if such laws or documents are not clear, any other appropriate legal authority, evidencing that the municipality is competent under such laws to engage in the business of development, transmitting, utilizing, or distributing power].

(5) The proposed term of the requested permit is [period not to exceed 36 months].

(6) If there is any existing dam or other project facility, the applicant must provide the name and address of the owner of the dam and facility. If the dam is federally owned or operated, provide the name of the agency.


(b) Exhibit 1 must contain a description of the proposed project, specifying and including, to the extent possible:

(1) The number, physical composition, dimensions, general configuration and, where applicable, age and condition, of any dams, spillways, penstocks, powerhouses, tailraces, or other structures, whether existing or proposed, that would be part of the project;

(2) The estimated number, surface area, storage capacity, and normal maximum surface elevation (mean sea level) of any reservoirs, whether existing or proposed, that would be part of the project;

(3) The estimated number, length, voltage, interconnections, and, where applicable, age and condition, of any primary transmission lines whether existing or proposed, that would be part of the project [see 16 U.S.C. 796(11)];

(4) The total estimated average annual energy production and installed capacity (provide only one energy and capacity value), the hydraulic head for estimating capacity and energy output, and the estimated number, rated capacity, and, where applicable, the age and condition, of any turbines and generators, whether existing or proposed, that would be part of the project works;

(5) All lands of the United States that are enclosed within the proposed project boundary described under paragraph (e)(3) of this section, identified and tabulated on a separate sheet by legal subdivisions of a public land survey of the affected area, if available. If the project boundary includes lands of the United States, such lands must be identified on a completed land description form, provided by the Commission. The project location must identify any Federal reservation, Federal tracts, and townships of the public land surveys (or official protractions thereof if unsurveyed). A copy of the form must also be sent to the Bureau of Land Management state office where the project is located;

(6) Any other information demonstrating in what manner the proposed project would develop, conserve, and utilize in the public interest the water resources of the region.

(c) Exhibit 2 is a description of studies conducted or to be conducted with respect to the proposed project, including field studies. Exhibit 2 must supply the following information:

(1) General requirement. For any proposed project, a study plan containing a description of:

(i) Any studies, investigations, tests, or surveys that are proposed to be carried out, and any that have already taken place, for the purposes of determining the technical, economic, and financial feasibility of the proposed project, taking into consideration its environmental impacts, and of preparing an application for a license for the project; and

(ii) The approximate locations and nature of any new roads that would be built for the purpose of conducting the studies; and

(2) Work plan for new dam construction. For any development within the project that would entail new dam construction, a work plan and schedule containing:

(i) A description, including the approximate location, of any field study, test, or other activity that may alter or disturb lands or waters in the vicinity of the proposed project, including floodplains and wetlands; measures that would be taken to minimize any such disturbance; and measures that would be taken to restore the altered or disturbed areas; and

(ii) A proposed schedule (a chart or graph may be used), the total duration of which does not exceed the proposed term of the permit, showing the intervals at which the studies, investigations, tests, and surveys, identified under this paragraph are proposed to be completed.

(iii) For purposes of this paragraph, new dam construction means any dam construction the studies for which would require test pits, borings, or other foundation exploration in the field.

(3) Waiver. The Commission may waive the requirements of paragraph (c)(2) pursuant to §385.207 of this chapter, upon a showing by the applicant that the field studies, tests, and other activities to be conducted under the permit would not adversely affect cultural resources or endangered species and would cause only minor alterations or disturbances of lands and waters, and that any land altered or disturbed would be adequately restored.

(4) Exhibit 2 must contain a statement of costs and financing, specifying and including, to the extent possible:

(i) The estimated costs of carrying out or preparing the studies, investigations, tests, surveys, maps, plans or specifications identified under paragraph (c) of this section;

(ii) The expected sources and extent of financing available to the applicant to carry out or prepare the studies, investigations, tests, surveys, maps, plans, or specifications identified under paragraph (c) of this section; and

(d) Exhibit 3 must include a map or series of maps, to be prepared on United States Geological Survey topographic quadrangle sheets or similar topographic maps of a State agency, if available. The maps need not conform to the precise specifications of §4.39 (a) and (b). If the scale of any base map is not sufficient to show clearly and legibly all of the information required by this paragraph, the maps submitted must be enlarged to a scale that is adequate for that purpose. (If Exhibit 4 comprises a series of maps, it must also include an index sheet showing, by outline, the parts of the entire project covered by each map of the series.) The maps must show:

(1) The location of the project as a whole with reference to the affected stream or other body of water and, if possible, to a nearby town or any permanent monuments or objects that can be noted on the maps and recognized in the field;

