Loading (50 kb)...'
(continued) toration Planning Phase. Otherwise, trustees may not take additional action under this part. However, trustees may recover all reasonable assessment costs incurred up to this point.
(2) Trustees must consider a reasonable range of restoration alternatives before selecting their preferred alternative(s). Each restoration alternative is comprised of primary and/or compensatory restoration components that address one or more specific injury(ies) associated with the incident. Each alternative must be designed so that, as a package of one or more actions, the alternative would make the environment and public whole. Only those alternatives considered technically feasible and in accordance with applicable laws, regulations, or permits may be considered further under this part.
(b) Primary restoration—(1) General. For each alternative, trustees must consider primary restoration actions, including a natural recovery alternative.
(2) Natural recovery. Trustees must consider a natural recovery alternative in which no human intervention would be taken to directly restore injured natural resources and services to baseline.
(3) Active primary restoration actions. Trustees must consider an alternative comprised of actions to directly restore the natural resources and services to baseline on an accelerated time frame. When identifying such active primary restoration actions, trustees may consider actions that:
(i) Address conditions that would prevent or limit the effectiveness of any restoration action;
(ii) May be necessary to return the physical, chemical, and/or biological conditions necessary to allow recovery or restoration of the injured natural resources (e.g., replacing substrate or vegetation, or modifying hydrologic conditions); or
(iii) Return key natural resources and services, and would be an effective approach to achieving or accelerating a return to baseline (e.g., replacing essential species, habitats, or public services that would facilitate the replacement of other, dependent natural resource or service components).
(c) Compensatory restoration—(1) General. For each alternative, trustees must also consider compensatory restoration actions to compensate for the interim loss of natural resources and services pending recovery.
(2) Compensatory restoration actions. To the extent practicable, when evaluating compensatory restoration actions, trustees must consider compensatory restoration actions that provide services of the same type and quality, and of comparable value as those injured. If, in the judgment of the trustees, compensatory actions of the same type and quality and comparable value cannot provide a reasonable range of alternatives, trustees should identify actions that provide natural resources and services of comparable type and quality as those provided by the injured natural resources. Where the injured and replacement natural resources and services are not of comparable value, the scaling process will involve valuation of lost and replacement services.
(d) Scaling restoration actions—(1) General. After trustees have identified the types of restoration actions that will be considered, they must determine the scale of those actions that will make the environment and public whole. For primary restoration actions, scaling generally applies to actions involving replacement and/or acquisition of equivalent of natural resources and/or services.
(2) Resource-to-resource and service-to-service scaling approaches. When determining the scale of restoration actions that provide natural resources and/or services of the same type and quality, and of comparable value as those lost, trustees must consider the use of a resource-to-resource or service-to-service scaling approach. Under this approach, trustees determine the scale of restoration actions that will provide natural resources and/or services equal in quantity to those lost.
(3) Valuation scaling approach. (i) Where trustees have determined that neither resource-to-resource nor service-to-service scaling is appropriate, trustees may use the valuation scaling approach. Under the valuation scaling approach, trustees determine the amount of natural resources and/or services that must be provided to produce the same value lost to the public. Trustees must explicitly measure the value of injured natural resources and/or services, and then determine the scale of the restoration action necessary to produce natural resources and/or services of equivalent value to the public.
(ii) If, in the judgment of the trustees, valuation of the lost services is practicable, but valuation of the replacement natural resources and/or services cannot be performed within a reasonable time frame or at a reasonable cost, as determined by §990.27(a)(2) of this part, trustees may estimate the dollar value of the lost services and select the scale of the restoration action that has a cost equivalent to the lost value. The responsible parties may request that trustees value the natural resources and services provided by the restoration action following the process described in §990.14(c) of this part.
(4) Discounting and uncertainty. When scaling a restoration action, trustees must evaluate the uncertainties associated with the projected consequences of the restoration action, and must discount all service quantities and/or values to the date the demand is presented to the responsible parties. Where feasible, trustees should use risk-adjusted measures of losses due to injury and of gains from the restoration action, in conjunction with a riskless discount rate representing the consumer rate of time preference. If the streams of losses and gains cannot be adequately adjusted for risks, then trustees may use a discount rate that incorporates a suitable risk adjustment to the riskless rate.
