CCLME.ORG - Hydraulic code rules
Loading (50 kb)...'
(continued)

Water crossing structure projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to water crossing structures:

(1) Bridge construction.

(a) Excavation for and placement of the foundation and superstructure shall be outside the ordinary high water line unless the construction site is separated from waters of the state by use of an approved dike, cofferdam, or similar structure.

(b) The bridge structure or stringers shall be placed in a manner to minimize damage to the bed.

(c) Alteration or disturbance of bank or bank vegetation shall be limited to that necessary to construct the project. All disturbed areas shall be protected from erosion, within seven calendar days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.

(d) Removal of existing or temporary structures shall be accomplished so that the structure and associated material does not enter the watercourse.

(e) The bridge shall be constructed, according to the approved design, to pass the 100-year peak flow with consideration of debris likely to be encountered. Exception shall be granted if applicant provides hydrologic or other information that supports alternative design criteria.

(f) Wastewater from project activities and water removed from within the work area shall be routed to an area landward of the ordinary high water line to allow removal of fine sediment and other contaminants prior to being discharged to state waters.

(g) Structures containing concrete shall be sufficiently cured prior to contact with water to avoid leaching.

(h) Abutments, piers, piling, sills, approach fills, etc., shall not constrict the flow so as to cause any appreciable increase (not to exceed .2 feet) in backwater elevation (calculated at the 100-year flood) or channel wide scour and shall be aligned to cause the least effect on the hydraulics of the watercourse.

(i) Riprap materials used for structure protection shall be angular rock and the placement shall be installed according to an approved design to withstand the 100-year peak flow.

(2) Temporary culvert installation.

The allowable placement of temporary culverts and time limitations shall be determined by the department, based on the specific fish resources of concern at the proposed location of the culvert.

(a) Where fish passage is a concern, temporary culverts shall be installed according to an approved design to provide adequate fish passage. In these cases, the temporary culvert installation shall meet the fish passage design criteria in Table 1 in subsection (3) of this section.

(b) Where culverts are left in place during the period of September 30 to June 15, the culvert shall be designed to maintain structural integrity to the 100-year peak flow with consideration of the debris loading likely to be encountered.

(c) Where culverts are left in place during the period June 16 to September 30, the culvert shall be designed to maintain structural integrity at a peak flow expected to occur once in 100 years during the season of installation.

(d) Disturbance of the bed and banks shall be limited to that necessary to place the culvert and any required channel modification associated with it. Affected bed and bank areas outside the culvert shall be restored to preproject condition following installation of the culvert.

(e) The culvert shall be installed in the dry, or in isolation from stream flow by the installation of a bypass flume or culvert, or by pumping the stream flow around the work area. Exception may be granted if siltation or turbidity is reduced by installing the culvert in the flowing stream. The bypass reach shall be limited to the minimum distance necessary to complete the project. Fish stranded in the bypass reach shall be safely removed to the flowing stream.

(f) Wastewater, from project activities and dewatering, shall be routed to an area outside the ordinary high water line to allow removal of fine sediment and other contaminants prior to being discharged to state waters.

(g) Imported fill which will remain in the stream after culvert removal shall consist of clean rounded gravel ranging in size from one-quarter to three inches in diameter. The use of angular rock may be approved from June 16 to September 30, where rounded rock is unavailable. Angular rock shall be removed from the watercourse and the site restored to preproject conditions upon removal of the temporary culvert.

(h) The culvert and fill shall be removed, and the disturbed bed and bank areas shall be reshaped to preproject configuration. All disturbed areas shall be protected from erosion, within seven days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors need to be considered.

(i) The temporary culvert shall be removed and the approaches shall be blocked to vehicular traffic prior to the expiration of the HPA.

(j) Temporary culverts may not be left in place for more than two years from the date of issuance of the HPA.

(3) Permanent culvert installation.

(a) In fish bearing waters or waters upstream of a fish passage barrier (which can reasonably be expected to be corrected, and if corrected, fish presence would be reestablished), culverts shall be designed and installed so as not to impede fish passage. Culverts shall only be approved for installation in spawning areas where full replacement of impacted habitat is provided by the applicant.

