Loading (50 kb)...'
(continued)
to any State Regulatory Agency to
which or through which the waste
described above will be
transported for disposal at least
60 days prior to the commencement
of such activities. Failure to
provide such a notification will
result in a violation of the
delisting petition and a possible
revocation of the decision.
American Steel Scottsburg, IN... Wastewater treatment plant (WWTP)
Cord. sludge from electroplating
operations (EPA Hazardous Waste
No. F006) generated at a maximum
annual rate of 3,000 cubic yards
per year, after January 26, 1999,
and disposed of in a Subtitle D
landfill.
1. Verification Testing: American
Steel Cord must implement an
annual testing program to
demonstrate, based on the
analysis of a minimum of four
representative samples, that the
constituent concentrations
measured in the TCLP extract of
the waste are within specific
levels. The constituent
concentrations must not exceed
the following levels (mg/l) which
are back-calculated from the
delisting health-based levels and
a DAF of 68. Arsenic_3.4;
Barium_100; Cadmium_.34;
Chromium_5; Copper_88.4.;
Lead_1.02; Mercury_.136;
Nickel_6.8.; Selenium_1;
Silver_5; Zinc_680; Cyanide_13.6;
Acetone_272; Benzo butyl
phthlate_476; Chloroform_.68; 1,4-
Dichlorobenzene_.272; cis-1,2-
Dichloroethene_27.2; Methylene
chloride_.34; Naphthalene_68;
Styrene_6.8;
Tetrachloroethene_.34;
Toluene_68; and Xylene_680.
American Steel Cord must measure
and record the pH of the waste
using SW 846 method 9045 and must
record all pH measurements
performed in accordance with the
TCLP.
2. Changes in Operating
Conditions: If American Steel
Cord significantly changes the
manufacturing or treatment
process or the chemicals used in
the manufacturing or treatment
process, American Steel Cord may
handle the WWTP filter press
sludge generated from the new
process under this exclusion only
after the facility has
demonstrated that the waste meets
the levels set forth in paragraph
1 and that no new hazardous
constituents listed in Appendix
VIII of Part 261 have been
introduced.
3. Data Submittals: The data
obtained through annual
verification testing or
compliance with paragraph 2 must
be submitted to U.S. EPA Region
5, 77 W. Jackson Blvd., Chicago,
IL 60604-3590, within 60 days of
sampling. Records of operating
conditions and analytical data
must be compiled, summarized, and
maintained on site for a minimum
of five years and must be made
available for inspection. All
data must be accompanied by a
signed copy of the certification
statement in 260.22(I)(12).
4. (a) If, anytime after disposal
of the delisted waste, American
Steel Cord possesses or is
otherwise made aware of any
environmental data (including but
not limited to leachate data or
groundwater monitoring data) or
any other data relevant to the
delisted waste indicating that
any constituent identified in
Condition (1) is at a level in
the leachate higher than the
delisting level established in
Condition (1), or is at a level
in the ground water or soil
higher than the health based
level, then American Steel Cord
must report such data, in
writing, to the Regional
Administrator within 10 days of
first possessing or being made
aware of that data.
(b) Based on the information
described in paragraph (a) and
any other information received
from any source, the Regional
Administrator will make a
preliminary determination as to
whether the reported information
requires Agency action to protect
human health or the environment.
Further action may include
suspending, or revoking the
exclusion, or other appropriate
response necessary to protect
human health and the environment.
(c) If the Regional Administrator
determines that the reported
information does require Agency
action, the Regional
Administrator will notify the
facility in writing of the
actions the Regional
Administrator believes are
necessary to protect human health
and the environment. The notice
shall include a statement of the
proposed action and a statement
providing the facility with an
opportunity to present
information as to why the
proposed Agency action is not
necessary or to suggest an
alternative action. The facility
shall have 10 days from the date
of the Regional Administrator's
notice to present such
information.
(d) Following the receipt of
information from the facility
described in paragraph (c) or (if
no information is presented under
paragraph (c) the initial receipt
of information described in
paragraph (a), the Regional
Administrator will issue a final
written determination describing
the Agency actions that are
necessary to protect human health
or the environment. Any required
action described in the Regional
Administrator's determination
shall become effective
immediately, unless the Regional
Administrator provides otherwise.
