(continued)



469.370 Draft proposed order for hearing; issues raised; final order; expedited processing. (1) Based on its review of the application and the comments and recommendations on the application from state agencies and local governments, the State Department of Energy shall prepare and issue a draft proposed order on the application.

(2) Following issuance of the draft proposed order, the Energy Facility Siting Council shall hold one or more public hearings on the application for a site certificate in the affected area and elsewhere, as the council considers necessary. Notice of the hearing shall be mailed at least 20 days before the hearing. The notice shall, at a minimum:

(a) Comply with the requirements of ORS 197.763 (2), with respect to the persons notified;

(b) Include a description of the facility and the facility’s general location;

(c) Include the name of an agency representative to contact and the telephone number where additional information may be obtained;

(d) State that copies of the application and draft proposed order are available for inspection at no cost and will be provided at a reasonable cost; and

(e) State that failure to raise an issue in person or in writing prior to the close of the record of the public hearing with sufficient specificity to afford the decision maker an opportunity to respond to the issue precludes consideration of the issue in a contested case.

(3) Any issue that may be the basis for a contested case shall be raised not later than the close of the record at or following the final public hearing prior to issuance of the department’s proposed order. Such issues shall be raised with sufficient specificity to afford the council, the department and the applicant an adequate opportunity to respond to each issue. A statement of this requirement shall be made at the commencement of any public hearing on the application.

(4) After reviewing the application, the draft proposed order and any testimony given at the public hearing and after consulting with other agencies, the department shall issue a proposed order recommending approval or rejection of the application. The department shall issue public notice of the proposed order, that shall include notice of a contested case hearing specifying a deadline for requests to participate as a party or limited party and a date for the prehearing conference.

(5) Following receipt of the proposed order from the department, the council shall conduct a contested case hearing on the application for a site certificate in accordance with the applicable provisions of ORS chapter 183 and any procedures adopted by the council. The applicant shall be a party to the contested case. The council may permit any other person to become a party to the contested case in support of or in opposition to the application only if the person appeared in person or in writing at the public hearing on the site certificate application. Issues that may be the basis for a contested case shall be limited to those raised on the record of the public hearing under subsection (3) of this section, unless:

(a) The department failed to follow the requirements of subsection (2) or (3) of this section; or

(b) The action recommended in the proposed order, including any recommended conditions of the approval, differs materially from that described in the draft proposed order, in which case only new issues related to such differences may be raised.

(6) If no person requests party status to challenge the department’s proposed order, the proposed order shall be forwarded to the council and the contested case hearing shall be concluded.

(7) At the conclusion of the contested case, the council shall issue a final order, either approving or rejecting the application based upon the standards adopted under ORS 469.501 and any additional statutes, rules or local ordinances determined to be applicable to the facility by the project order, as amended. The council shall make its decision by the affirmative vote of at least four members approving or rejecting any application for a site certificate. The council may amend or reject the proposed order, so long as the council provides public notice of its hearing to adopt a final order, and provides an opportunity for the applicant and any party to the contested case to comment on material changes to the proposed order, including material changes to conditions of approval resulting from the council’s review. The council’s order shall be considered a final order for purposes of appeal.

(8) Rejection or approval of an application, together with any conditions that may be attached to the certificate, shall be subject to judicial review as provided in ORS 469.403.

(9) The council shall either approve or reject an application for a site certificate:

(a) Within 24 months after filing an application for a nuclear installation, or for a thermal power plant, other than that described in paragraph (b) of this subsection, with a nameplate rating of more than 200,000 kilowatts;

(b) Within nine months after filing of an application for a site certificate for a combustion turbine power plant, a geothermal-fueled power plant or an underground storage facility for natural gas;

(c) Within six months after filing an application for a site certificate for an energy facility, if the application is:

(A) To expand an existing industrial facility to include an energy facility;

(B) To expand an existing energy facility to achieve a nominal electric generating capacity of between 25 and 50 megawatts; or

(C) To add injection or withdrawal capacity to an existing underground gas storage facility; or

(d) Within 12 months after filing an application for a site certificate for any other energy facility.

(10) At the request of the applicant, the council shall allow expedited processing of an application for a site certificate for an energy facility with an average electric generating capacity of less than 100 megawatts. No notice of intent shall be required. Following approval of a request for expedited review, the department shall issue a project order, which may be amended at any time. The council shall either approve or reject an application for a site certificate within six months after filing the site certificate application if there are no intervenors in the contested case conducted under subsection (5) of this section. If there are intervenors in the contested case, the council shall either approve or reject an application within nine months after filing the site certificate application. For purposes of this subsection, the generating capacity of a thermal power plant is the nameplate rating of the electrical generator proposed to be installed in the plant.