(b) To facilitate fish passage, culverts shall be designed to the following standards:

(i) Culverts may be approved for placement in small streams if placed on a flat gradient with the bottom of the culvert placed below the level of the streambed a minimum of twenty percent of the culvert diameter for round culverts, or twenty percent of the vertical rise for elliptical culverts (this depth consideration does not apply within bottomless culverts). Footings of bottomless culverts shall be buried sufficiently deep so they will not become exposed by scour within the culvert. The twenty percent placement below the streambed shall be measured at the culvert outlet. The culvert width at the bed, or footing width, shall be equal to or greater than the average width of the bed of the stream.

(ii) Where culvert placement is not feasible as described in (b)(i) of this subsection, the culvert design shall include the elements in (b)(ii)(A) through (E) of this subsection:

(A) Water depth at any location within culverts as installed and without a natural bed shall not be less than that identified in Table 1. The low flow design, to be used to determine the minimum depth of flow in the culvert, is the two-year seven-day low flow discharge for the subject basin or ninety-five percent exceedance flow for migration months of the fish species of concern. Where flow information is unavailable for the drainage in which the project will be conducted, calibrated flows from comparable gauged drainages may be used, or the depth may be determined using the installed no-flow condition.

(B) The high flow design discharge, used to determine maximum velocity in the culvert (see Table 1), is the flow that is not exceeded more than ten percent of the time during the months of adult fish migration. The two-year peak flood flow may be used where stream flow data are unavailable.

(C) The hydraulic drop is the abrupt drop in water surface measured at any point within or at the outlet of a culvert. The maximum hydraulic drop criteria must be satisfied at all flows between the low and high flow design criteria.

(D) The bottom of the culvert shall be placed below the natural channel grade a minimum of twenty percent of the culvert diameter for round culverts, or twenty percent of the vertical rise for elliptical culverts (this depth consideration does not apply within bottomless culverts). The downstream bed elevation, used for hydraulic calculations and culvert placement in relation to bed elevation, shall be taken at a point downstream at least four times the average width of the stream (this point need not exceed twenty-five feet from the downstream end of the culvert). The culvert capacity for flood design flow shall be determined by using the remaining capacity of the culvert.




Table 1

Fish Passage Design Criteria for Culvert Installation
Criteria Adult

Trout

>6 in. (150mm) Adult

Pink, Chum

Salmon Adult

Chinook, Coho,

Sockeye,

Steelhead


1. Velocity, Maximum (fps)


Culvert Length (ft)
a. 10 - 60 4.0 5.0 6.0
b. 60 - 100 4.0 4.0 5.0
c. 100 - 200 3.0 3.0 4.0
d. > 200 2.0 2.0 3.0


2. Flow Depth Minimum (ft) 0.8 0.8 1.0
3. Hydraulic Drop,

Maximum (ft)

0.8

0.8

1.0


(E) Appropriate statistical or hydraulic methods must be applied for the determination of flows in (b)(ii)(A) and (B) of this subsection. These design flow criteria may be modified for specific proposals as necessary to address unusual fish passage requirements, where other approved methods of empirical analysis are provided, or where the fish passage provisions of other special facilities are approved by the department.

(F) Culvert design shall include consideration of flood capacity for current conditions and future changes likely to be encountered within the stream channel, and debris and bedload passage.

(c) Culverts shall be installed according to an approved design to maintain structural integrity to the 100-year peak flow with consideration of the debris loading likely to be encountered. Exception may be granted if the applicant provides justification for a different level or a design that routes that flow past the culvert without jeopardizing the culvert or associated fill.

(d) Disturbance of the bed and banks shall be limited to that necessary to place the culvert and any required channel modification associated with it. Affected bed and bank areas outside the culvert and associated fill shall be restored to preproject configuration following installation of the culvert, and the banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.

(e) Fill associated with the culvert installation shall be protected from erosion to the 100-year peak flow.

