CCLME.ORG - DIVISION 7. CALIFORNIA INTEGRATED WASTE MANAGEMENT BOARD
Loading (50 kb)...'
(continued)
(g) This Article does not apply to persons who generate C&D debris or inert debris in the course of carrying out construction, remodeling, repair, demolition or deconstruction of buildings, roads and other structures (collectively, "construction work") at the site of the construction work or to persons who own the land, buildings and other structures that are the object of the construction work, provided that such persons do not accept at the site any C&D debris or inert debris that is generated at any other location, unless it will be used in the construction work, and provided further that such persons do not allow C&D debris or inert debris, other than C&D debris or inert debris that is used in the construction work, to remain on the site of the construction work after the construction work is completed. For example, public works agencies constructing roads and bridges, road repair, airport runway construction, bridge and roadway work, levee work, flood control work, or landslide debris cleanup, and public or private contractors demolishing or constructing buildings are not subject to these regulations during the course of the construction work.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020 and 43021, Public Resources Code.





s 17380.1. Purpose.
(a) It is the board's intent in adopting this Article to encourage the recycling and reuse of C&D debris and inert debris that may otherwise be disposed in a solid waste disposal facility.
(b) These regulations are intended to provide a sufficient level of information and oversight to ensure that the receipt, storage, handling, transfer, and processing of C&D debris and inert debris will be conducted in a manner which meets the purposes of the Act while protecting public health, safety and the environment.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020, and 43021, Public Resources Code.