(11) Failure of the council to comply with the deadlines set forth in subsection (9) or (10) of this section shall not result in the automatic issuance or denial of a site certificate.

(12) The council shall specify in the site certificate a date by which construction of the facility must begin.

(13) For a facility that is subject to and has been or will be reviewed by a federal agency under the National Environmental Policy Act, 42 U.S.C. Section 4321, et seq., the council shall conduct its site certificate review, to the maximum extent feasible, in a manner that is consistent with and does not duplicate the federal agency review. Such coordination shall include, but need not be limited to:

(a) Elimination of duplicative application, study and reporting requirements;

(b) Council use of information generated and documents prepared for the federal agency review;

(c) Development with the federal agency and reliance on a joint record to address applicable council standards;

(d) Whenever feasible, joint hearings and issuance of a site certificate decision in a time frame consistent with the federal agency review; and

(e) To the extent consistent with applicable state standards, establishment of conditions in any site certificate that are consistent with the conditions established by the federal agency. [Formerly 453.365; 1977 c.296 §14; 1977 c.794 §11; 1977 c.895 §1; 1985 c.569 §17; 1993 c.544 §4; 1993 c.569 §8; 1995 c.79 §288; 1995 c.505 §11; 1997 c.428 §2; 2001 c.134 §6]



469.371 [1985 c.569 §5; 1991 c.480 §6; repealed by 1993 c.544 §9]



469.372 [1985 c.569 §14; 1985 c.673 §196; repealed by 1993 c.544 §9]



469.373 Expedited processing for certain natural gas energy facilities. (1) Notwithstanding the expedited review process established pursuant to ORS 469.370, an applicant may apply under the provisions of this section for expedited review of an application for a site certificate for an energy facility if the energy facility:

(a) Is a combustion turbine energy facility fueled by natural gas or is a reciprocating engine fueled by natural gas, including an energy facility that uses petroleum distillate fuels for backup power generation;

(b) Is a permitted or conditional use allowed under an applicable local acknowledged comprehensive plan, land use regulation or federal land use plan, and is located:

(A) At or adjacent to an existing energy facility; or

(B)(i) At, adjacent to or in close proximity to an existing industrial use; and

(ii) In an area currently zoned or designated for industrial use;

(c)(A) Requires no more than three miles of associated transmission lines or three miles of new natural gas pipelines outside of existing rights of way for transmission lines or natural gas pipelines; or

(B) Imposes, in the determination of the Energy Facility Siting Council, no significant impact in the locating of associated transmission lines or new natural gas pipelines outside of existing rights of way;

(d) Requires no new water right or water right transfer;

(e) Provides funds to a qualified organization in an amount determined by the council to be sufficient to produce any required reduction in carbon dioxide emissions as specified in ORS 469.503 (2)(c)(C) and in rules adopted under ORS 469.503 for the total carbon dioxide emissions produced by the energy facility for the life of the energy facility; and

(f)(A) Discharges process wastewater to a wastewater treatment facility that has an existing National Pollutant Discharge Elimination System permit, can obtain an industrial pretreatment permit, if needed, within the expedited review process time frame and has written confirmation from the wastewater facility permit holder that the additional wastewater load will be accommodated by the facility without resulting in a significant thermal increase in the facility effluent or without requiring any changes to the wastewater facility National Pollutant Discharge Elimination System permit;

(B) Plans to discharge process wastewater to a wastewater treatment facility owned by a municipal corporation that will accommodate the wastewater from the energy facility and supplies evidence from the municipal corporation that:

(i) The municipal corporation has included, or intends to include, the process wastewater load from the energy facility in an application for a National Pollutant Discharge Elimination System permit; and

(ii) All conditions required of the energy facility to allow the discharge of process wastewater from the energy facility will be satisfied; or

(C) Obtains a National Pollutant Discharge Elimination System or water pollution control facility permit for process wastewater disposal, supplies evidence to support a finding that the discharge can likely be permitted within the expedited review process time frame and that the discharge will not require:

(i) A new National Pollutant Discharge Elimination System permit, except for a storm water general permit for construction activities; or

(ii) A change in any effluent limit or discharge location under an existing National Pollutant Discharge Elimination System or water pollution control facility permit.

(2) An applicant seeking expedited review under this section shall submit documentation to the State Department of Energy, prior to the submission of an application for a site certificate, that demonstrates that the energy facility meets the qualifications set forth in subsection (1) of this section. The department shall determine, within 14 days of receipt of the documentation, on a preliminary, nonbinding basis, whether the energy facility qualifies for expedited review.