(f) Culverts shall be designed and installed to avoid inlet scouring and shall be designed in a manner to prevent erosion of streambanks downstream of the project.

(g) Where fish passage criteria are required, the culvert facility shall be maintained by the owner(s), such that fish passage design criteria in Table 1 are not exceeded. If the structure becomes a hindrance to fish passage, the owner shall be responsible for obtaining a HPA and providing prompt repair.

(h) The culvert shall be installed in the dry or in isolation from the stream flow by the installation of a bypass flume or culvert, or by pumping the stream flow around the work area. Exception may be granted if siltation or turbidity is reduced by installing the culvert in the flowing stream. The bypass reach shall be limited to the minimum distance necessary to complete the project. Fish stranded in the bypass reach shall be safely removed to the flowing stream.

(i) Wastewater, from project activities and dewatering, shall be routed to an area outside the ordinary high water line to allow removal of fine sediment and other contaminants prior to being discharged to state waters.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-070, filed 11/14/94, effective 12/15/94. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-070, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-080
Channel change/realignment.
Channel changes/realignments are generally discouraged, and shall only be approved where the applicant can demonstrate benefits or lack of adverse impact to fish life. Channel change/realignment projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to channel change and channel realignment projects:

When approved, a channel change may occur provided:

(1) Permanent new channels shall, at a minimum, be similar in length, width, depth, floodplain configuration, and gradient, as the old channel. The new channel shall incorporate fish habitat components, bed materials, meander configuration, and native or other approved vegetation equivalent to or greater than that which previously existed in the old channel.

(2) During construction, the new channel shall be isolated from the flowing stream by plugs at the upstream and downstream ends of the new channel.

(3) Before water is diverted into a permanent new channel, the applicant shall complete the following actions:

(a) Approved fish habitat components, bed materials and bank protection to prevent erosion shall be in place.

(b) Approved fish habitat components shall be installed according to an approved design to withstand the 100-year peak flows.

(4) All disturbed areas shall be protected from erosion, within seven days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.

(5) Diversion of flow into a new channel shall be accomplished by: (a) First removing the downstream plug; (b) removing the upstream plug; and (c) closing the upstream end of the old channel.

(6) Filling of the old channel shall begin from the upstream closure and the fill material shall be compacted. Water discharging from the fill shall not adversely impact fish life.

(7) The angle of the structure used to divert the water into the new channel shall allow a smooth transition of water flow.

(8) If fish may be adversely impacted as a result of this project, the permittee will be required to capture and safely move food fish, game fish or other fish life (at the discretion of the department) to the nearest free-flowing water. The permittee may request the department to assist in capturing and safely moving fish life from the job site to free-flowing water, and assistance may be granted if personnel are available.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-080, filed 11/14/94, effective 12/15/94; 87-15-086 (Order 87-48), § 220-110-080, filed 7/20/87. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-080, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-100
Conduit crossing.
Conduit crossing projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. An HPA is not required for conduit crossings attached to bridge structures. The following technical provisions shall apply to conduit crossing projects:

(1) Conduit alignment shall be as nearly perpendicular to the watercourse as possible.

(2) The conduit shall be installed at sufficient depth so that subsequent disturbance of the bed of the watercourse is avoided.

(3) If the method used is boring or jacking:

(a) Pits shall be isolated from surface water flow;

(b) Wastewater, from project activities and dewatering, shall be routed to an area outside the ordinary high water line to allow removal of fine sediment and other contaminants prior to being discharged to state waters.

(4) If the method used is trench excavation:

(a) Trenches shall be excavated in the dry or shall be isolated from the flowing watercourse by the installation of a cofferdam, culvert, flume, or other approved method;

(b) Plowing, placement, and covering shall occur in a single pass of the equipment;

(c) Disturbance of the bed as a result of the plowing operation shall be limited to the amount necessary to complete the project.

(5) Trenches shall be backfilled with approved materials and the bed shall be returned to preproject condition.

(6) Excess spoils shall be disposed of so as not to reenter the watercourse.

(7) The conduit approach trench shall be isolated from the watercourse until laying of the conduit across the watercourse takes place.