Ampex Recording Opelika, Alabama. Solvent recovery residues in the
Media powder or pellet form (EPA
Corporation. Hazardous Waste Nos. F003 and
F005) generated from the recovery
of spent solvents from the
manufacture of tape recording
media (generated at a maximum
annual rate of 1,000 cubic yards
in the powder or pellet form)
after August 9, 1993. In order to
confirm that the characteristics
of the wastes do not change
significantly, the facility must,
on an annual basis, analyze a
representative composite sample
of the waste (in its final form)
for the constituents listed in 40
CFR 261.24 using the method
specified therein. The annual
analytical results, including
quality control information, must
be compiled, certified according
to 40 CFR 260.22(i)(12),
maintained on-site for a minimum
of five years, and made available
for inspection upon request by
any employee or representative of
EPA or the State of Alabama.
Failure to maintain the required
records on-site will be
considered by EPA, at its
discretion, sufficient basis to
revoke the exclusion to the
extent directed by EPA.
Aptus, Inc....... Coffeyville, Kiln residue and spray dryer/
Kansas. baghouse residue (EPA Hazardous
Waste No. F027) generated during
the treatment of cancelled
pesticides containing 2,4,5-T and
Silvex and related materials by
Aptus' incinerator at
Coffeyville, Kansas after
December 27, 1991, so long as:
(1) The incinerator is monitored
continuously and is in compliance
with operating permit conditions.
Should the incinerator fail to
comply with the permit conditions
relevant to the mechanical
operation of the incinerator,
Aptus must test the residues
generated during the run when the
failure occurred according to the
requirements of Conditions (2)
through (4), regardless of
whether or not the demonstration
in Condition (5) has been made.
(2) A minimum of four grab samples
must be taken from each hopper
(or other container) of kiln
residue generated during each 24-
hour run; all grabs collected
during a given 24-hour run must
then be composited to form one
composite sample. A minimum of
four grab samples must also be
taken from each hopper (or other
container) of spray dryer/
baghouse residue generated during
each 24-hour run; all grabs
collected during a given 24-hour
run must then be composited to
form one composite sample. Prior
to the disposal of the residues
from each 24-hour run, a TCLP
leachate test must be performed
on these composite samples and
the leachate analyzed for the TC
toxic metals, nickel, and
cyanide. If arsenic, chromium,
lead or silver TC leachate test
results exceed 1.6 ppm, barium
levels exceed 32 ppm, cadmium or
selenium levels exceed 0.3 ppm,
mercury levels exceed 0.07 ppm,
nickel levels exceed 10 ppm, or
cyanide levels exceed 6.5 ppm,
the wastes must be retreated to
achieve these levels or must be
disposed in accordance with
subtitle C of RCRA. Analyses must
be performed according to
appropriate methods. As
applicable to the method-defined
parameters of concern, analyses
requiring use of SW-846 methods
incorporated by reference in 40
CFR 260.11 must be used without
substitution. As applicable, the
SW-846 methods might include
Methods 0010, 0011, 0020, 0023A,
0030, 0031, 0040, 0050, 0051,
0060, 0061, 1010A, 1020B, 1110A,
1310B, 1311, 1312, 1320, 1330A,
9010C, 9012B, 9040C, 9045D,
9060A, 9070A (uses EPA Method
1664, Rev. A), 9071B, and 9095B.