(3) If the department determines that the energy facility preliminarily qualifies for expedited review, the applicant may submit an application for expedited review. Within 30 days after the date that the application for expedited review is submitted, the department shall determine whether the application is complete. If the department determines that the application is complete, the application shall be deemed filed on the date that the department sends the applicant notice of its determination. If the department determines that the application is not complete, the department shall notify the applicant of the deficiencies in the application and shall deem the application filed on the date that the department determines that the application is complete. The department or the council may request additional information from the applicant at any time.

(4) The State Department of Energy shall send a copy of a filed application to the Department of Environmental Quality, the Water Resources Department, the State Department of Fish and Wildlife, the State Department of Geology and Mineral Industries, the State Department of Agriculture, the Department of Land Conservation and Development, the Public Utility Commission and any other state agency, city, county or political subdivision of the state that has regulatory or advisory responsibility with respect to the proposed energy facility. The State Department of Energy shall send with the copy of the filed application a notice specifying that:

(a) In the event the council issues a site certificate for the energy facility, the site certificate will bind the state and all counties, cities and political subdivisions in the state as to the approval of the site, the construction of the energy facility and the operation of the energy facility, and that after the issuance of a site certificate, all permits, licenses and certificates addressed in the site certificate must be issued as required by ORS 469.401 (3); and

(b) The comments and recommendations of state agencies, counties, cities and political subdivisions concerning whether the proposed energy facility complies with any statute, rule or local ordinance that the state agency, county, city or political subdivision would normally administer in determining whether a permit, license or certificate required for the construction or operation of the energy facility should be approved will be considered only if the comments and recommendations are received by the department within a reasonable time after the date the application and notice of the application are sent by the department.

(5) Within 90 days after the date that the application was filed, the department shall issue a draft proposed order setting forth:

(a) A description of the proposed energy facility;

(b) A list of the permits, licenses and certificates that are addressed in the application and that are required for the construction or operation of the proposed energy facility;

(c) A list of the statutes, rules and local ordinances that are the standards and criteria for approval of any permit, license or certificate addressed in the application and that are required for the construction or operation of the proposed energy facility; and

(d) Proposed findings specifying how the proposed energy facility complies with the applicable standards and criteria for approval of a site certificate.

(6) The council shall review the application for site certification in the manner set forth in subsections (7) to (10) of this section and shall issue a site certificate for the facility if the council determines that the facility, with any required conditions to the site certificate, will comply with:

(a) The requirements for expedited review as specified in this section;

(b) The standards adopted by the council pursuant to ORS 469.501 (1)(a), (c) to (e), (g), (h) and (L) to (o);

(c) The requirements of ORS 469.503 (3); and

(d) The requirements of ORS 469.504 (1)(b).

(7) Following submission of an application for a site certificate, the council shall hold a public informational meeting on the application. Following the issuance of the proposed order, the council shall hold at least one public hearing on the application. The public hearing shall be held in the area affected by the energy facility. The council shall mail notice of the hearing at least 20 days prior to the hearing. The notice shall comply with the notice requirements of ORS 197.763 (2) and shall include, but need not be limited to, the following:

(a) A description of the energy facility and the general location of the energy facility;

(b) The name of a department representative to contact and the telephone number at which people may obtain additional information;

(c) A statement that copies of the application and proposed order are available for inspection at no cost and will be provided at reasonable cost; and

(d) A statement that the record for public comment on the application will close at the conclusion of the hearing and that failure to raise an issue in person or in writing prior to the close of the record, with sufficient specificity to afford the decision maker an opportunity to respond to the issue, will preclude consideration of the issue, by the council or by a court on judicial review of the council’s decision.

(8) Prior to the conclusion of the hearing, the applicant may request an opportunity to present additional written evidence, arguments or testimony regarding the application. In the alternative, prior to the conclusion of the hearing, the applicant may request a contested case hearing on the application. If the applicant requests an opportunity to present written evidence, arguments or testimony, the council shall leave the record open for that purpose only for a period not to exceed 14 days after the date of the hearing. Following the close of the record, the department shall prepare a draft final order for the council. If the applicant requests a contested case hearing, the council may grant the request if the applicant has shown good cause for a contested case hearing. If a request for a contested case hearing is granted, subsections (9) to (11) of this section do not apply, and the application shall be considered under the same contested case procedures used for a nonexpedited application for a site certificate.

(9) The council shall make its decision based on the record and the draft final order prepared by the department. The council shall, within six months of the date that the application is deemed filed:

(a) Grant the application;

(b) Grant the application with conditions;

(c) Deny the application; or

(d) Return the application to the site certification process required by ORS 469.320.