(8) Alteration or disturbance of the banks and bank vegetation shall be limited to that necessary to construct the project. All disturbed areas shall be protected from erosion within seven days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-100, filed 11/14/94, effective 12/15/94; 87-15-086 (Order 87-48), § 220-110-100, filed 7/20/87. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-100, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-120
Temporary bypass culvert, flume, or channel.
Temporary bypass culvert, flume, or channel projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to temporary bypass culvert, flume, or channel projects:

(1) The temporary bypass culvert, flume, or channel shall be in place prior to initiation of other work in the wetted perimeter.

(2) A sandbag revetment or similar device shall be installed at the inlet to divert the entire flow through the culvert, flume, or channel.

(3) A sandbag revetment or similar device shall be installed at the downstream end of the culvert, flume, or channel to prevent backwater from entering the work area.

(4) The culvert, flume, or channel shall be of sufficient size to pass flows and debris for the duration of the project.

(5) For diversion of flow into a temporary channel the relevant provisions of WAC 220-110-080 shall apply.

(6) Prior to releasing the water flow to the project area, all bank protection or armoring shall be completed.

(7) Upon completion of the project, all material used in the temporary bypass shall be removed from the site and the site returned to preproject conditions.

(8) If fish may be adversely impacted as a result of this project, the permittee shall be required to capture and safely move game and food fish and other fish life, (at the discretion of the department), from the job site to the nearest free-flowing water. The permittee may request the department to assist in capturing and safely moving fish life from the job site to free-flowing water, and assistance may be granted if personnel are available.

(9) Alteration or disturbance of the banks and bank vegetation shall be limited to that necessary to construct the project. All disturbed areas shall be protected from erosion, within seven days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-120, filed 11/14/94, effective 12/15/94; 87-15-086 (Order 87-48), § 220-110-120, filed 7/20/87. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-120, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-130
Dredging in freshwater areas.
Dredging projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to dredging projects:

(1) Dredging shall not be conducted in fish spawning areas unless it is designed to create or improve the access or quality of fish spawning areas.

(2) During the dredging of a lake or pond, a boom or similar device may be required to contain floatable materials.

(3) Dredged bed materials shall be disposed of at approved in-water disposal sites or upland so as not to reenter state waters. The department may allow placement of dredged material in areas for beneficial uses such as beach nourishment or capping of contaminated sediments.

(4) Dredging shall be conducted with dredge types and methods that cause the least adverse impact to fish and shellfish and their habitat.

(5) If at any time, fish are observed in distress, a fish kill occurs, or water quality problems develop as a result of dredging, operations shall cease immediately and the department shall be immediately contacted.

(6) An hydraulic dredge shall only be operated with the intake at or below the surface of the material being removed. The intake shall only be raised a maximum of three feet above the bed for brief periods of purging or flushing the intake system.

(7) If a dragline or clamshell is used, it shall be operated to minimize turbidity. During excavation, each pass with the clamshell or dragline bucket shall be complete. Dredged material shall not be stockpiled waterward of the ordinary high water line.

(8) Upon completion of the dredging, the bed shall not contain pits, potholes, or large depressions to avoid stranding of fish.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-130, filed 11/14/94, effective 12/15/94. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-130, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-140
Gravel removal.
Gravel removal projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to gravel removal projects:

(1) Gravel removal from a watercourse shall be limited to removal from exposed bars and shall not result in a lowering, over time, of the average channel cross-section profile through the project area or downstream. Additional removal of bed material, including removal from wetted portions of the channel, may be authorized where the project is an integral part of a comprehensive flood control plan approved by the department.

(2) An "excavation line" shall be established. "Excavation line" means a line on the dry bed, at or parallel to the water's edge, the distance from the water's edge to be determined by the department on a site-specific basis. The excavation line may change with water level fluctuations.

(3) An "excavation zone" shall be defined as the area between the "excavation line" and the bank or the center of the bar. The "excavation zone" shall be identified by boundary markers placed by the applicant and approved by the department prior to the commencement of gravel removal.