(2) The relative locations and physical interrelationships of the principal project features identified under paragraph (b) of this section;

(3) A proposed boundary for the project, enclosing:

(i) All principal project features identified under paragraph (b) of this section, including but not limited to any dam, reservoir, water conveyance facilities, powerplant, transmission lines, and other appurtenances; if the project is located at an existing Federal dam, the Federal dam and impoundment must be shown, but may not be included within the project boundary;

(ii) Any non-Federal lands and any public lands or reservations of the United States [see 16 U.S.C. 796 (1) and (2)] necessary for the purposes of the project. To the extent that those public lands or reservations are covered by a public land survey, the project boundary must enclose each of and only the smallest legal subdivisions (quarter-quarter section, lots, or other subdivisions, identified on the map by subdivision) that may be occupied in whole or in part by the project.

(4) Areas within or in the vicinity of the proposed project boundary which are included in or have been designated for study for inclusion in the National Wild and Scenic Rivers System; and

(5) Areas within the project boundary that, under the provisions of the Wilderness Act, have been:

(i) Designated as wilderness area;

(ii) Recommended for designation as wilderness area; or

(iii) Designated as wilderness study area.

(Federal Power Act, as amended, 16 U.S.C. 792–828c (1976); Department of Energy Organization Act, 42 U.S.C. 7101–7352 (Supp. IV 1980); E.O. 12009, 3 CFR part 142 (1978); 5 U.S.C. 553 (Supp. IV 1980))

[Order 54, 44 FR 61336, Oct. 25, 1979, as amended by Order 123, 46 FR 9029, Jan. 28, 1981; 46 FR 11811, Feb. 11, 1981; Order 225, 47 FR 19056, May 3, 1982; Order 413, 50 FR 11685, Mar. 25, 1985; Order 2002, 68 FR 51120, Aug. 25, 2003; Order 655, 70 FR 33828, June 10, 2005]

§ 4.82 Amendments.
top
(a) Any permittee may file an application for amendment of its permit, including any extension of the term of the permit that would not cause the total term to exceed three years. (Transfer of a permit is prohibited by section 5 of the Federal Power Act.) Each application for amendment of a permit must conform to any relevant requirements of §4.81 (b), (c), (d), and (e).

(b) If an application for amendment of a preliminary permit requests any material change in the proposed project, public notice of the application will be issued as required in §4.32(d)(2)(i).

(c) If an application to extend the term of a permit is submitted not less than 30 days prior to the termination of the permit, the permit term will be automatically extended (not to exceed a total term for the permit of three years) until the Commission acts on the application for an extension. The Commission will not accept extension requests that are filed less than 30 days prior to the termination of the permit.

[Order 413, 50 FR 11685, Mar. 25, 1985, as amended by Order 499, 53 FR 27002, July 18, 1988]

§ 4.83 Cancellation and loss of priority.
top
(a) The Commission may cancel a preliminary permit after notice and opportunity for hearing if the permittee fails to comply with the specific terms and conditions of the permit. The Commission may also cancel a permit for other good cause shown after notice and opportunity for hearing. Cancellation of a permit will result in loss of the permittee's priority of application for a license for the proposed project.

(b) Failure of a permittee to file an acceptable application for a license before the permit expires will result in loss of the permittee's priority of application for a license for the proposed project.

[Order 413, 50 FR 11686, Mar. 25, 1985]

§ 4.84 Surrender of permit.
top
A permittee must submit a petition to the Commission before the permittee may voluntarily surrender its permit. Unless the Commission issues an order to the contrary, the permit will remain in effect through the thirtieth day after the Commission issues a public notice of receipt of the petition.

[Order 413, 50 FR 11686, Mar. 25, 1985]

Subpart J—Exemption of Small Conduit Hydroelectric Facilities
top
§ 4.90 Applicability and purpose.
top
This subpart implements section 30 of the Federal Power Act and provides procedures for obtaining an exemption for constructed or unconstructed small conduit hydroelectric facilities, as defined in §4.30(b)(28), from all or part of the requirements of Part I of the Federal Power Act, including licensing, and the regulations issued under Part I.

[Order 76, 45 FR 28090, Apr. 28, 1980, as amended by Order 413, 50 FR 11686, Mar. 25, 1985; Order 2002, 68 FR 51121, Aug. 25, 2003]

§ 4.91 [Reserved]
top
§ 4.92 Contents of exemption application.
top
(a) An application for exemption for this subpart must include:

(1) An introductory statement, including a declaration that the facility for which application is made meets the requirements of §4.30(b)(28), the facility qualifies but for the discharge requirement of §4.30(b)(28)(v), the introductory statement must identify that fact and state that the application is accompanied by a petition for waiver of §4.30(b)(28)(v), filed pursuant to §385.207 of this chapter);

(2) Exhibits A, E, F, and G.

