Loading (50 kb)...'
(continued) sufficient to assess the impact of the discharge on water, sediment, and biological quality including, where appropriate, analysis of the bioaccumulative and/or persistent impact on aquatic life of the discharge;
(3) Contain any other conditions, such as performance of liquid or suspended particulate phase bioaccumulation tests, seasonal restrictions on discharge, process modifications, dispersion of pollutants, or schedule of compliance for existing discharges, which are determined to be necessary because of local environmental conditions, and
(4) Contain the following clause: In addition to any other grounds specified herein, this permit shall be modified or revoked at any time if, on the basis of any new data, the director determines that continued discharges may cause unreasonable degradation of the marine environment.
§ 125.124 Information required to be submitted by applicant.
top
The applicant is responsible for providing information which the director may request to make the determination required by this subpart. The director may require the following information as well as any other pertinent information:
(a) An analysis of the chemical constituents of any discharge;
(b) Appropriate bioassays necessary to determine the limiting permissible concentrations for the discharge;
(c) An analysis of initial dilution;
(d) Available process modifications which will reduce the quantities of pollutants which will be discharged;
(e) Analysis of the location where pollutants are sought to be discharged, including the biological community and the physical description of the discharge facility;
(f) Evaluation of available alternatives to the discharge of the pollutants including an evaluation of the possibility of land-based disposal or disposal in an approved ocean dumping site.