(4) Excavation shall begin at the excavation line and proceed toward the bank or the center of the bar, perpendicular to the alignment of the watercourse.

(5) Bed material shall not be removed from the water side of the excavation line.

(6) Equipment shall not enter or operate within the wetted perimeter of the watercourse.

(7) Gravel may be removed within the excavation zone from a point beginning at the excavation line and progressing upward toward the bank or the center of the bar on a minimum two percent gradient. It may be necessary to survey the excavation zone upon completion of the gravel removal operation to ensure the two percent gradient is maintained and that no depressions exist. When required the survey shall be made at the applicant's expense.

(8) Preproject and postproject channel cross-section surveys shall be required for gravel removal projects for commercial purposes, and may be required as part of a comprehensive flood control plan approved by the department. The cross-sections shall be referenced vertically to a permanent bench mark and horizontally to a permanent base line, and shall be done perpendicular to the high flow channel every one hundred feet through the project area and at cross-sections upstream and downstream at adjacent channel riffles. The preproject survey information shall be submitted to the department at the time of application for HPA, and the postproject survey shall be submitted to the department within ninety days of completion of removal of gravel or the expiration date of the HPA, whichever occurs first.

(9) At the end of each work day the excavation zone shall not contain pits, or potholes, or depressions that may trap fish as a result of fluctuation in water levels.

(10) Stockpiling of material waterward of the ordinary high water line, after the initial bed disturbance, shall be limited to avoid impacts to fish life. If stockpiling is approved waterward of the ordinary high water line, the material shall be completely removed prior to the onset of fish spawning in the vicinity or the typical onset of increasing stream flows. Timing restrictions shall be determined on a site-specific basis. If the water level rises and makes contact with stockpiles, further operation of equipment or removal of the stockpiles shall not proceed unless authorized under a separate HPA issued by the department.

(11) The upstream end of the gravel bar shall be left undisturbed to maintain watercourse stability waterward of the ordinary high water line.

(12) Large woody material shall be retained waterward of the ordinary high water line and repositioned within the watercourse. Other debris shall be disposed of so as not to reenter the watercourse.

(13) Gravel washing or crushing operations shall not take place waterward of the ordinary high water line.

(14) Alteration or disturbance of the banks and bank vegetation shall be limited to that necessary to access the excavation zone. All disturbed areas shall be protected from erosion, within seven days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.

(15) Equipment shall be inspected, cleaned, and maintained to prevent loss of petroleum products waterward of the ordinary high water line.

(16) The department shall be notified at least five working days before the start of actual gravel removal, and upon project completion to allow for compliance inspection.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-140, filed 11/14/94, effective 12/15/94; 87-15-086 (Order 87-48), § 220-110-140, filed 7/20/87. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-140, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-150
Large woody material removal or repositioning.
Large woody material removal or repositioning projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to large woody material removal or repositioning:

(1) Large woody material removal from watercourses shall only be approved where necessary to address safety considerations, or its removal would not diminish the fish habitat quality of the watercourse. The department may approve the repositioning of large woody material within the watercourse to protect life and property or as needed to conduct a hydraulic project. Repositioned large woody material shall be placed or anchored to provide stable, functional fish habitat.

(2) Large woody material removal shall be conducted by equipment stationed on the bank, bridge, or other approved structure.

(3) Unless otherwise authorized, large woody material shall be suspended during its removal so no portion of the large woody material or limbs can damage the bed or banks. Yarding corridors or full suspension shall be required to avoid damage to riparian vegetation. It may be necessary to cut the large woody material in place, to a size that allows suspension during removal.

(4) Where large woody material cannot be suspended above the bed and banks, skid logs or similar methods shall be used to avoid bank damage. Upon completion of the yarding operation, skid logs shall be removed in a manner that avoids damage to streambanks and vegetation, and the bank shall be restored to preproject condition.

(5) Smaller limb and bark debris associated with the large woody material shall be removed and disposed of so as not to reenter the watercourse.

(6) Large woody material embedded in a bank or bed shall be left undisturbed and intact except where authorized for removal.