(3) An appendix containing documentary evidence showing that the applicant has the real property interests required under §4.31(b); and

(4) Identification of all Indian tribes that may be affected by the project.

(b) Introductory Statement. The introductory statement must be set forth in the following format:


Before the Federal Energy Regulatory Commission

Application for Exemption for Small Conduit Hydroelectric Facility

[Name of applicant] applies to the Federal Energy Regulatory Commission for an exemption for the [name of facility], a small conduit hydroelectric facility that meets the requirements of [insert the following language, as appropriate: “§4.30(b)(28) of this subpart” or “§4.30(b)(28) of this subpart, except paragraph (b)(26)(v)”], from certain provisions of Part I of the Federal Power Act.

The location of the facility is:

State or Territory: ____________________
County: ____________________
Township or nearby town: ____________________

The exact name and business address of each applicant is:

____________________

The exact name and business address of each person authorized to act as agent for the applicant in this application is:

____________________

[Name of applicant] is [a citizen of the United States, an association of citizens of the United States, a municipality, State, or a corporation incorporated under the laws of (specify the United States or the state of incorporation, as appropriate), as appropriate].

The provisions of Part I of the Federal Power Act for which exemption is requested are:

[List here all sections or subsections for which exemption is requested.]

[If the facility does not meet the requirement of §4.30(b)(28)(v), add the following sentence: “This application is accompanied by a petition for waiver of §4.30(b)(28)(v), submitted pursuant to 18 CFR 385.207.”]


(c) Exhibit A. Exhibit A must describe the small conduit hydroelectric facility and proposed mode of operation with appropriate references to Exhibits F and G. To the extent feasible the information in this exhibit may be submitted in tabular form. The following information must be included:

(1) A brief description of any conduits and associated consumptive water supply facilities, intake facilities, powerhouses, and any other structures associated with the facility.

(2) The proximate natural sources of water that supply the related conduit.

(3) The purposes for which the conduit is used.

(4) The number of generating units, including auxiliary units, the capacity of each unit, and provisions, if any, for future units.

(5) The type of each hydraulic turbine.

(6) A description of how the plant is to be operated, manually or automatically, and whether the plant is to be used for peaking.

(7) Estimations of:

(i) The average annual generation in kilowatt hours;

(ii) The average head of the plant;

(iii) The hydraulic capacity of the plant (flow through the plant) in cubic feet per second;

(iv) The average flow of the conduit at the plant or point of diversion (using best available data and explaining the sources of the data and the method of calculation); and

(v) The average amount of the flow described in paragraph (c)(7)(iv) of this section available for power generation.

(8) The planned date for beginning construction of the facility.

(9) If the hydroelectric facility discharges directly into a natural body of water and a petition for waiver of §4.30(b)(28)(v) has not been submitted, evidence that a quantity of water equal to or greater than the quantity discharged from the hydroelectric facility is withdrawn from that water body downstream into a conduit that is part of the same water supply system as the conduit on which the hydroelectric facility is located.

(10) If the hydroelectric facility discharges directly to a point of agricultural, municipal, or industrial consumption, a description of the nature and location of that point of consumption.

(11) A description of the nature and extent of any construction of a dam that would occur in association with construction of the proposed small conduit hydroelectric facility, including a statement of the normal maximum surface area and normal maximum surface elevation of any existing impoundment before and after that construction; and any evidence that the construction would occur for agricultural, municipal, or industrial consumptive purposes even if hydroelectric generating facilities were not installed.

(d) Exhibit G. Exhibit G is a map of the project and boundary and must conform to the specifications of §4.41(h) of this chapter.

(e) Exhibit E. This exhibit is an Environmental Report. It must be prepared pursuant to §4.38 and must include the following information, commensurate with the scope and environmental impact of the facility's construction and operation:

(1) A description of the environmental setting in the vicinity of the facility, including vegetative cover, fish and wildlife resources, water quality and quantity, land and water uses, recreational use, socio-economic conditions, historical and archeological resources, and visual resources. The report must give special attention to endangered or threatened plant and animal species, critical habitats, and sites eligible for or included on the National Register of Historic Places. The applicant may obtain assistance in the preparation of this information from State natural resources agencies, the State historic preservation officer, and from local offices of Federal natural resources agencies.

(2) A description of the expected environmental impacts resulting from the continued operation of an existing small conduit hydroelectric facility, or from the construction and operation of a proposed small conduit hydroelectric facility, including a discussion of the specific measures proposed by the applicant and others to protect and enhance environmental resources and to mitigate adverse impacts of the facility on them.