s 17381. Definitions.
For the purposes of this Article, the following definitions shall apply. Additional definitions and related provisions that apply to this Article are found at California Code of Regulations (CCR), Title 14, Division 7, Chapter 3.0, Article 6.0, sections 17402 and 17402.5, and Article 4, section 17225 et seq.
(a) "Active Compost" as set forth in CCR, Title 14, Division 7, Chapter 3.1, Article 1, section 17852.
(b) "C&D" means Construction and Demolition debris.
(c) "CDI" means any combination of Construction and Demolition debris and Inert debris.
(d) "Compostable Material" means any organic material that when accumulated may become active compost.
(e) "Construction and Demolition Debris", or "C&D Debris" " is solid waste that is a portion of the waste stream defined as "construction and demolition wastes," as defined in Section 17225.15 of Article 4 of this Chapter, and means source separated or separated for reuse solid waste and recyclable materials, including commingled and separated materials, that result from construction work, that are not hazardous, as defined in CCR, Title 22, section 66261.3 et seq., and that contain no more than 1% putrescible wastes by volume calculated on a monthly basis and the putrescible wastes do not constitute a nuisance, as determined by the EA.
(1) C&D debris includes only the following items which meet the above criteria:
(A) components of the building or structure that is the subject of the construction work including, but not limited to, lumber and wood, gypsum wallboard, glass, metal, roofing material, tile, carpeting and floor coverings, window coverings, plastic pipe, concrete, fully cured asphalt, heating, ventilating, and air conditioning systems and their components, lighting fixtures, appliances, equipment, furnishings, and fixtures;
(B) tools and building materials consumed or partially consumed in the course of the construction work including material generated at construction trailers, such as blueprints, plans, and other similar wastes;
(C) cardboard and other packaging materials derived from materials installed in or applied to the building or structure or from tools and equipment used in the course of the construction work; and
(D) plant materials resulting from construction work when commingled with dirt, rock, inert debris or C&D debris.
(2) C&D debris expressly excludes, commingled office recyclables and, except as provided in subdivision 17381 (e) above, commingled commercial solid waste and commingled industrial solid waste as they are defined in Title 27, CCR section 20164.
(3) Notwithstanding anything to the contrary in this Article, C&D debris includes material, whether or not from construction work, that is generally similar to C&D debris and that is separated for reuse, that is not hazardous, that contains no putrescible wastes and that can be processed without generating any residual, provided that the material is generated by an activity that is similar to, or is directly or indirectly related to, construction work, including without limitation: manufacturing materials for use in construction work, such as wood products, clay or ceramic products, plumbing systems, electrical equipment, metal work and HVAC systems.
(f) "Construction and Demolition Wood Mulch" or "C&D Mulch" means source separated wood waste that is not compostable material (C&D mulch feedstock), including that portion of C&D debris that is lumber or wood, which has been mechanically reduced in size. C&D mulch feedstock does not include food material, animal material, biosolids, mixed solid waste, chromated copper arsenate (CCA) pressure treated wood, wood containing lead-based paint, or mixed C&D debris.
(g) "Construction Work" means construction, remodeling, repair, demolition or deconstruction of buildings, other structures, roads, parking lots, and similar paved or covered surfaces.
(h) "Emergency Construction and Demolition/Inert Debris Processing Operation" means a site that is established due to a proclamation of a state of emergency or local emergency as provided in CCR, Title 14, Division 7, Chapter 3.0, Article 3, sections 17210.1(j) and (k),
(i) "Fully Cured Asphalt" means that the material must be at ambient temperature, be substantially hardened and be inelastic.
(j) "Handling" means the receipt, collection, transportation, storage, transfer, or processing of solid waste and recyclable materials.
(k) "Inert Debris" means solid waste and recyclable materials that are source separated or separated for reuse, do not contain hazardous waste (as defined in CCR, Title 22, section 66261.3 et. seq.) or soluble pollutants at concentrations in excess of applicable water quality objectives and do not contain significant quantities of decomposable waste. Inert debris may not contain more than 1% putrescible wastes by volume calculated on a monthly basis and the putrescible wastes shall not constitute a nuisance, as determined by the EA. Gravel, rock, soil, sand and similar materials, whether processed or not, that have never been used in connection with any structure, development, or other human purpose are not inert debris and may be commingled with inert debris.
(1) "Type A inert debris" includes but is not limited to concrete (including fiberglass or steel reinforcing bar embedded in the concrete), fully cured asphalt, glass, fiberglass, asphalt or fiberglass roofing shingles, brick, slag, ceramics, plaster, clay and clay products. Type A inert debris is waste that does not contain soluble pollutants at concentrations in excess of water quality objectives and has not been treated in order to reduce such pollutants. The board, upon consultation with the State Water Resources Control Board, will determine on a case by case basis whether materials not listed in this subdivision qualify as Type A inert debris.
(2) "Type B inert debris" is solid waste that is specifically determined to be inert by the applicable RWQCB, such as treated industrial wastes and de-watered bentonite-based drilling mud, but excluding Type A inert debris.
(l) "Inert Debris Engineered Fill Operation" means a disposal activity exceeding one year in duration in which fully cured asphalt, uncontaminated concrete (including steel reinforcing rods embedded in the concrete), brick, ceramics, clay and clay products, which may be mixed with rock and soil, are spread on land in lifts and compacted under controlled conditions to achieve a uniform and dense mass which is capable of supporting structural loading as necessary, and having other characteristics appropriate for an end use approved by all governmental agencies having jurisdiction (e.g., roads, building sites, or other improvements) where an engineered fill is required to facilitate productive use of the land. The engineered fill shall be constructed and compacted in accordance with all applicable laws and ordinances and shall be certified by a Civil Engineer, Certified Engineering Geologist, or similar professional licensed by the State of California.