(3) Aptus must generate, prior to
the disposal of the residues,
verification data from each 24
hour run for each treatment
residue (i.e., kiln residue,
spray dryer/baghouse residue) to
demonstrate that the maximum
allowable treatment residue
concentrations listed below are
not exceeded. Samples must be
collected as specified in
Condition (2). Analyses must be
performed according to
appropriate methods. As
applicable to the method-defined
parameters of concern, analyses
requiring the use of SW-846
methods incorporated by reference
in 40 CFR 260.11 must be used
without substitution. As
applicable, the SW-846 methods
might include Methods 0010, 0011,
0020, 0023A, 0030, 0031, 0040,
0050, 0051, 0060, 0061, 1010A,
1020B, 1110A, 1310B, 1311, 1312,
1320, 1330A, 9010C, 9012B, 9040C,
9045D, 9060A, 9070A (uses EPA
Method 1664, Rev. A), 9071B, and
9095B. Any residues which exceed
any of the levels listed below
must be retreated or must be
disposed of as hazardous. Kiln
residue and spray dryer/baghouse
residue must not exceed the
following levels:
Aldrin_0.015 ppm, Benzene_9.7 ppm,
Benzo(a)pyrene_0.43 ppm,
Benzo(b)fluoranthene)_1.8 ppm,
Chlordane_0.37 ppm,
Chloroform_5.4 ppm, Chrysene_170
ppm, Dibenz(a,h)anthracene_0.083
ppm, 1.2-Dichloroethane_4.1 ppm,
Dichloromethane_2.4 ppm, 2,4-
Dichlorophenol_480 ppm,
Dichlorvos_260 ppm, Disulfaton_23
ppm, Endosulfan I_310 ppm,
Fluorene_120 ppm,
Indeno(1,2,3,cd)-pyrene_330 ppm,
Methyl parathion_210 ppm,
Nitrosodiphenylamine_130 ppm,
Phenanthrene_150 ppm,
Polychlorinated biphenyls_0.31
ppm, Tetrachlorethylene_59 ppm,
2,4,5-TP (silvex)_110 ppm, 2,4,6-
Trichlorophenol_3.9 ppm.
(4) Aptus must generate, prior to
disposal of residues,
verification data from each 24-
hour run for each treatment
residue (i.e., kiln residue,
spray dryer/baghouse residue) to
demonstrate that the residues do
not contain tetra-, penta-, or
hexachlorodibenzo-p-dioxins or
furans at levels of regulatory
concern. Samples must be
collected as specified in
Condition (2). The TCDD
equivalent levels for the solid
residues must be less than 5 ppt.
Any residues with detected
dioxins or furans in excess of
this level must be retreated or
must be disposed of as acutely
hazardous. For tetra- and penta-
chlorinated dioxin and furan
homologs, the maximum practical
quantitation limit must not
exceed 15 ppt for the solid
residues. For hexachlorinated
dioxin and furan homologs, the
maximum practical quantitation
limit must not exceed 37 ppt for
the solid residues.
(5) The test data from Conditions
(1), (2), (3), and (4) must be
kept on file by Aptus for
inspection purposes and must be
compiled, summarized, and
submitted to the Director for the
Characterization and Assessment
Division, Office of Solid Waste,
by certified mail on a monthly
basis and when the treatment of
the cancelled pesticides and
related materials is concluded.
The testing requirements for
Conditions (2), (3), and (4) will
continue until Aptus provides the
Director with the results of four
consecutive batch analyses for
the petitioned wastes, none of
which exceed the maximum
allowable levels listed in these
conditions and the director
notifies Aptus that the
conditions have been lifted. All
data submitted will be placed in
the RCRA public docket.
(6) Aptus must provide a signed
copy of the following
certification statement when
submitting data in response to
the conditions listed above:
``Under civil and criminal
penalty of law for the making or
submission of false or fraudulent
statements or representations, I
certify that the information
contained in or accompanying this
document is true, accurate, and
complete. As to the (those)
identified section(s) of this
document for which I cannot
personally verify its (their)
truth and accuracy, I certify as
the company official having
supervisory responsibility for
the persons who, acting under my
direct instructions, made the
verification that this
information is true, accurate,
and complete.''
Arco Building Sugarcreek, Ohio. Dewatered wastewater treatment
Products. sludge (EPA Hazardous Waste No.
F019) generated from the chemical
conversion coating of aluminum
after August 15, 1986.
Arco Chemical Co. Miami, FL........ Dewatered wastewater treatment
sludge (EPA Hazardous Waste No.
FO19) generated from the chemical
conversion coating of aluminum
after April 29, 1986.
Arkansas Vertac Superfund Kiln ash, cyclone ash, and calcium
Department of site, chloride salts from incineration
Pollution Jacksonville, of residues (EPA Hazardous Waste
Control and Arkansas. No. F020 and F023) generated from
Ecology. the primary production of 2,4,5-T
and 2,4-D after August 24, 1990.