(10) If the application is granted, the council shall issue a site certificate pursuant to ORS 469.401 and 469.402. Notwithstanding subsection (6) of this section, the council may impose conditions based on standards adopted under ORS 469.501 (1)(b), (f) and (i) to (k), but may not deny an application based on those standards.

(11) Judicial review of the approval or rejection of a site certificate by the council under this section shall be as provided in ORS 469.403. [2001 c.683 §15]



Note: 469.373 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.



469.374 [1985 c.569 §15; repealed by 1993 c.544 §9]



469.375 Required findings for radioactive waste disposal facility certificate. The Energy Facility Siting Council shall not issue a site certificate for a waste disposal facility for uranium mine overburden or uranium mill tailings, mill wastes or mill by-product or for radioactive waste or radioactively contaminated containers or receptacles used in the transportation, storage, use or application of radioactive material, unless, accompanying its decision it finds:

(1) The site is:

(a) Suitable for disposal of such wastes, and the amount of the wastes, intended for disposal at the site;

(b) Not located in or adjacent to:

(A) An area determined to be potentially subject to river or creek erosion within the lifetime of the facility;

(B) Within the 500-year flood plain of a river, taking into consideration the area determined to be potentially subject to river or creek erosion within the lifetime of the facility;

(C) An active fault or an active fault zone;

(D) An area of ancient, recent or active mass movement including land sliding, flow or creep;

(E) An area subject to ocean erosion; or

(F) An area having experienced volcanic activity within the last two million years.

(2) There is no available disposal technology and no available alternative site for disposal of such wastes that would better protect the health, safety and welfare of the public and the environment;

(3) The disposal of such wastes and the amount of the wastes, at the site will be compatible with the regulatory programs of federal government for disposal of such wastes;

(4) The disposal of such wastes, and the amount of the wastes, at the site will be coordinated with the regulatory programs of adjacent states for disposal of such wastes;

(5) That following closure of the site, there will be no release of radioactive materials or radiation from the waste;

(6) That suitable deed restrictions have been placed on the site recognizing the hazard of the material; and

(7) That, where federal funding for remedial actions is not available, a surety bond in the name of the state has been provided in an amount determined by the State Department of Energy to be sufficient to cover any costs of closing the site and monitoring it or providing for its security after closure and to secure performance of any site certificate conditions. The bond may be withdrawn when the council finds that:

(a) The radioactive waste has been disposed of at a waste disposal facility for which a site certificate has been issued; and

(b) A fee has been paid to the State of Oregon sufficient for monitoring the site after closure.

(8) If any section, portion, clause or phrase of this section is for any reason held to be invalid or unconstitutional the remaining sections, portions, clauses and phrases shall not be affected but shall remain in full force or effect, and to this end the provisions of this section are severable. [Formerly 459.625; 1979 c.283 §3; 1981 c.587 §3; 1985 c.4]



469.378 Land use compatibility statement for energy facility. Notwithstanding ORS 197.180, when a state agency action or recommendation concerning an energy facility requires a land use compatibility statement prior to the action being completed, the state agency shall satisfy any applicable requirement of ORS 197.180 by conditioning the agency action or recommendation on a determination by either the Energy Facility Siting Council or the applicable city or county that the energy facility as affected by the state agency action satisfies, or will continue to satisfy, the applicable requirements of ORS 197.180. [2001 c.683 §17]



Note: 469.378 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.



469.380 [Formerly 453.375; 1977 c.794 §12; 1977 c.895 §2; 1993 c.569 §9; repealed by 1995 c.505 §32]



469.390 [Formerly 453.385; repealed by 1993 c.569 §31]



469.400 [Formerly 453.395; 1977 c.794 §13; 1977 c.895 §3; repealed by 1993 c.569 §10 (469.401 and 469.403 enacted in lieu of 469.400)]



469.401 Energy facility site certificate; conditions; effect of issuance on state and local government agencies. (1) Upon approval, the site certificate or any amended site certificate with any conditions prescribed by the Energy Facility Siting Council shall be executed by the chairperson of the council and by the applicant. The certificate or amended certificate shall authorize the applicant to construct, operate and retire the facility subject to the conditions set forth in the site certificate or amended site certificate. The duration of the site certificate or amended site certificate shall be the life of the facility.

(2) The site certificate or amended site certificate shall contain conditions for the protection of the public health and safety, for the time for completion of construction, and to ensure compliance with the standards, statutes and rules described in ORS 469.501 and 469.503. The site certificate or amended site certificate shall require both parties to abide by local ordinances and state law and the rules of the council in effect on the date the site certificate or amended site certificate is executed, except that upon a clear showing of a significant threat to the public health, safety or the environment that requires application of later-adopted laws or rules, the council may require compliance with such later-adopted laws or rules. For a permit addressed in the site certificate or amended site certificate, the site certificate or amended site certificate shall provide for facility compliance with applicable state and federal laws adopted in the future to the extent that such compliance is required under the respective state agency statutes and rules.