[61 FR 500, Jan. 5, 1996, as amended at 67 FR 61493, Oct. 1, 2002]
§ 990.54 Restoration selection—evaluation of alternatives.
top
(a) Evaluation standards. Once trustees have developed a reasonable range of restoration alternatives under §990.53 of this part, they must evaluate the proposed alternatives based on, at a minimum:
(1) The cost to carry out the alternative;
(2) The extent to which each alternative is expected to meet the trustees' goals and objectives in returning the injured natural resources and services to baseline and/or compensating for interim losses;
(3) The likelihood of success of each alternative;
(4) The extent to which each alternative will prevent future injury as a result of the incident, and avoid collateral injury as a result of implementing the alternative;
(5) The extent to which each alternative benefits more than one natural resource and/or service; and
(6) The effect of each alternative on public health and safety.
(b) Preferred restoration alternatives. Based on an evaluation of the factors under paragraph (a) of this section, trustees must select a preferred restoration alternative(s). If the trustees conclude that two or more alternatives are equally preferable based on these factors, the trustees must select the most cost-effective alternative.
(c) Pilot projects. Where additional information is needed to identify and evaluate the feasibility and likelihood of success of restoration alternatives, trustees may implement restoration pilot projects. Pilot projects should only be undertaken when, in the judgment of the trustees, these projects are likely to provide the information, described in paragraph (a) of this section, at a reasonable cost and in a reasonable time frame.
§ 990.55 Restoration selection—developing restoration plans.
top
(a) General. OPA requires that damages be based upon a plan developed with opportunity for public review and comment. To meet this requirement, trustees must, at a minimum, develop a Draft and Final Restoration Plan, with an opportunity for public review of and comment on the draft plan.
(b) Draft Restoration Plan. (1) The Draft Restoration Plan should include:
(i) A summary of injury assessment procedures used;
(ii) A description of the nature, degree, and spatial and temporal extent of injuries resulting from the incident;
(iii) The goals and objectives of restoration;
(iv) The range of restoration alternatives considered, and a discussion of how such alternatives were developed under §990.53 of this part, and evaluated under §990.54 of this part;
(v) Identification of the trustees' tentative preferred alternative(s);
(vi) A description of past and proposed involvement of the responsible parties in the assessment; and
(vii) A description of monitoring for documenting restoration effectiveness, including performance criteria that will be used to determine the success of restoration or need for interim corrective action.
(2) When developing the Draft Restoration Plan, trustees must establish restoration objectives that are specific to the injuries. These objectives should clearly specify the desired outcome, and the performance criteria by which successful restoration will be judged. Performance criteria may include structural, functional, temporal, and/or other demonstrable factors. Trustees must, at a minimum, determine what criteria will:
(i) Constitute success, such that responsible parties are relieved of responsibility for further restoration actions; or
(ii) Necessitate corrective actions in order to comply with the terms of a restoration plan or settlement agreement.
(3) The monitoring component to the Draft Restoration Plan should address such factors as duration and frequency of monitoring needed to gauge progress and success, level of sampling needed to detect success or the need for corrective action, and whether monitoring of a reference or control site is needed to determine progress and success. Reasonable monitoring and oversight costs cover those activities necessary to gauge the progress, performance, and success of the restoration actions developed under the plan.
(c) Public review and comment. The nature of public review and comment on the Draft and Final Restoration Plans will depend on the nature of the incident and any applicable federal trustee NEPA requirements, as described in §§990.14(d) and 990.23 of this part.
(d) Final Restoration Plan. Trustees must develop a Final Restoration Plan that includes the information specified in paragraph (a) of this section, responses to public comments, if applicable, and an indication of any changes made to the Draft Restoration Plan.
§ 990.56 Restoration selection—use of a Regional Restoration Plan or existing restoration project.
top
(a) General. Trustees may consider using a Regional Restoration Plan or existing restoration project where such a plan or project is determined to be the preferred alternative among a range of feasible restoration alternatives for an incident, as determined under §990.54 of this part. Such plans or projects must be capable of fulfilling OPA's intent for the trustees to restore, rehabilitate, replace, or acquire the equivalent of the injured natural resources and services and compensate for interim losses.
(b) Existing plans or projects—(1) Considerations. Trustees may select a component of a Regional Restoration Plan or an existing restoration project as the preferred alternative, provided that the plan or project:
(i) Was developed with public review and comment or is subject to public review and comment under this part;
(ii) Will adequately compensate the environment and public for injuries resulting from the incident;
(iii) Addresses, and is currently relevant to, the same or comparable natural resources and services as those identified as having been injured; and
(iv) Allows for reasonable scaling relative to the incident.