This one-time exclusion applies
only to the incineration of the
waste materials described in the
petition, and it is conditional
upon the data obtained from
ADPC&E's full-scale
incineration facility. To ensure
that hazardous constituents are
not present in the waste at
levels of regulatory concern once
the full-scale treatment facility
is in operation, ADPC&E must
implement a testing program for
the petitioned waste. This
testing program must meet the
following conditions for the
exclusion to be valid:
(1) Testing: Sample collection
and analyses (including
quality control (QC)
procedures) must be performed
according to appropriate
methods. As applicable to the
method-defined parameters of
concern, analyses requiring
the use of SW-846 methods
incorporated by reference in
40 CFR 260.11 must be used
without substitution. As
applicable, the SW-846 methods
might include Methods 0010,
0011, 0020, 0023A, 0030, 0031,
0040, 0050, 0051, 0060, 0061,
1010A, 1020B, 1110A, 1310B,
1311, 1312, 1320, 1330A,
9010C, 9012B, 9040C, 9045D,
9060A, 9070A (uses EPA Method
1664, Rev. A), 9071B, and
9095B.
(A) Initial testing:
Representative grab samples
must be taken from each drum
and kiln ash and cyclone ash
generated from each 24 hours
of operation, and the grab
samples composited to form
one composite sample of ash
for each 24-hour period.
Representative grab samples
must also be taken from each
drum of calcium chloride
salts generated from each 24
hours of operation and
composited to form one
composite sample of calcium
chloride salts for each 24-
hour period. The initial
testing requirements must be
fullfilled for the following
wastes: (i) Incineration by-
products generated prior to
and during the incinerator's
trial burn; (ii)
incineration by-products
from the treatment of 2,4-D
wastes for one week (or 7
days if incineration is not
on consecutive days) after
completion of the trial
burn; (iii) incineration by-
products from the treatment
of blended 2,4-D and 2,4, 5-
T wastes for two weeks (or
14 days if incineration is
not on consecutive days)
after completion of the
trial burn; and (iv)
incineration by-products
from the treatment of
blended 2,4-D and 2,4,5-T
wastes for one week (or 7
days if incineration is not
on consecutive days) when
the percentage of 2, 4, 5-T
wastes exceeds the maximum
percentage treated under
Condition (1)(A)(iii). Prior
to disposal of the residues
from each 24-hour sampling
period, the daily composite
must be analyzed for all the
constituents listed in
Condition (3). ADPC&E
must report the analytical
test data, including quality
control information,
obtained during this initial
period no later than 90 days
after the start of the
operation.
(B) Subsequent testing:
Representative grab samples
of each drum of kiln and
cyclone ash generated from
each week of operation must
be composited to form one
composite sample of ash for
each weekly period.
Representative grab samples
of each drum of calcium
chloride salts generated
from each week of operation
must also be composited to
form one composite sample of
calcium chloride salts for
each weekly period.
Prior to disposal of the
residues from each weekly
sampling period, the weekly
composites must be analyzed
for all of the constituents
listed in Condition (3). The
analytical data, including
quality control information,
must be compiled and
maintained on site for a
minimum of three years.
These data must be furnished
upon request and made
available for inspection by
any employee or
representative of EPA.
(2) Waste holding: The
incineration residues that are
generated must be stored as
hazardous until the initial
verification analyses or
subsequent analyses are
completed.
If the composite incineration
residue samples (from either
Condition (1)(A) or Condition
(1)(B)) do not exceed any of
the delisting levels set in
Condition (3), the
incineration residues
corresponding to these samples
may be managed and disposed of
in accordance with all
applicable solid waste
regulations.
If any composite incineration
residue sample exceeds any of
the delisting levels set in
Condition (3), the
incineration residues
generated during the time
period corresponding to this
sample must be retreated until
they meet these levels
(analyses must be repeated) or
managed and disposed of in
accordance with subtitle C of
RCRA. Incineration residues
which are generated but for
which analysis is not complete
or valid must be managed and
disposed of in accordance with
subtitle C of RCRA, until
valid analyses demonstrate
that the wastes meet the
delisting levels.