(3) Subject to the conditions set forth in the site certificate or amended site certificate, any certificate or amended certificate signed by the chairperson of the council shall bind the state and all counties and cities and political subdivisions in this state as to the approval of the site and the construction and operation of the facility. After issuance of the site certificate or amended site certificate, any affected state agency, county, city and political subdivision shall, upon submission by the applicant of the proper applications and payment of the proper fees, but without hearings or other proceedings, promptly issue the permits, licenses and certificates addressed in the site certificate or amended site certificate, subject only to conditions set forth in the site certificate or amended site certificate. After the site certificate or amended site certificate is issued, the only issue to be decided in an administrative or judicial review of a state agency or local government permit for which compliance with governing law was considered and determined in the site certificate or amended site certificate proceeding shall be whether the permit is consistent with the terms of the site certificate or amended site certificate. Each state or local government agency that issues a permit, license or certificate shall continue to exercise enforcement authority over the permit, license or certificate.

(4) Nothing in ORS chapter 469 shall be construed to preempt the jurisdiction of any state agency or local government over matters that are not included in and governed by the site certificate or amended site certificate. Such matters include but are not limited to employee health and safety, building code compliance, wage and hour or other labor regulations, local government fees and charges or other design or operational issues that do not relate to siting the facility. [1993 c.569 §11 (469.401 and 469.403 enacted in lieu of 469.400); 1995 c.505 §12; 1999 c.385 §2]



469.402 Delegation of review of future action required by site certificate. If the Energy Facility Siting Council elects to impose conditions on a site certificate or an amended site certificate, that require subsequent review and approval of a future action, the council may delegate the future review and approval to the State Department of Energy if, in the council’s discretion, the delegation is warranted under the circumstances of the case. [1995 c.505 §27; 1999 c.385 §3]



Note: 469.402 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.



469.403 Rehearing on approval or rejection of application for site certificate or amendment; appeal; judicial review vested in Supreme Court; stay of order. (1) Any party to a contested case proceeding may apply for rehearing within 30 days from the date the approval or rejection is served. The date of service shall be the date on which the Energy Facility Siting Council delivered or mailed its approval or rejection in accordance with ORS 183.470. The application for rehearing shall set forth specifically the ground upon which the application is based. No objection to the council’s approval or rejection of an application for a site certificate or a site certificate amendment shall be considered on rehearing without good cause shown unless the basis for the objection is urged with reasonable specificity before the council in the site certificate or amended site certificate process. Upon such application, the council shall have the power to grant or deny rehearing or to abrogate or modify its order without further hearing. Unless the council acts upon the application for rehearing within 30 days after the application is filed, the application shall be considered denied. The filing of an application for rehearing shall not, unless specifically ordered by the council, operate as a stay of the site certificate or amended site certificate for the facility.

(2) Any party to a contested case proceeding on a site certificate or amended site certificate application may appeal the council’s approval or rejection of the site certificate or amended site certificate application. Issues on appeal shall be limited to those raised by the parties to the contested case proceeding before the council.

(3) Jurisdiction for judicial review of the council’s approval or rejection of an application for a site certificate or amended site certificate is conferred upon the Supreme Court. Proceedings for review shall be instituted by filing a petition in the Supreme Court. The petition shall be filed within 60 days after the date of service of the council’s final order or within 30 days after the date the petition for rehearing is denied or deemed denied. Date of service shall be the date on which the council delivered or mailed its order in accordance with ORS 183.470.

(4) The filing of a petition for judicial review may not stay the order, except that a party to the contested case may apply to the Supreme Court for a stay upon a showing that there is a colorable claim of error and that:

(a) The petitioner will suffer irreparable injury; or

(b) Construction of the energy facility will result in irreparable harm to resources protected by applicable council standards or applicable agency or local government standards.

(5) If the Supreme Court grants a stay pursuant to subsection (4) of this section, the court:

(a) Shall require the petitioner requesting the stay to give an undertaking in the amount of $5,000.

(b) May grant a stay in whole or in part.

(c) May impose other reasonable conditions on the stay.

(6) Except as otherwise provided in ORS 469.320 and this section, the review by the Supreme Court shall be the same as the review by the Court of Appeals described in ORS 183.482. The Supreme Court shall give priority on its docket to such a petition for review and shall render a decision within six months of the filing of the petition for review.