(m) "Inert Debris Processing Facility" means a site that receives 1500 tons or more per operating day of any combination of Type A and Type B inert debris, or any amount of Type B inert debris, for storage, handling, transfer, or processing.
(n) "Inert Debris Type A Disposal Facility" means a site where only Type A inert debris is disposed to land. Inert debris Type A disposal facilities do not include inert debris engineered fill operations.
(o) "Inert Debris Type A Processing Operation " means a site that receives less than 1500 tons per operating day of only Type A inert debris for storage, handling, transfer, or processing.
(p) "Large Volume C&D Wood Debris Chipping and Grinding Facility" means a site that receives 500 tons per operating day or more of C&D mulch feedstock for purposes of processing it into C&D mulch.
(q) "Large Volume Construction and Demolition/Inert (CDI) Debris Processing Facility" means a site that receives 175 tons or more of any combination of C&D debris and Type A inert debris per operating day for the purposes of storage, handling, transfer, or processing.
(r) "Material Production Facility" means a facility that primarily handles raw materials to produce a new product that is a rock product operation (i.e., an "aggregate" operation), a hot mix asphalt plant, or a concrete, concrete product or a Portland cement product manufacturing facility.
(s) "Medium Volume C&D Wood Debris Chipping and Grinding Facility" means a site that receives at least 200 tons per operating day and less than 500 tons per operating day of C&D mulch feedstock for purposes of processing it into C&D mulch.
(t) "Medium Volume Construction and Demolition/Inert (CDI) Debris Processing Facility" means a site that receives at least 25 tons per operating day and less than 175 tons per operating day of any combination of C&D debris and Type A inert debris for the purposes of storage, handling, transfer, or processing.
(u) "Physical Contaminants" means human-made inert products contained within feedstocks, including, but not limited to, glass, metal, and plastic.
(v) "Processing" means controlled separation, recovery, volume reduction, or recycling of solid waste including, but not limited to, organized, manual, automated, or mechanical sorting; chipping, grinding, shredding or baling; the use of vehicles for spreading of waste for the purpose of recovery; and the use of conveyor belts, sorting lines or volume reduction equipment.
(w) "Putrescible Wastes" means solid wastes that are capable of being decomposed by micro-organisms with sufficient rapidity as to cause nuisances because of odors, vectors, gases or other offensive conditions, and include materials such as, but not limited to food wastes, offal and dead animals. The EA shall determine on a case-by-case basis whether or not a site is handling putrescible wastes.
(x) "Residual" means the solid waste destined for disposal, further transfer/processing as defined in section 17402(a)(30) or (31) of Article 6.0, or transformation which remains after processing has taken place and is calculated in percent as the weight of residual divided by the total incoming weight of materials. Notwithstanding, for purposes of this Article, "residual" excludes any inert debris that is destined for or disposed in an inert debris engineered fill operation. Further notwithstanding, for purposes of this Article, "further transfer/processing" does not include processing that occurs at a CDI recycling center or an inert debris recycling center, as described in Section 17381.1(a) of this Article, or at a recycling center as defined at Section 17402.5(d) of Article 6.0 of this Chapter.
(y) "Separated for Reuse" means materials, including commingled recyclables, that have been separated or kept separate from the solid waste stream for the purpose of additional sorting or processing those materials for recycling or reuse in order to return them to the economic mainstream in the form of raw material for new, reused, or reconstituted products which meet the quality standards necessary to be used in the marketplace, and includes materials that have been "source separated".
(z) "Site" means the area where the handling of solid waste and/or recyclable materials occurs at a recycling center, CDI debris processing operation or facility, inert debris processing operation or facility, or C&D wood debris chipping and grinding operation or facility.
(aa) "Site Restoration" means removing unprocessed or processed solid waste and recyclable material from the site to allow reuse of the property.
(bb) "Small Volume C&D Wood Debris Chipping and Grinding Operation" means a site that receives less than 200 tons per operating day of C&D mulch feedstock for purposes of processing it into C&D mulch.
(cc) "Small Volume Construction and Demolition/Inert (CDI) Debris Processing Operation" means a site that receives less than 25 tons of any combination of C&D debris and Type A inert debris per operating day for the purposes of storage, handling, transfer, or processing.
(dd) "Source Separated" means materials, including commingled recyclables, that have been separated or kept separate from the solid waste stream, at the point of generation, for the purpose of additional sorting or processing those materials for recycling or reuse in order to return them to the economic mainstream in the form of raw material for new, reused, or reconstituted products which meet the quality standards necessary to be used in the marketplace.
(ee) "Storage" means the holding or stockpiling of processed or unprocessed C&D debris, C&D mulch, inert debris or recyclable materials for a temporary period, at the end of which the material either is recycled or is transferred elsewhere. Storage of C&D debris, C&D mulch, inert debris or recyclable materials for periods exceeding the limits set in this Article is deemed to be disposal and shall be regulated as set forth in the Consolidated Regulations for Treatment, Storage, Processing or Disposal of Solid Waste (commencing at CCR, Title 27, Division 1, Subdivision 1, Chapter 1, Article 1, section 20005).
(ff) "Vector" includes any insect or other arthropod, rodent, or other animal capable of transmitting the causative agents of human disease.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020 and 43021, Public Resources Code.