(3) A description of alternative means of obtaining an amount of power equivalent to that provided by the proposed or existing facility.

(4) Any additional information the applicant considers important.

(f) Exhibit F. Exhibit F is a set of drawings showing the structures and equipment of the small conduit hydroelectric facility and must conform to the specifications of §4.41(g) of this chapter.

[Order 76, 45 FR 28090, Apr. 28, 1980, as amended by Order 413, 50 FR 11686, Mar. 25, 1985; Order 533, 56 FR 23153, May 20, 1991; Order 2002, 68 FR 51121, Aug. 25, 2003]

§ 4.93 Action on exemption applications.
top
(a) An application for exemption that does not meet the eligibility requirements of §4.30(b)(28)(v) may be accepted, provided the application has been accompanied by a request for waiver under §4.92(a)(1) and the waiver request has not been denied. Acceptance of an application that has been accompanied by a request for waiver under §4.92(a)(1) does not constitute a ruling on the waiver request, unless expressly stated in the acceptance.

(b) The Commission will circulate a notice of application for exemption to interested agencies and Indian tribes at the time the applicant is notified that the application is accepted for filing.

(c) In granting an exemption the Commission may prescribe terms or conditions in addition to those set forth in §4.94, in order to:

(1) Protect the quality or quantity of the related water supply for agricultural, municipal, or industrial consumption;

(2) Otherwise protect life, health, or property;

(3) Avoid or mitigate adverse environmental impact; or

(4) Conserve, develop, or utilize in the public interest the water power resources of the region.

(d) Conversion to license application. (1) If an application for exemption under this subpart is denied by the Commission, the applicant may convert the exemption application into an application for license for the hydroelectric project.

(2) The applicant must provide the Commission with written notification, within 30 days after the date of issuance of the order denying exemption, that it intends to convert the exemption application into a license application. The applicant must submit to the Commission, no later than 90 days after the date of issuance of the order denying exemption, additional information that is necessary to conform the exemption application to the relevant regulations for a license application.

(3) If all the information timely submitted is found sufficient, together with the application for exemption, to conform to the relevant regulations for a license application, the converted application will be considered accepted for filing as of the date that the exemption application was accepted for filing.

[Order 76, 45 FR 28090, Apr. 28, 1980, as amended by Order 413, 50 FR 11687, Mar. 25, 1985; Order 533, 56 FR 23153, May 20, 1991; Order 2002, 68 FR 51121, Aug. 25, 2003]

§ 4.94 Standard terms and conditions of exemption.
top
Any exemption granted under §4.93 for a small conduit hydroelectric facility is subject to the following standard terms and conditions:

(a) Article 1. The Commission reserves the right to conduct investigations under sections 4(g), 306, 307, and 311 of the Federal Power Act with respect to any acts, complaints, facts, conditions, practices, or other matters related to the construction, operation, or maintenance of the exempt facility. If any term or condition of the exemption is violated, the Commission may revoke the exemption, issue a suitable order under section 4(g) of the Federal Power Act, or take appropriate action for enforcement, forfeiture, or penalties under Part III of the Federal Power Act.

(b) Article 2. The construction, operation, and maintenance of the exempt project must comply with any terms and conditions that the United States Fish and Wildlife Service, the National Marine Fisheries Service, and any state fish and wildlife agencies have determined are appropriate to prevent loss of, or damage to, fish or wildlife resources or otherwise to carry out the purposes of the Fish and Wildlife Coordination Act, as specified in exhibit E of the application for exemption from licensing or in the comments submitted in response to the notice of exemption application.

(c) Article 3. The Commission may revoke this exemption if actual construction of any proposed generating facilities has not begun within two years or has not been completed within four years from the effective date of this exemption. If an exemption is revoked under this article, the Commission will not accept from the prior exemption holder a subsequent application for exemption from licensing or a notice of exemption from licensing for the same project within two years of the revocation.

(d) Article 4. In order to best develop, conserve, and utilize in the public interest the water resources of the region, the Commission may require that the exempt facilities be modified in structure or operation or may revoke this exemption.

(e) Article 5. The Commission may revoke this exemption if, in the application process, material discrepancies, inaccuracies, or falsehoods were made by or on behalf of the applicant.

(f) Article 6. Before transferring any property interests in the exempt project, the exemption holder must inform the transferee of the terms and conditions of the exemption. Within 30 days of transferring the property interests, the exemption holder must inform the Commission of the identity and address of the transferee.