(7) Large woody material removal or repositioning shall be accomplished in a manner which minimizes the release of bedload, logs, or debris downstream.

(8) Depressions created in gravel bars shall be filled, smoothed over, and sloped upwards toward the bank on a minimum two percent gradient.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-150, filed 11/14/94, effective 12/15/94. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-150, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-160
Felling and yarding of timber.
The following technical provisions shall apply to any felling and yarding of timber for which an HPA is required (see WAC 220-110-020). Timber felling and yarding projects requiring an HPA shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat.

(1) Trees shall not be felled into or across a watercourse, with identifiable bed or banks, except where authorized in special provisions of an HPA.

(2) Trees or logs which enter a watercourse, with identifiable bed or banks, during felling or yarding shall remain where they enter unless parts or all of the trees or logs are specifically authorized to be removed.

(3) Logs transported across a watercourse, with identifiable bed or banks, shall be suspended so no portion of the logs or limbs can enter the watercourse or damage the bed and banks. Yarding corridors or full suspension shall be required to prevent damage to riparian vegetation.

(4) Cable tailholds may be placed over watercourses, with identifiable bed or banks, provided the number of yarding roads is kept to a minimum. When changing roads, the cable shall be moved around or over the riparian vegetation to avoid damage to the vegetation.

(5) If limbs or other small debris enter the watercourse, with identifiable bed or banks, as a result of felling and yarding of timber, they shall be removed concurrently with each change in yarding road or within seventy-two hours after entry into the watercourse and placed outside the 50-year flood plain. Limbs or other small debris shall be removed from dry watercourses prior to the normal onset of high flows. Large woody material which was in place prior to felling and yarding of timber shall not be disturbed.

(6) Precautions shall be taken to minimize the release of sediment to waters downstream from the felling or yarding activity. Sediment control devices, including, but not limited to, straw bales and filter fabric check dams, shall be used as necessary to avoid the release of sediment downstream. Accumulated sediment shall be removed from above check dams prior to their removal. The requirement to provide sediment control may be waived where adequate protection is provided through seasonal restriction of operations.

(7) There shall be no skidding or ground lead yarding or equipment operation within flowing waters in channels with defined bed or banks.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-160, filed 11/14/94, effective 12/15/94. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-160, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-170
Outfall structures.
Outfall structure projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to outfall structure projects:

(1) The outfall structure shall be constructed according to an approved design to prevent the entry of fish, except where fish passage could enhance fish life or habitat.

(2) The watercourse bank and bed at the point of discharge shall be armored to prevent scouring.

(3) Excavation for placement of the structure or armoring materials shall be isolated from the wetted perimeter.

(4) Alteration or disturbance of banks and bank vegetation shall be limited to that necessary to construct the project. All disturbed areas shall be protected from erosion within seven days of completion of the project using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.

(5) Structures containing concrete shall be sufficiently cured prior to contact with water, to avoid leaching.

(6) All piling, lumber, or other materials treated with preservatives shall be sufficiently cured to minimize leaching into the water or bed. The use of wood treated with creosote or pentachlorophenol is not allowed in lakes.



[Statutory Authority: RCW 77.12.047. 05-14-001 (Order 05-131), § 220-110-170, filed 6/22/05, effective 7/23/05. Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-170, filed 11/14/94, effective 12/15/94. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-170, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-180
Pond construction.
Pond construction projects shall incorporate mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. The following technical provisions shall apply to pond construction projects connected to a watercourse:

(1) Ponds shall not be constructed within the watercourse.

(2) Ponds shall be designed, constructed, and screened to prevent the entry of fish unless the pond will provide beneficial habitat, as determined by the department, in which case free and unrestricted access shall be provided.

(3) Pond return flow shall be located to minimize the length of the bypass reach unless the bypass reach is intended to enhance fish life or habitat.

(4) Pond construction activities involving diversion of state waters shall be dependent upon first obtaining a water right. This requirement does not apply to construction of storm water pond facilities landward of the ordinary high water line.

(5) The work area shall be isolated from the watercourse during construction of the pond, the diversion system, and the return flow system.