s 17381.1. Activities That Are Not Subject to the Construction and Demolition/Inert Debris Regulatory Requirements.
(a) A site that receives only construction and demolition debris and inert debris (CDI) and which meets the requirements of this section shall be classified as a CDI recycling center. A site that receives only inert debris and which meets the requirements of this section shall be classified as an inert debris recycling center. CDI recycling centers and inert debris recycling centers shall not be subject to any other requirements of this Article except as specified in this section.
(1) The CDI debris that a CDI recycling center receives shall have been separated at the point of generation.
(A) For the purposes of this section, "separated at the point of generation" means that the material has been separated from the solid waste stream by the generator of that material or by a processor prior to receipt at a CDI recycling center and has not been commingled with other solid waste or recyclable materials. For example, each material type must be transferred in separate containers to the recycling center. Notwithstanding, cardboard, lumber and metal may be commingled in a single container.
(2) An inert debris recycling center shall receive only Type A inert debris that is source separated or separated for reuse. The inert debris may be commingled in a single container.
(b) CDI recycling centers and inert debris recycling centers shall meet the following requirements:
(1) The residual shall be less than 10% by weight of the amount of debris received at the site, calculated on a monthly basis. Recycling center operators may report their residual percentage to the EA and the board on Form CIWMB 607 (see Appendix A).
(2) The amount of putrescible wastes in the CDI debris received at the site shall be less than 1% by volume of the amount of debris received at the site, calculated on a monthly basis, and the putrescible wastes shall not constitute a nuisance, as determined by the EA.
(c) Chipping and grinding of any material, or the receipt of chipped and ground material, is prohibited at CDI recycling centers.
(d) The following storage time limits apply to CDI recycling centers:
(1) CDI debris stored for more than 30 days that has not been processed and sorted for resale or reuse shall be deemed to have been unlawfully disposed and therefore subject to enforcement action, including the use of a Notice and Order as provided in section 18304.
(2) CDI debris that has been processed and sorted for resale or reuse, but remains stored on site for more than one year, shall be deemed to have been unlawfully disposed and therefore subject to enforcement action, including the use of a Notice and Order as provided in section 18304.
(3) Storage time limits do not apply to CDI recycling centers where a financial assurance mechanism pursuant to section 17384(c) has been approved by the board.
(4) At the EA's discretion, storage time limits for sorted and processed materials may be extended to the time specified in a land use entitlement for the site that has an express time limit for the storage of materials.
(5) CDI recycling center storage time limits may be extended for a specified period, if the operator submits to the EA a storage plan as described in section 17384(b) and if the EA finds, on the basis of substantial evidence, that the additional time does not increase the potential harm to public health, safety and the environment. The EA may consult with other public agencies in making this determination. The extended storage term, any applicable conditions the EA imposes and the EA's findings shall be in writing.
(e) The following storage limits apply to inert debris recycling centers:
(1) Inert debris stored for more than 6 months that has not been processed and sorted for resale or reuse shall be deemed to have been unlawfully disposed and therefore subject to enforcement action, including the use of a Notice and Order as provided in section 18304.
(2) Inert debris that has been processed and sorted for resale, or reuse, but remains stored on site for more than 18 months, shall be deemed to have been unlawfully disposed and therefore subject to enforcement action, including the use of a Notice and Order as provided in section 18304.
(3) Storage time limits do not apply to Type A inert debris recycling centers which are located at an inert debris engineered fill operation, an inert debris Type A disposal facility, or at a material production facility.
(4) Storage time limits do not apply to Type A inert debris recycling centers where a financial assurance mechanism pursuant to section 17384(c) has been approved by the board.
(5) At the EA's discretion, storage limits for sorted and processed materials may be extended to the time specified in a land use entitlement for the site that has an express time limit for the storage of materials.
(6) Inert debris recycling center storage limits may be extended for a specified period, if the operator submits to the EA a storage plan as described in section 17384(b) and if the EA finds, on the basis of substantial evidence, that the additional time does not increase the potential harm to public health, safety and the environment. The EA may consult with other public agencies in making this determination. The extended storage term, any applicable conditions the EA imposes and the EA's findings shall be in writing.
(f) Nothing in this section precludes the EA or the board from inspecting a site to verify that it is and has been operating in a manner that meets the requirements of this section, or from taking any appropriate enforcement action, including the use of a Notice and Order as provided in section 18304.
(g) In evaluating whether or not a particular site is in compliance with this section, the EA shall, among other things, do the following:
(1) If the EA has reason to believe that each load of debris received at a recycling center is not separated at the point of generation, is not source separated or is not separated for reuse, as applicable, or that the residual exceeds 10% of the total debris received per month, or that the amount of putrescible wastes exceeds 1% by volume of the total debris received per month, or material is being stored in excess of the applicable storage limits, or that the site is not in compliance with any other requirement in this section, the EA may require the owner or operator to provide evidence that the recycling center is in compliance. The burden of proof shall be on the owner and operator of the recycling center to demonstrate it is in compliance.
(2) At the time that the EA requires a recycling center to provide evidence that it is in compliance with this section, the EA shall provide the owner and operator of the recycling center a written description of the information that has caused the EA to believe that the recycling center is not in compliance. Notwithstanding, the EA shall not be required to identify the name or other identifying information regarding any person(s) who has complained about the recycling center.
(h) Sites which do not meet the applicable requirements of this section do not qualify as recycling centers and shall comply with this Article and all laws and regulations applicable to them. The burden of proof shall be on the owner and operator of a site to demonstrate that the activities at the site are not subject to the requirements of this Article.