(2) Demand. (i) If the conditions of paragraph (b)(1) of this section are met, the trustees must invite the responsible parties to implement that component of the Regional Restoration Plan or existing restoration project, or advance to the trustees the trustees' reasonable estimate of the cost of implementing that component of the Regional Restoration Plan or existing restoration project.
(ii) If the conditions of paragraph (b)(1) of this section are met, but the trustees determine that the scale of the existing plan or project is greater than the scale of compensation required by the incident, trustees may only request funding from the responsible parties equivalent to the scale of the restoration determined to be appropriate for the incident of concern. Trustees may pool such partial recoveries until adequate funding is available to successfully implement the existing plan or project.
(3) Notice of Intent To Use a Regional Restoration Plan or Existing Restoration Project. If trustees intend to use an appropriate component of a Regional Restoration Plan or existing restoration project, they must prepare a Notice of Intent to Use a Regional Restoration Plan or Existing Restoration Project. Trustees must make a copy of the notice publicly available. The notice must include, at a minimum:
(i) A description of the nature, degree, and spatial and temporal extent of injuries; and
(ii) A description of the relevant component of the Regional Restoration Plan or existing restoration project; and
(iii) An explanation of how the conditions set forth in paragraph (b)(1) of this section are met.
Subpart F—Restoration Implementation Phase
top
§ 990.60 Purpose.
top
The purpose of this subpart is to provide a process for implementing restoration.
§ 990.61 Administrative record.
top
(a) Closing the administrative record for restoration planning. Within a reasonable time after the trustees have completed restoration planning, as provided in §§990.55 and 990.56 of this part, they must close the administrative record. Trustees may not add documents to the administrative record once it is closed, except where such documents:
(1) Are offered by interested parties that did not receive actual or constructive notice of the Draft Restoration Plan and the opportunity to comment on the plan;
(2) Do not duplicate information already contained in the administrative record; and
(3) Raise significant issues regarding the Final Restoration Plan.
(b) Opening an administrative record for restoration implementation. Trustees may open an administrative record for implementation of restoration, as provided in §990.45 of this part. The costs associated with the administrative record are part of the costs of restoration. Ordinarily, the administrative record for implementation of restoration should document, at a minimum, all Restoration Implementation Phase decisions, actions, and expenditures, including any modifications made to the Final Restoration Plan.
§ 990.62 Presenting a demand.
top
(a) General. After closing the administrative record for restoration planning, trustees must present a written demand to the responsible parties. Delivery of the demand should be made in a manner that establishes the date of receipt by the responsible parties.
(b) When a Final Restoration Plan has been developed. Except as provided in paragraph (c) of this section and in §990.14(c) of this part, the demand must invite the responsible parties to either:
(1) Implement the Final Restoration Plan subject to trustee oversight and reimburse the trustees for their assessment and oversight costs; or
(2) Advance to the trustees a specified sum representing all trustee direct and indirect costs of assessment and restoration, discounted as provided in §990.63(a) of this part.
(c) Regional Restoration Plan or existing restoration project. When the trustees use a Regional Restoration Plan or an existing restoration project under §990.56 of this part, the demand will invite the responsible parties to implement a component of a Regional Restoration Plan or existing restoration project, or advance the trustees' estimate of damages based on the scale of the restoration determined to be appropriate for the incident of concern, which may be the entire project or a portion thereof.
(d) Response to demand. The responsible parties must respond within ninety (90) calendar days in writing by paying or providing binding assurance they will reimburse trustees' assessment costs and implement the plan or pay assessment costs and the trustees' estimate of the costs of implementation.
(e) Additional contents of demand. The demand must also include:
(1) Identification of the incident from which the claim arises;
(2) Identification of the trustee(s) asserting the claim and a statement of the statutory basis for trusteeship;
(3) A brief description of the injuries for which the claim is being brought;
(4) An index to the administrative record;
(5) The Final Restoration Plan or Notice of Intent to Use a Regional Restoration Plan or Existing Restoration Project; and
(6) A request for reimbursement of:
(i) Reasonable assessment costs, as defined in §990.30 of this part and discounted as provided in §990.63(b) of this part;
(ii) The cost, if any, of conducting emergency restoration under §990.26 of this part, discounted as provided in §990.63(b) of this part; and
(iii) Interest on the amounts recoverable, as provided in section 1005 of OPA (33 U.S.C. 2705), which allows for prejudgment and post-judgment interest to be paid at a commercial paper rate, starting from thirty (30) calendar days from the date a demand is presented until the date the claim is paid.