(7) The following periods of delay shall be excluded from the six-month period within which the court must render a decision under subsection (6) of this section:

(a) Any period of delay resulting from a motion properly before the court; or

(b) Any reasonable period of delay resulting from a continuance granted by the court on the court’s own motion or at the request of one of the parties, if the court granted the continuance on the basis of findings that the ends of justice served by granting the continuance outweigh the best interests of the public and the other parties in having a decision within six months.

(8) No period of delay resulting from a continuance granted by the Supreme Court under subsection (7)(b) of this section shall be excluded from the six-month period unless the court sets forth, in the record, either orally or in writing, its reasons for finding that the ends of justice served by granting the continuance outweigh the best interests of the public and the other parties in having a decision within six months. The factors the court shall consider in determining whether to grant a continuance under subsection (7)(b) of this section are:

(a) Whether the failure to grant a continuance in the proceeding would be likely to make a continuation of the proceeding impossible or result in a miscarriage of justice; or

(b) Whether the case is so unusual or so complex, due to the number of parties involved or the existence of novel questions of fact or law, that it is unreasonable to expect adequate consideration of the issues within the six-month period.

(9) No continuance under subsection (7)(b) of this section shall be granted because of general congestion of the court calendar or lack of diligent preparation or attention to the case by any member of the court or any party. [1993 c.569 §12 (469.401 and 469.403 enacted in lieu of 469.400); 1995 c.505 §13; 1999 c.385 §4; 2001 c.683 §12]



469.405 Amendment of site certificate; judicial review; exemption. (1) A site certificate may be amended with the approval of the Energy Facility Siting Council. The council may establish by rule the type of amendment that must be considered in a contested case proceeding. Judicial review of an amendment to a site certificate shall be as provided in ORS 469.403.

(2) Notwithstanding ORS 34.020 or 197.825, or any other provision of law, the land use approval by an affected local government of a proposed amendment to a facility and the recommendation of the special advisory group of applicable substantive criteria shall be subject to judicial review only as provided in ORS 469.403. If the applicant elects to show compliance with the statewide planning goals by demonstrating that the facility has received local land use approval, the provisions of this section shall apply only to proposed projects for which the land use approval by the local government occurs after the date an application for amendment is submitted to the State Department of Energy.

(3) An amendment to a site certificate is not required for a pipeline less than 16 inches in diameter and less than five miles in length that is proposed to be constructed to test or maintain an underground gas storage reservoir. If the proposed pipeline will connect to a council certified surface facility related to an underground gas storage reservoir or to a council certified gas pipeline, whether the proposed pipeline is to be located inside or outside the site of a council certified facility, the certificate holder must obtain, prior to construction, the approval of the department for the construction, operation and retirement of the proposed pipeline. The department shall approve such a proposed pipeline if the pipeline meets applicable council substantive standards. Notwithstanding ORS 469.503 (3), the department may not review the proposed pipeline for compliance with other state standards. Notwithstanding ORS 469.503 (4), or any council rule addressing compliance with land use standards, the department shall not review such a proposed pipeline for compliance with land use requirements. Notwithstanding ORS 469.401 (3), the approval by the department of such pipeline shall not bind any state or local agency. The council may adopt appropriate procedural rules for the department review. The department shall issue an order approving or rejecting the proposed pipeline. Judicial review of a department order under this section shall be as provided in ORS 469.403. [1995 c.505 §2; 1999 c.385 §5]



Note: 469.405 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.



469.407 Amendment of application to increase capacity of facility. (1) A recipient may by amendment of its application for a site certificate or by amendment of its site certificate increase the capacity of the facility if the Energy Facility Siting Council finds that:

(a) The facility will satisfy the conditions of the 500-megawatt exemption, unless modified by the council;

(b) The enlarged facility does not exceed 500 megawatts and meets the applicable carbon dioxide standard provided for in ORS 469.503 (2) for any increase in capacity beyond the capacity of the 500-megawatt exemption; and

(c) The enlarged facility meets all other applicable council standards.

(2) A recipient is deemed to meet any applicable need standard and carbon dioxide emissions standard for the nominal generating capacity of the 500-megawatt exemption provided that the recipient satisfies the conditions of the 500-megawatt exemption, unless the council modifies the conditions.

(3) As used in this section:

(a) “Recipient” means any base load gas plant, as defined in ORS 469.503, determined by the council to have the lowest net monetized air emissions among the applicants participating in a contested case proceeding.

(b) “500-megawatt exemption” means the council order in which a recipient was determined to have the lowest net monetized air emissions. [1997 c.428 §8]



Note: 469.407 and 469.409 were added to and made a part of 469.300 to 469.563 by legislative action but were not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.