Note: Authority cited: Section 40502, 43020 and 43021, Public Resources Code. Reference: 40053, 43020 and 43021, Public Resources Code.





s 17381.2. Regulatory Tiers Placement for CDI Debris and Inert Debris Processing Operations and Facilities.
Construction & Demolition and Inert Debris Tier Placement


Excluded Full Solid
Not Subject To Operations EA Registration Waste Facility
Tier Notification
Article 5.9 Section Tier Tier Permit
17382
____________________________________________________________________________
CDI Recycling Containers Small Volume Medium
used CDI
Centers Section to store debris Volume CDI CDI debris
C&D processing
17381.1 debris at operations debris processing
the (less
place of than 25 tons processing facilities (175 P
per
Alternative generation day - Section facilities (25 tons per day or R
Daily Cover
at solid waste 17383.4 tons per day more) - Sec O
disposal tion
facilities per 15 cubic to up to less 17383 .5 C
27 CCR yards
20680 or less of Small Volume than 175 tons E
separated C&D Wood per day) Inert Debris S
for Debris
Wood waste reuse Chipping and Section Processing S
facilities debris 17383.3
pursuant to PRC Grinding Facility (1500 I
40195.1(b) Specified Operations Medium tons per day or N
(less
chipping than 200 tons Volume C&D more) of any G
and per
Inert Debris grinding day) - Section Wood Debris combination of
Recycling
Centers Section activities 17383.3 Chipping and Type A and A
17381.1
Grinding Type B inert C
See Section Specified Emergency CDI Facilities debris or any T
17402.5 (200
for other Grading processing to <500 tons amount of Type I
Activities
Not
Subject to the Activities operations - per day) - B inert debris V
Regulations Section Section Section I
17383.8
17383.3 17383.7 T
Road building Inert debris I
and Type
specified A only Large Volume E
public works processing
activities operations C&D Wood S
Section (less
17380(g) than 1500 tons Debris Chipping
per day) and Grinding
Section
17383.6 Facilities (500
tons per day or
more) - Section
17383.3

NOTE: THERE ARE NO FACILITIES PLACED WITHIN THE STANDARDIZED TIER




s 17382. Excluded Activities.
(a) The following activities do not constitute CDI debris processing, inert debris processing, or chipping and grinding operations or facilities for the purposes of this Article and are not required to meet the requirements set forth herein:
(1) Containers used to store C&D debris or inert debris at the place of generation.
(2) Locations where 15 cubic yards or less per day of separated for reuse material is handled.
(3) Grading or clearing of land that is consistent with local ordinances.
(4) Chipping and grinding of lumber or other wood material which meet any of the following criteria;
(A) The chipping and grinding activity handles materials derived from and applied to lands owned or leased by the same person, including a parent or subsidiary of a corporate owner; or
(B) Handling any combination of green material, additives, amendments, compost, or chipped and ground material that does not exceed 500cubic yards on-site at any one time; or
(C) The activity is located at the site of biomass conversion as defined in PRC section 40106 and is for use in biomass conversion at that site; or
(D) The activity is part of a silvicultural operation or a wood, paper, or wood product manufacturing operation; or
(E) The storage of bagged chipped and ground material.
(b) Nothing in this section precludes the EA or the board from inspecting an excluded activity to verify that the activity is being conducted in a manner that qualifies as an excluded activity, or from taking any appropriate enforcement action, including the use of a Notice and Order. The burden of proof shall be on the owner and operator to demonstrate that the activities are excluded pursuant to this section.

Note: Authority cited: 40502, 43020 and 43021, Public Resources Code. Reference: 40053, 43020 and 43021, Public Resources Code.





s 17383. State Minimum Standards.
(a) This section sets forth minimum standards that apply to CDI debris processing, inert debris processing and C&D wood debris chipping and grinding operations and facilities.
(b) All small, medium and large CDI debris processing operations and facilities, inert debris processing operations and facilities and small, medium and large C&D wood debris chipping and grinding operations and facilities shall meet the State Minimum Standards requirements of CCR, Title 14, Division 7, Chapter 3.0, Article 6.2 and sections 17406.1, 17406.2 of Article 6.1 and 17414 of Article 6.3.
(c) In addition, medium and large CDI debris processing facilities, inert debris processing facilities and medium and large volume C&D wood debris chipping and grinding facilities shall meet the State Minimum Standards requirements of CCR, Title 14, Division 7, Chapter 3.0, Article 6.35.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020, 43021, 43200 and 43209, Public Resources Code.





s 17383.1. Multiple Wood Debris Chipping and Grinding Activities.
All operations and facilities that receive lumber or wood material and mechanically reduce the material in size are subject to regulation under either Chapter 3 (Minimum Standards for Solid Waste Handling and Disposal) or Chapter 3.1 (Composting Operations Regulatory Requirements) and shall be further regulated as follows: If multiple waste streams, such as C&D wood debris and compostable green material, are handled at one location or site as determined by the EA, the site shall be deemed a single site and shall comply with the permitting requirements of Chapter 3, Article 5.9, Article 6.0 or Chapter 3.1 as determined by the EA. All material handled at the site shall count toward determining the appropriate regulatory tier for the operation or facility. Notwithstanding the above, each separate activity will be required to meet the State Minimum Standards applicable to the specific waste stream being handled.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Section 40053, 43020 and 43021, Public Resources Code.