(3) Delisting levels: If
concentrations in one or more
of the incineration residues
for any of the hazardous
constituents listed below
exceed their respective
maximum allowable
concentrations also listed
below, the batch of failing
waste must either be re-
treated until it meets these
levels or managed and disposed
of in accordance with subtitle
C of RCRA.
(A) Inorganics (Leachable):
Arsenic, 0.32 ppm; Barium,
6.3 ppm; Cadmium, 0.06 ppm;
Chromium, 0.32 ppm; Cyanide,
4.4 ppm; Lead, 0.32 ppm;
Mercury, 0.01 ppm; Nickel,
4.4 ppm; Selenium, 0.06 ppm;
Silver, 0.32 ppm. Metal
concentrations must be
measured in the waste
leachate as per 40 CFR
261.24. Cyanide extractions
must be conducted using
distilled water.
(B) Organics: Benzene, 0.87
ppm; Benzo(a)anthracene,
0.10 ppm; Benzo(a)pyrene,
0.04 ppm; Benzo
(b)fluoranthene, 0.16 ppm;
Chlorobenzene, 152 ppm; o-
Chlorophenol, 44 ppm;
Chrysene, 15 ppm; 2, 4-D,
107 ppm; DDE, 1.0 ppm;
Dibenz(a,h)anthracene, 0.007
ppm; 1, 4-Dichlorobenzene,
265 ppm; 1, 1-
Dichloroethylene, 1.3 ppm;
trans-1,2-Dichloroethylene,
37 ppm; Dichloromethane,
0.23 ppm; 2,4-
Dichlorophenol, 43 ppm;
Hexachlorobenzene, 0.26 ppm;
Indeno (1,2,3-cd) pyrene, 30
ppm; Polychlorinated
biphenyls, 12 ppm; 2,4,5-T,
1 x 10 \6\ ppm; 1,2,4,5-
Tetrachlorobenzene, 56 ppm;
Tetrachloroethylene, 3.4
ppm; Trichloroethylene, 1.1
ppm; 2,4,5-Trichlorophenol,
21,000 ppm; 2,4,6-
Trichlorophenol, 0.35 ppm.
(C) Chlorinated dioxins and
furans: 2,3,7,8-
Tetrachlorodibenzo-p-dioxin
equivalents, 4 x 10-7 ppm.
The petitioned by-product
must be analyzed for the
tetra-, penta-, hexa-, and
heptachlorodibenzo-p-
dioxins, and the tetra-,
penta-, hexa-, and
heptachlorodibenzofurans to
determine the 2, 3, 7, 8-
tetra-chlorodibenzo-p-dioxin
equivalent concentration.
The analysis must be
conducted using a
measurement system that
achieves practical
quantitation limits of 15
parts per trillion (ppt) for
the tetra- and penta-
homologs, and 37 ppt for the
hexa- and hepta-homologs.
(4) Termination of testing: Due
to the possible variability of
the incinerator feeds, the
testing requirements of
Condition (1)(B) will continue
indefinitely.
(5) Data submittals: Within one
week of system start-up,
ADPC&E must notify the
Section Chief, Variances
Section (see address below)
when the full-scale
incineration system is on-line
and waste treatment has begun.
The data obtained through
Condition (1)(A) must be
submitted to PSPD/OSW (5303W),
U.S. EPA, 1200 Pennsylvania
Ave., NW., Washington, DC
20460, within the time period
specified. At the Section
Chief's request, ADPC&E
must submit analytical data
obtained through Condition
(1)(B) within the time period
specified by the Section
Chief. Failure to submit the
required data obtained from
Condition (1)(A) within the
specified time period or to
maintain the required records
for the time specified in
Condition (1)(B) (or to submit
data within the time specified
by the Section Chief) will be
considered by the Agency, at
its discretion, sufficient
basis to revoke ADPC&E's
exclusion to the extent
directed by EPA. All data must
be accompanied by the
following certification
statement:
``Under civil and criminal
penalty of law for the making
or submission of false or
fraudulent statements or
representations (pursuant to
the applicable provisions of
the Federal Code, which
include, but may not be
limited to, 18 U.S.C. 1001 and
42 U.S.C. 6928), I certify
that the information contained
in or accompanying this
document is true, accurate and
complete. As to the (those) (continued)