(f) Cost accounting procedures. Trustees must use methods consistent with generally accepted accounting principles and the requirements of §990.27 of this part in determining past assessment and restoration costs incurred by trustees. When cost accounting for these costs, trustees must compound these costs using the guidance in §990.63(b) of this part.
(g) Cost estimating procedures. Trustees must use methods consistent with generally accepted cost estimating principles and meet the standards of §990.27 of this part in estimating future costs that will be incurred to implement a restoration plan. Trustees also must apply discounting methodologies in estimating costs using the guidance in §990.63(a) of this part.
[61 FR 500, Jan. 5, 1996, as amended at 67 FR 61493, Oct. 1, 2002]
§ 990.63 Discounting and compounding.
top
(a) Estimated future restoration costs. When determining estimated future costs of implementing a Final Restoration Plan, trustees must discount such future costs back to the date the demand is presented. Trustees may use a discount rate that represents the yield on recoveries available to trustees. The price indices used to project future inflation should reflect the major components of the restoration costs.
(b) Past assessment and emergency restoration costs. When calculating the present value of assessment and emergency restoration costs already incurred, trustees must compound the costs forward to the date the demand is presented. To perform the compounding, trustees may use the actual U.S. Treasury borrowing rate on marketable securities of comparable maturity to the period of analysis. For costs incurred by state or tribal trustees, trustees may compound using parallel state or tribal borrowing rates.
(c) Trustees are referred to Appendices B and C of OMB Circular A–94 for information about U.S. Treasury rates of various maturities and guidance in calculation procedures. Copies of Appendix C, which is regularly updated, and of the Circular are available from the OMB Publications Office (202–395–7332).
§ 990.64 Unsatisfied demands.
top
(a) If the responsible parties do not agree to the demand within ninety (90) calendar days after trustees present the demand, the trustees may either file a judicial action for damages or present the uncompensated claim for damages to the Oil Spill Liability Trust Fund, as provided in section 1012(a)(4) of OPA (33 U.S.C. 2712(a)(4)) or seek an appropriation from the Oil Spill Liability Trust Fund as provided in section 1012(a)(2) of OPA (33 U.S.C. 2712(a)(2)).
(b) Judicial actions and claims must be filed within three (3) years after the Final Restoration Plan or Notice of Intent to Use a Regional Restoration Plan or Existing Restoration Project is made publicly available, in accordance with 33 U.S.C. 2717(f)(1)(B) and 2712(h)(2).
[61 FR 500, Jan. 5, 1996, as amended at 67 FR 61493, Oct. 1, 2002]
§ 990.65 Opening an account for recovered damages.
top
(a) General. Sums recovered by trustees in satisfaction of a natural resource damage claim must be placed in a revolving trust account. Sums recovered for past assessment costs and emergency restoration costs may be used to reimburse the trustees. All other sums must be used to implement the Final Restoration Plan or all or an appropriate component of a Regional Restoration Plan or an existing restoration project.
(b) Joint trustee recoveries—(1) General. Trustees may establish a joint account for damages recovered pursuant to joint assessment activities, such as an account under the registry of the applicable federal court.
(2) Management. Trustees may develop enforceable agreements to govern management of joint accounts, including agreed-upon criteria and procedures, and personnel for authorizing expenditures out of such joint accounts.
(c) Interest-bearing accounts. Trustees may place recoveries in interest-bearing revolving trust accounts, as provided by section 1006(f) of OPA (33 U.S.C. 2706(f)). Interest earned on such accounts may only be used for restoration.
(d) Escrow accounts. Trustees may establish escrow accounts or other investment accounts.
(e) Records. Trustees must maintain appropriate accounting and reporting procedures to document expenditures from accounts established under this section.
(f) Oil Spill Liability Trust Fund. Any sums remaining in an account established under this section that are not used either to reimburse trustees for past assessment and emergency restoration costs or to implement restoration must be deposited in the Oil Spill Liability Trust Fund, as provided by section 1006(f) of OPA (33 U.S.C. 2706(f)).
§ 990.66 Additional considerations.
top
(a) Upon settlement of a claim, trustees should consider the following actions to facilitate implementation of restoration:
(1) Establish a trustee committee and/or memorandum of understanding or other agreement to coordinate among affected trustees, as provided in §990.14(a)(3) of this part;
(2) Develop more detailed workplans to implement restoration;
(3) Monitor and oversee restoration; and
(4) Evaluate restoration success and the need for corrective action.
(b) The reasonable costs of such actions are included as restoration costs.