s 17383.2. Activities at Solid Waste Facilities.
(a) C&D wood debris chipping and grinding operations and facilities and CDI debris and inert debris processing operations and facilities are not required to obtain a separate permit or meet the notification requirements of this Article if the activity is occurring at a facility that has a full solid waste facilities permit and the permit authorizes the activity either through a specific condition in the permit or as a described and approved activity in a Report of Facility Information.
(b) Notwithstanding, C&D wood debris chipping and grinding activities when located at a solid waste facility which has a full solid waste facilities permit shall satisfy the requirements of sections 17383 and 17383.3 (b) through (k) except if material is used on site.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020 and 43021, Public Resources Code.





s 17383.3. C&D Wood Debris Chipping and Grinding Operations and Facilities.
(a) C&D wood debris chipping and grinding operations and facilities conduct chipping and grinding activities to produce C&D mulch. Authorized chipping and grinding activities do not produce active compost, but mechanically reduce the size of lumber and other wood material to produce C&D mulch. The C&D wood debris chipping and grinding operation or facility shall satisfy the appropriate tier requirements. A small volume C&D wood debris chipping and grinding operation shall comply with the EA Notification requirements set forth in CCR, Title 14, Division 7, Chapter 5.0, Article 3.0, commencing at section 18100 et seq. A medium volume C&D wood debris chipping and grinding operation shall comply with the Registration Permit tier requirements set forth in CCR, Title 14, Division 7, Chapter 5.0, Article 3.0, commencing at section 18100 et seq. A large volume C&D wood debris chipping and grinding facility shall comply with the Full Permit tier requirements set forth in CCR, Title 27, Division 2, Subdivision 1, Chapter 4, commencing with section 21563. To the greatest extent possible, all inspections shall be unannounced and shall be conducted at irregular intervals. Except as otherwise specified in this section, small volume C&D wood debris chipping and grinding activities shall comply with all requirements applicable to small volume CDI debris processing operations, medium volume C&D wood debris chipping and grinding facilities shall comply with all requirements applicable to medium volume CDI processing facilities, and large volume C&D wood debris chipping and grinding facilities shall comply with all requirements applicable to large volume CDI debris processing facilities.
(b) All of the following requirements for the storage and stockpiling of C&D mulch feedstock, material being processed and finished C&D mulch apply:
(1) Unprocessed feedstock may be stored on site prior to processing up to 30 days. Unprocessed feedstock stored for more than 30 days shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(2) C&D mulch shall be removed from the site within 90 days from processing. C&D mulch stored for more than 90 days shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(3) If the temperature of the unprocessed feedstock or C&D mulch reaches 50 degrees Celsius (122 degrees Fahrenheit), then the site shall be regulated as a compostable material handling operation or facility, as set forth in Chapter 3.1 commencing with Article 1, section 17850.
(4) The maximum amount of material that may be stored on the site, including unprocessed material, material that is being processed, and material that has been processed, is that amount which is the product of 30 days multiplied by the maximum amount of incoming material permitted per day.
(5) Storage time limits may be extended in accordance with sections 17384 (a) (Land Use Entitlement), 17384 (b) (Storage Plan), and 17384(c) Financial Assurances of this Article.
(c) All the following requirements for the inspection of C&D mulch feedstock apply:
(1) The feedstock shall undergo load checking to ensure that physical contaminants in the feedstock are reduced to no greater than 1% of total feedstock, by weight. Load checking shall include both visual observation of incoming loads of feedstock and load sorting to quantify the percentage of contaminating materials.
(2) A minimum of 1% of daily incoming feedstock volume or at least one truckload per day, whichever is greater, shall be inspected visually. If a visual load check indicates a contamination level is potentially greater than 1%, a representative sample shall be taken, physical contaminants shall be collected and weighed, and the percentage of physical contaminants determined. The load shall be rejected if physical contaminants are greater than 1% of total weight.
(3) Upon request of the EA, the operator shall take a representative sample of feedstock, shall collect and weigh physical contaminants, and shall calculate the percentage of physical contaminants in the sample.
(4) The operator shall take adequate measures through signage, training, load checking, detection systems, and/or chemical analysis to avoid incorporating any chromated copper arsenate (CCA) pressure treated wood and lead based painted materials into C&D mulch. Such contaminated feedstock shall be stored in a designated area for proper handling and disposition.
(5) The operator's employees shall be adequately trained to perform the activities specified in this section.
(d) Operations and facilities producing C&D mulch shall maintain all records demonstrating compliance with this section.
(e) All C&D wood debris chipping and grinding activities shall minimize odor impacts.
(f) The operator shall provide fire prevention, protection and control measures, including, but not limited to, temperature monitoring of windrows and piles, adequate water supply for fire suppression, and the isolation of potential ignition sources from combustible materials. Fire lanes shall be provided to allow fire control equipment access to all operation areas. These requirements are in addition to the requirement for a Fire Prevention, Control and Mitigation Plan described in sections 17386(a)(19), 18223(a)(19) and 18223.5(a)(20),
(g) If C&D debris other than C&D wood debris is accepted at the site, the site shall be regulated as a CDI processing operation or facility under this Article or under in the Transfer/Processing Regulatory requirements (commencing at section 17400), as appropriate.
(h) Should the EA have reason to believe that a C&D wood debris chipping and grinding material handler is engaging in other activities that constitute or are deemed to be disposal, the burden of proof shall be on the owner and operator of the site to demonstrate otherwise.
(i) Each operator of a small volume C&D wood debris chipping and grinding operation shall file with the EA, together with its application for an EA Notification, an Operation Plan (as more fully described in section 17386 of this Article). Each operator of a medium volume C&D wood debris chipping and grinding facility shall file with the EA, together with its application for a Registration Permit, a Facility Plan (as more fully described in Article 3.2, section 18223 of this Chapter). Each operator of a large volume C&D wood debris chipping and grinding facility shall file with the EA, together with its application for a Full Permit, a Facility Report (as more fully described in Article 3.2, section 18223.5 of this Chapter). The information contained in the Plan or Report shall be reviewed by the EA to determine whether it is complete and correct as defined in CCR, Title 14, Chapter 5, Article 3.0, section 18101.
(j) Where the public may have access to them, the debris piles and other piles of materials on site must be stable and otherwise configured so as to protect the public health and safety.
(k) Each operator shall determine the weight of all material received at the operation or facility for handling and shall maintain records of the weight of materials in accord with State Minimum Standards. Weight shall be determined by the use of scales which may be located at the operation or facility or off-site.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020 and 43021, Public Resources Code.