(6) Prior to the initial filling, all disturbed areas shall be protected from erosion, within seven days of completion of the project, using vegetation or other means. The banks shall be revegetated within one year with native or other approved woody species. Vegetative cuttings shall be planted at a maximum interval of three feet (on center), and maintained as necessary for three years to ensure eighty percent survival. Where proposed, planting densities and maintenance requirements for rooted stock will be determined on a site-specific basis. The requirement to plant woody vegetation may be waived for areas where the potential for natural revegetation is adequate, or where other engineering or safety factors preclude them.

(7) Ponds shall be designed and constructed so the outflow temperature is not harmful to fish life.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-180, filed 11/14/94, effective 12/15/94. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-180, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-190
Water diversions.
A written HPA is not required for emergency water diversions during emergency fire response. The department shall be notified prior to the diversion, when possible. When prior notification is not possible, the department shall be notified within twenty-four hours of the diversion. The hydraulic code cannot be used to limit the amount or timing of water diverted under a water right. However, construction of structures or placement of devices or other work within waters of the state which will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state, or that will utilize any of the waters of the state in order to divert water pursuant to a water right, requires an HPA. Regulation of water flow from a permanent irrigation structure by operating valves, or manipulating stop logs, check boards or head boards, does not require an HPA. Any hydraulic project activity related to a change in the manner or location of water diversion will require an HPA modification.

Persons who have gravel berm dams as the method of diversion permitted by the department prior to January 1994 shall be allowed to continue to do so consistent with the provisions of an HPA. The department can, however, condition the approval of gravel berms.

Construction or maintenance of fish screens or guards requiring use of equipment requires a written HPA. Installation of suction hoses or cleaning, adjusting, operating, and maintaining existing irrigation or stock water diversion structures including intakes or screens without the use of equipment, may be accomplished without first securing a written HPA. For these activities, compliance with the provisions of the latest edition of the Irrigation and Fish pamphlet issued by the department is required. The pamphlet shall be on-site and serve as the HPA. If a fish kill occurs or fish are observed in distress, the project activity shall cease and the department shall be notified immediately.

The following technical provisions shall apply to water diversions:

(1) Gravel berm dams shall be constructed of gravels available on site waterward of the ordinary high water line, or of clean round gravel transported to the site. Bed disturbance shall be limited to the minimum necessary to achieve the provisions of the water right. No dirt from outside the ordinary high water line shall be used to seal the dam and no logs or woody material waterward of the ordinary high water line may be utilized for construction of the dam, unless specifically authorized.

(2) Logs and large woody material may be relocated waterward of the ordinary high water line, if they block water flow into the ditch or inhibit construction.

(3) As long as the applicant or permittee can divert enough water to satisfy the water right, the diversion dam shall be constructed so that it does not hinder upstream and downstream adult and juvenile fish passage. If passage problems develop, department personnel may, after consultation, require modification of the gravel berm dam.

(4) At pump stations, screens and headgate areas, a backhoe or suction dredge may be used to remove accumulated silts and gravel from the pumping sump. Material removed shall be placed so it will not reenter state waters.

(5) Any device used for diverting water from a fish bearing watercourse shall be equipped with a fish guard to prevent passage of fish into the diversion device pursuant to RCW 75.20.040 and 77.16.220.

(6) Diversion canals shall be maintained (sediment and debris removal) to provide maximum hydraulic gradient in the diversion canal in order to minimize the need for work within the natural watercourse.

(7) The exercise of project activity associated with diversion of state waters shall be dependent upon first obtaining a water right.



[Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-190, filed 11/14/94, effective 12/15/94; 87-15-086 (Order 87-48), § 220-110-190, filed 7/20/87. Statutory Authority: RCW 75.08.012, 75.08.080 and 75.20.100. 84-04-047 (Order 84-04), § 220-110-190, filed 1/30/84. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-190, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-200
Mineral prospecting technical provisions.
WAC 220-110-201 through 220-110-205 set forth technical provisions that shall apply to mineral prospecting and placer mining projects as necessary to protect fish life. Additional special provisions may be included in written HPAs as necessary to address site-specific conditions. Written HPAs shall also have specific time limitations on project activities to protect fish life. Timing limitations for projects conducted under authority of the Gold and Fish pamphlet are found in WAC 220-110-206 through 220-110-209. Saltwater provisions may be applied to tidally influenced areas upstream of river mouths and the mainstem Columbia River downstream of Bonneville Dam where applicable in written HPAs.