[Order 76, 45 FR 28090, Apr. 28, 1980, as amended by Order 413, 50 FR 11687, Mar. 25, 1985; Order 413–A, 56 FR 31331, July 10, 1991]

§ 4.95 Surrender of exemption.
top
(a) To voluntarily surrender its exemption, a holder of an exemption for a small conduit hydroelectric facility must file a petition with the Commission.

(b)(1) If construction has begun, prior to filing a petition with the Commission, the exemption holder must consult with the fish and wildlife agencies in accordance with §4.38, substituting for the information required under §4.38(b)(1) information appropriate to the disposition and restoration of the project works and lands. The petition must set forth the exemption holder's plans with respect to disposition and restoration of the project works and lands.

(2) If construction has begun, public notice of the petition will be given, and, at least 30 days thereafter, the Commission will act upon the petition.

(c) If no construction has begun, unless the Commission issues an order to the contrary, the exemption will remain in effect through the thirtieth day after the Commission issues a public notice of receipt of the petition. New applications involving the site of the surrendered exemption may be filed on the next business day.

(d) Exemptions may be surrendered only upon fulfillment by the exemption holder of such obligations under the exemption as the Commission may prescribe and, if construction has begun, upon such conditions with respect to the disposition of such project works and restoration of project lands as may be determined by the Commission and the Federal and state fish and wildlife agencies.

[Order 413, 50 FR 11687, Mar. 25, 1985]

§ 4.96 Amendment of exemption.
top
(a) An exemption holder must construct and operate its project as described in the exemption application approved by the Commission or its delegate.

(b) If an exemption holder desires to change the design, location, method of construction or operation of its project, it must first notify the appropriate Federal and state fish and wildlife agencies and inform them in writing of the changes it intends to implement. If these agencies determine that the changes would not cause the project to violate the terms and conditions imposed by the agencies, and if the changes would not materially alter the design, location, method of construction or operation of the project, the exemption holder may implement the changes. If any of these agencies determines that the changes would cause the project to violate the terms and conditions imposed by the agencies, or if the changes would materially alter the design, location, method of construction or the operation of the project works, the exemption holder may not implement the changes without first acquiring authorization from the Commission to amend its exemption, or acquiring a license that authorizes the project, as changed.

(c) An application to amend an exemption may be filed only by the holder of the exemption. An application to amend an exemption will be governed by the Commission's regulations governing applications for exemption. The Commission will not accept applications in competition with an application to amend an exemption, unless the Director of the Office of Hydropower Licensing determines that it is in the public interest to do so.

[Order 413, 50 FR 11687, Mar. 25, 1985]

Subpart K—Exemption of Small Hydroelectric Power Projects of 5 Megawatts or Less
top
§ 4.101 Applicability.
top
This subpart provides procedures for exemption on a case-specific basis from all or part of Part I of the Federal Power Act (Act), including licensing, for small hydroelectric power projects as defined in §4.30(b)(29).

(Energy Security Act of 1980, Pub. L. 96–294, 94 Stat. 611; Federal Power Act, as amended (16 U.S.C. 792–828c); Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2601–2645); and the Department of Energy Organization Act (42 U.S.C. 7101–7352); E.O. 12009, 3 CFR 142 (1978))

[Order 202, 47 FR 4243, Jan. 29, 1982, as amended by Order 413, 50 FR 11687, Mar. 25, 1985; Order 482, 52 FR 39630, Oct. 23, 1987; Order 2002, 68 FR 51121, Aug. 25, 2003]

§ 4.102 Surrender of exemption.
top
(a) To voluntarily surrender its exemption, a holder of an exemption for a small hydroelectric power project must file a petition with the Commission.

(b)(1) If construction has begun, prior to filing a petition with the Commission, the exemption holder must consult with the fish and wildlife agencies in accordance with §4.38, substituting for the information required under §4.38(b)(1) information appropriate to the disposition and restoration of the project works and lands. The petition must set forth the exemption holder's plans with respect to disposition and restoration of the project works and lands.

(2) If construction has begun, public notice of the petition will be given, and, at least 30 days thereafter, the Commission will act upon the petition. New applications involving the site may be filed on the next business day.

(c) If no construction had begun, unless the Commission issues an order to the contrary, the surrender will take effect at the close of the thirtieth day after the Commission issues a public notice of receipt of the petition. New applications involving the site may be filed on the next business day.

(d) Exemptions may be surrendered only upon fulfillment by the exemption holder of such obligations under the exemption as the Commission may prescribe and, if construction has begun, upon such conditions with respect to the disposition of such project works and restoration of project lands as may be determined by the Commission and the Federal and statefish and wildlife agencies. (continued)