s 17383.4. Small Volume Construction and Demolition/Inert Debris Processing Operations.
All small volume CDI debris processing operations shall comply with the EA Notification requirements set forth in CCR, Title 14, Division 7, Chapter 5.0, Article 3.0, commencing at section 18100. These operations shall be inspected quarterly by the EA to verify compliance with minimum standards. To the greatest extent possible, all inspections shall be unannounced and shall be conducted at irregular intervals. The operator shall specify the operation's boundary area in the operating record.
(a) CDI debris stored for more than 15 days that has not been processed and sorted for resale or reuse shall be deemed to have been unlawfully disposed and therefore subject to enforcement action, including the use of a Notice and Order as provided in section 18304.
(b) CDI debris that has been processed and sorted for resale or reuse, but remains stored on site for more than one year, shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(c) The maximum amount of material that may be stored on the site, including unprocessed material, material that is being processed, and material that has been processed, is that amount which is the product of 30 days multiplied by the maximum amount of incoming material permitted per day.
(d) Storage time limits may be extended in accordance with sections 17384 (a) (Land Use Entitlement), 17384 (b) (Storage Plan), and 17384(c) Financial Assurances of this Article.
(e) Residual material shall be removed from the site within 48 hours or at an alternate frequency approved by the EA.
(f) Each operator of a Small Volume CDI Processing Operation shall file with the EA, together with its application for an EA Notification, a Small Volume CDI Processing Operation Plan (as more fully described in Article 3.2, section 17386 of this Article). The information contained in the Plan shall be reviewed by the EA to determine whether it is complete and correct as defined in CCR, Title 14, Chapter 5, Article 3.0, section 18101.
(g) Where the public may have access to them, the debris piles and other piles of materials on site must be stable and otherwise configured so as to protect the public health and safety.
(h) C&D Mulch that is not compostable material produced at a small volume CDI processing operation must meet all requirements of a small volume C&D wood debris chipping and grinding operation, including the storage limits.
(i) Each operator shall determine the weight of all material received at the operation for handling and shall maintain records of the weight of materials in accord with State Minimum Standards. Weight shall be determined by the use of scales which may be located at the operation or off-site.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020 and 43021, Public Resources Code.