[Statutory Authority: RCW 75.08.080, 75.20.100 and 75.20.330. 99-01-088 (Order 98-252), § 220-110-200, filed 12/16/98, effective 1/16/99. Statutory Authority: RCW 75.08.080. 94-23-058 (Order 94-160), § 220-110-200, filed 11/14/94, effective 12/15/94; 87-15-086 (Order 87-48), § 220-110-200, filed 7/20/87. Statutory Authority: RCW 75.20.100 and 75.08.080. 83-09-019 (Order 83-25), § 220-110-200, filed 4/13/83.]




--------------------------------------------------------------------------------

220-110-201
Common mineral prospecting technical provisions.
A copy of the current Gold and Fish pamphlet available from the department shall serve as an HPA, unless otherwise indicated, and be on the job site at all times. Mineral prospecting and placer mining projects authorized through a written HPA may incorporate additional mitigation measures as necessary to achieve no-net-loss of productive capacity of fish and shellfish habitat. Project activities may be prohibited where project impacts adversely affect fish habitats for which no proven mitigation methods are available. The following technical provisions shall apply to all mineral prospecting and placer mining projects.

(1) Excavation, collection and processing of aggregate from the bed shall comply with the timing and location restrictions specified in WAC 220-110-206 through 220-110-209. Excavation, collection and processing of aggregate within the wetted perimeter shall only occur between 5:00 a.m. and 11:00 p.m.

(2) Excavation sites shall be separated by at least two hundred feet.

(3) There shall be no excavation, collection or processing of aggregate within four hundred feet of any fishway, dam or hatchery water intake.

(4) Except as specified in WAC 220-110-203, aggregate collected from outside the bed shall not be washed, sluiced, processed or deposited within two hundred feet landward of the ordinary high water line.

(5) A maximum of five individuals eight years of age and over may collect and process aggregate from any excavation site. No more than one pit, furrow or pothole at a time shall be excavated by any one individual.

(6) Excavations shall not occur between the ordinary high water line and two hundred feet landward of the ordinary high water line. Excavations between the ordinary high water line and the toe of the bank shall not result in undercutting below the ordinary high water line or in disturbance of land surfaces above the ordinary high water line.

(7) There shall be no disturbance of live rooted vegetation of any kind. Woody debris jams and large woody material shall not be disturbed in any manner.

(8) With the exception of aggregate excavated by a suction dredge, all excavations of aggregate shall only be performed by hand or with hand-held tools. A maximum of one hand-operated cable, chain or rope winch may be used to move bed material below the ordinary high water line. Additional safety cables, chains or ropes may be attached to this material provided they do not offer a mechanical advantage and are used solely to hold material in place. The use of horses, other livestock or motorized mineral prospecting equipment, except those specifically authorized under WAC 220-110-203 through 220-110-205, is prohibited. Materials too large to be moved with a single hand-operated cable, chain or rope winch shall not be disturbed.

(9) Boulders may be moved only to facilitate collection of aggregate underneath them. Boulders shall be immediately replaced in their original location prior to working another excavation site or leaving the excavation site. Not working the excavation site for more than sixteen hours constitutes leaving the site.

(10) Only equipment, methods, locations and timing for processing aggregate specified in WAC 220-110-201 through220-110-209 are authorized. Exceptions shall require additional authorization from the department in the form of a supplemental approval to the Gold and Fish pamphlet or a written HPA. A written HPA shallbe required for exceptions in cases where "submit application" or "closed" is listed for state waters in WAC 220-110-206 through 220-110-209. Only the following exceptions may be authorized through a supplemental approval to the Gold and Fish pamphlet: (continued)