469.409 Amendment of site certificate to demonstrate compliance with carbon dioxide emissions standard; binding arbitration to resolve disputes. Any site certificate holder that is required by its site certificate or by law to demonstrate need for the facility shall instead demonstrate compliance with the carbon dioxide emissions standard applicable to the type of facility subject to the site certificate before beginning construction. Such a demonstration shall be made as an amendment to the site certificate. Notwithstanding ORS 469.405 or any council rule, if the site certificate holder proceeds pursuant to ORS 469.503 (2)(c)(A) or (C), or both, the Energy Facility Siting Council shall not conduct a contested case hearing on such amendment and the council’s order shall not be subject to judicial review. Any dispute about the site certificate holder’s demonstration of compliance with the applicable carbon dioxide emissions standard shall be settled through binding arbitration. [1997 c.428 §7]



Note: See note under 469.407.



469.410 Energy facility site certificate applications filed or under construction prior to July 2, 1975; conditions of site certificate; monitoring programs. (1) Any applicant for a site certificate for an energy facility shall be deemed to have met all the requirements of ORS 176.820, 192.501 to 192.505, 192.690, 469.010 to 469.225, 469.300 to 469.563, 469.990, 757.710 and 757.720 relating to eligibility for a site certificate and a site certificate shall be issued by the Energy Facility Siting Council for:

(a) Any transmission lines for which application has been filed with the federal government and the Public Utility Commission of Oregon prior to July 2, 1975; and

(b) Any energy facility under construction on July 2, 1975.

(2) Each applicant for a site certificate under this section shall pay the fees required by ORS 469.421 (2) to (9), if applicable, and shall execute a site certificate in which the applicant agrees:

(a) To abide by the conditions of all licenses, permits and certificates required by the State of Oregon or any subdivision in the state to operate the energy facility and issued prior to July 2, 1975; and

(b) On and after July 2, 1975, to abide by the rules of the Director of the State Department of Energy adopted pursuant to ORS 469.040 (1)(d) and rules of the council adopted pursuant to ORS 469.300 to 469.563, 469.590 to 469.619 and 469.930.

(3) The council has continuing authority over the site for which the site certificate is issued and may inspect, or direct the State Department of Energy to inspect, or request another state agency or local government to inspect, the site at any time in order to ensure that the facility is being operated consistently with the terms and conditions of the site certificate and any applicable health or safety standards.

(4) The council shall establish programs for monitoring the environmental and ecological effects of the operation and the decommissioning of energy facilities subject to site certificates issued prior to July 2, 1975, to ensure continued compliance with the terms and conditions of the site certificate and any applicable health or safety standards.

(5) Site certificates executed by the Governor under ORS 469.400 (1991 Edition) prior to July 2, 1975, shall bind successor agencies created hereunder in accordance with the terms of such site certificates. Any holder of a site certificate issued prior to July 2, 1975, shall abide by the rules of the director adopted pursuant to ORS 469.040 (1)(d) and rules of the council adopted pursuant to ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992. [1975 c.606 §24; 1983 c.740 §184; 1989 c.88 §5; 1993 c.569 §13; 1995 c.505 §15]



469.420 [Formerly 453.405; 1977 c.813 §1; 1979 c.234 §1; 1981 c.792 §3; repealed by 1981 c.792 §4 (469.421 enacted in lieu of 469.420)]



469.421 Fees; exemptions; assessment of certain utilities and suppliers; penalty. (1) Subject to the provisions of ORS 469.441, any person submitting a notice of intent, a request for exemption under ORS 469.320, a request for an expedited review under ORS 469.370, a request for an expedited review under ORS 469.373, a request for the State Department of Energy to approve a pipeline under ORS 469.405 (3), an application for a site certificate or a request to amend a site certificate shall pay all expenses incurred by the Energy Facility Siting Council, the State Department of Energy and the Oregon Department of Administrative Services related to the review and decision of the council. These expenses may include legal expenses, expenses incurred in processing and evaluating the application, issuing a final order or site certificate, commissioning an independent study by a contractor, state agency or local government under ORS 469.360, and changes to the rules of the council that are specifically required and related to the particular site certificate.

(2) Every person submitting a notice of intent to file for a site certificate, a request for exemption or a request for expedited review shall submit the fee required under the fee schedule established under ORS 469.441 to the State Department of Energy when the notice or request is submitted to the council. To the extent possible, the full cost of the evaluation shall be paid from the fee paid under this subsection. However, if costs of the evaluation exceed the fee, the person submitting the notice or request shall pay any excess costs shown in an itemized statement prepared by the council. In no event shall the council incur evaluation expenses in excess of 110 percent of the fee initially paid unless the council provides prior notification to the applicant and a detailed projected budget the council believes necessary to complete the project. If costs are less than the fee paid, the excess shall be refunded to the person submitting the notice or request.