s 17383.5. Medium Volume Construction and Demolition/Inert Debris Processing Facilities.
All medium volume CDI debris processing facilities subject to this Article shall comply with the Registration Permit tier requirements set forth in CCR, Title 14, Division 7, Chapter 5.0, Article 3.0, commencing at section 18100 et seq..
(a) The amount of residual in the C&D debris and type A inert debris shall be less than 40 % of the amount of such material received by weight. The residual amount is calculated on a monthly basis. Facilities which do not meet the 40 % residual requirement of this subsection shall obtain a Full Permit and shall comply with the requirements applicable to a Large Volume CDI Debris Processing Facility. If the EA determines that a Medium Volume CDI Debris Processing Facility has exhibited a pattern and practice of failing to comply with the provisions of this subsection, the EA shall take appropriate enforcement action.
(b) CDI debris stored for more than 15 days that has not been processed and sorted for resale or reuse shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(c) CDI debris that has been processed and sorted for resale or reuse, but remains stored on site for more than one year, shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(d) The maximum amount of material that may be stored on the site, including unprocessed material, material that is being processed, and material that has been processed, is that amount which is the product of 30 days multiplied by the maximum amount of incoming material permitted per day.
(e) Storage time limits may be extended in accordance with sections 17384 (a) (Land Use Entitlement), 17384 (b) (Storage Plan), and 17384(c) Financial Assurances of this Article.
(f) Residual material shall be removed from the site within 48 hours or at an alternate frequency approved by the EA.
(g) Each operator of a medium volume CDI processing facility shall file with the EA, together with its application for a Registration Permit, a CDI Processing Facility Plan (as more fully described in Article 3.2, section 18223 of this Chapter). The information contained in the Plan shall be reviewed by the EA to determine whether it is complete and correct as defined in CCR, Title 14, Chapter 5, Article 3.0, section 18101.
(h) Medium volume CDI debris processing facilities shall be inspected monthly by the EA in accordance with PRC section 43218. To the greatest extent possible, all inspections shall be unannounced and shall be conducted at irregular intervals.
(i) Where the public may have access to them, the debris piles and other piles of materials on site must be stable and otherwise configured so as to protect the public health and safety.
(j) C&D Mulch that is not compostable material produced at a medium volume CDI processing operation must meet all requirements of a medium volume chipping and grinding operation, including the storage limits.
(k) If a medium volume CDI processing facility exceeds any combination of the following limitations, which are more fully described in this Section 17383.5, three (3) or more times within any two (2) year period which the EA determines constitutes a violation of this Article, the facility no longer qualifies for a Registration Permit under this section. Upon the third such violation, the EA shall notify the operator in writing that the facility no longer qualifies for a Registration Permit, and the operator must within 30 days apply for a Full Permit as if it were a large volume CDI processing facility pursuant to Section 17383.6. In addition, the EA shall issue a cease and desist order pursuant to Section 18304 directing, among other things, that the operator immediately cease accepting material at the site until the operator has demonstrated to the EA that it has corrected the violation and eliminated the cause of the violation. The limitations to which this subdivision applies are:
1. Maximum amount of residual specified in Subsection 17383.5(a).
2. Maximum tonnage received per day as specified in Subsection 17381(t)
3. Maximum amount of material on site as specified 17383.5(d).
(l) Each operator shall determine the weight of all material received at the facility for handling and shall maintain records of the weight of materials in accord with State Minimum Standards. Weight shall be determined by the use of scales which may be located at the facility or off-site.

Note: Authority cited: Sections 40502, 43020 and 43021, Public Resources Code. Reference: Sections 40053, 43020 and 43021, Public Resources Code.





s 17383.6. Large Volume Construction and Demolition/Inert Debris Processing Facilities.
All large volume CDI debris processing facilities subject to this Article shall comply with the Full Permit tier requirements set forth in Title 27, CCR, Division 2, Subdivision 1, Chapter 4, commencing with section 21450.
(a) CDI debris stored for more than 15 days that has not been processed and sorted for resale or reuse shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(b) CDI debris that has been processed and sorted for resale, or reuse, but remains stored on site for more than one year, shall be deemed to have been unlawfully disposed, and therefore subject to enforcement action including the use of a Notice and Order as provided in section 18304.
(c) The maximum amount of material that may be stored on the site, including unprocessed material, material that is being processed, and material that has been processed, is that amount which is the product of 30 days multiplied by the maximum amount of incoming material permitted per day.
(d) Storage time limits may be extended in accordance with sections 17384 (a) (Land Use Entitlement), 17384 (b) (Storage Plan), and 17384(c) Financial Assurances of this Article.
(e) Residual material shall be removed from the site within 48 hours or at an alternate frequency approved by the EA.
(f) Each operator of a large volume CDI processing facility shall file with the EA, together with its application for a Full Permit, a Large Volume CDI Processing Facility Report (as more fully described in Article 3.2, section 18223.5 of this Chapter). The information contained in the Report shall be reviewed by the EA to determine whether it is complete and correct as defined in CCR, Title 14, Chapter 5, Article 3.0, section 18101.
(g) Large volume CDI debris processing facilities shall be inspected monthly by the EA in accordance with PRC section 43218. To the greatest extent possible, all inspections shall be unannounced and shall be conducted at irregular intervals.
(h) Where the public may have access to them, the debris piles and other piles of materials on site must be stable and otherwise configured so as to protect the public health and safety.
(i) C&D Mulch that is not compostable material produced at a large volume CDI processing operation must meet all requirements of a large volume C&D wood debris chipping and grinding operation, including the storage limits.
(j) Each operator shall determine the weight of all material received at the facility for handling and shall maintain records of the weight of materials in accord with State Minimum Standards. Weight shall be determined by the use of scales which may be located at the facility or off-site. (continued)