(3) Before submitting a site certificate application, the applicant shall request from the State Department of Energy an estimate of the costs expected to be incurred in processing the application. The department shall inform the applicant of that amount and require the applicant to make periodic payments of such costs pursuant to a cost reimbursement agreement. The cost reimbursement agreement shall provide for payment of 25 percent of the estimated costs when the applicant submits the application. If costs of the evaluation exceed the estimate, the applicant shall pay any excess costs shown in an itemized statement prepared by the council. In no event shall the council incur evaluation expenses in excess of 110 percent of the fee initially estimated unless the council provided prior notification to the applicant and a detailed projected budget the council believes is necessary to complete the project. If costs are less than the fee paid, the council shall refund the excess to the applicant.

(4) Any person who is delinquent in the payment of fees under subsections (1) to (3) of this section shall be subject to the provisions of subsection (11) of this section.

(5) Subject to the provisions of ORS 469.441, each holder of a certificate shall pay an annual fee, due every July 1 following issuance of a site certificate. For each fiscal year, upon approval of the State Department of Energy’s budget authorization by a regular session of the Legislative Assembly or as revised by the Emergency Board, the Director of the State Department of Energy promptly shall enter an order establishing an annual fee based on the amount of revenues that the director estimates is needed to fund the cost of ensuring that the facility is being operated consistently with the terms and conditions of the site certificate, any order issued by the department under ORS 469.405 (3) and any applicable health or safety standards. In determining this cost, the director shall include both the actual direct cost to be incurred by the council, the State Department of Energy and the Oregon Department of Administrative Services to ensure that the facility is being operated consistently with the terms and conditions of the site certificate, any order issued by the State Department of Energy under ORS 469.405 (3) and any applicable health or safety standards, and the general costs to be incurred by the council, the State Department of Energy and the Oregon Department of Administrative Services to ensure that all certificated facilities are being operated consistently with the terms and conditions of the site certificates, any orders issued by the State Department of Energy under ORS 469.405 (3) and any applicable health or safety standards that cannot be allocated to an individual, licensed facility. Not more than 35 percent of the annual fee charged each facility shall be for the recovery of these general costs. The fees for direct costs shall reflect the size and complexity of the facility and its certificate conditions.

(6) Each holder of a site certificate executed after July 1 of any fiscal year shall pay a fee for the remaining portion of the year. The amount of the fee shall be set at the cost of regulating the facility during the remaining portion of the year determined in the same manner as the annual fee.

(7) When the actual costs of regulation incurred by the council, the State Department of Energy and the Oregon Department of Administrative Services for the year, including that portion of the general regulation costs that have been allocated to a particular facility, are less than the annual fees for that facility, the unexpended balance shall be refunded to the site certificate holder. When the actual regulation costs incurred by the council, the State Department of Energy and the Oregon Department of Administrative Services for the year, including that portion of the general regulation costs that have been allocated to a particular facility, are projected to exceed the annual fee for that facility, the Director of the State Department of Energy may issue an order revising the annual fee.

(8) In addition to any other fees required by law, each energy resource supplier shall pay to the State Department of Energy annually its share of an assessment to fund the activities of the Energy Facility Siting Council, the Oregon Department of Administrative Services and the State Department of Energy, determined by the Director of the State Department of Energy in the following manner:

(a) Upon approval of the budget authorization of the Energy Facility Siting Council, the Oregon Department of Administrative Services and the State Department of Energy by a regular session ofthe Legislative Assembly, the Director of the State Department of Energy shall promptly enter an order establishing the amount of revenues required to be derived from an assessment pursuant to this subsection in order to fund the activities of the Energy Facility Siting Council, the Oregon Department of Administrative Services and the State Department of Energy, including those enumerated in ORS 469.030 and others authorized by law, for the first fiscal year of the forthcoming biennium. On or before June 1 of each even-numbered year, the Director of the State Department of Energy shall enter an order establishing the amount of revenues required to be derived from an assessment pursuant to this subsection in order to fund the activities of the Energy Facility Siting Council, the Oregon Department of Administrative Services and the State Department of Energy, including those enumerated in ORS 469.030 and others authorized by law, for the second fiscal year of the biennium which order shall take into account any revisions to the biennial budget of the Energy Facility Siting Council, the State Department of Energy and the Oregon Department of Administrative Services made by the Emergency Board or by a special session of the Legislative Assembly subsequent to the most recently concluded regular session of the Legislative Assembly. (continued)